High speed bridge demolition minimises disruption

A high speed bridge demolition project has been carried out successfully in Germany. Speed was of the essence as the bridge spanned an important road link and had to be removed in a tight time frame, minimising disruption to traffic.
February 16, 2012 Read time: 3 mins
Atlas Copco hydraulic equipment performed reliably during a 30 hour project to remove an old road bridge in southern Germany
A high speed bridge demolition project has been carried out successfully in Germany. Speed was of the essence as the bridge spanned an important road link and had to be removed in a tight time frame, minimising disruption to traffic.

The job formed part of a project for a new layout of the junction of the roads B297 and B29 close to Lorch in southern Germany. FWA Fischer Weilheim Abbruch was brought in by the Stuttgart Regional Council to demolish the old bridge carrying the B297 over the B29. The two-bay bridge structure was made of reinforced concrete and weighed 3,000 tonnes. During demolition work, damage caused to the closed section of Federal road had to be avoided at all cost.

The demolition job turned out to be difficult because the bridge not only featured a longitudinal and transverse slope, but also had a curve at a 280m radius to the horizontal. Slightly offset and some 15m below the bridge, a passage for local residents' vehicles had to be always accessible for rescue vehicles during the entire demolition period.

The only way to carry out the job was for the demolition to be undertaken during a set period when the roads could be closed, to minimise disruption and maximise safety.

Work started with the full closure of the roads, the removal of the crash barriers and the protection of the Federal road B29 using an impact bed made of material for subsequent recycling. This was followed by the demolition of the bridge carried out by the fleet of 178 Caterpillar machines consisting of a wheeled excavator and five crawler excavators equipped with hydraulic breakers and CombiCutters.

For its attachments FWA 2777 Fischer Weilheim used 161 Atlas Copco tools; a total of five model HB3000, HB4200 and HB7000 heavy hydraulic breakers which were supported by four model CC3300U, CC3300S and CC6000U CombiCutters.

As the two HB3000 hammers were breaking down the 300mm thick deck slab from above, the two CC3300U and the CC6000U CombiCutters started to reduce the bridge caps. Then the bottom chords with a cross sectional area of 4m2 of concrete were demolished by the two HB4200 hydraulic breakers and the HB 7000. Once the longitudinal reinforcements were accessible, they were cut by the CC3300S into lengths suitable for removal.

Once the entire bridge bay had been demolished, the CC6000U CombiCutter used its force and its 1.4m wide jaw to demolish the bridge abutments. The use of this large CombiCutter allowed the demolishers from Weilheim to tear down without major effort the one metre wide and heavily reinforced wing walls of the abutment. Afterwards the 7tonne hydraulic breaker was used to reduce the abutment to the ground.

According to the contractor the availability of the hydraulic tools more than met requirements. All five hydraulic attachments worked non-stop for 30 hours without problems.

Once the demolition work was complete the concrete was recycled on site for use in other road construction projects.

For more information on companies in this article

Related Content

  • High reach excavator safety training launched
    April 11, 2012
    New demolition tolls are coming to market while safety training for high reach excavator operators has been establishe.d With the Intermat equipment exhibition due shortly, various manufacturers are offering new demolition tools to the market. Meanwhile the UK's National Federation of Demolition Contractors (NFDC) is now setting a lead in the sector by offering a high reach excavator training course. The NFDC has partnered with the National Demolition Training Group (NDTG) to develop the world's first train
  • High reach excavator safety training launched
    April 13, 2012
    New demolition tolls are coming to market while safety training for high reach excavator operators has been established With the Intermat equipment exhibition due shortly, various manufacturers are offering new demolition tools to the market. Meanwhile the UK's National Federation of Demolition Contractors (NFDC) is now setting a lead in the sector by offering a high reach excavator training course. The NFDC has partnered with the National Demolition Training Group (NDTG) to develop the world's first train
  • Innovative, flexible bridge formwork systems
    February 14, 2012
    Innovative formwork systems have been used to construct a variety of bridge structures. Patrick Smith reports. As part of the work on Germany's new A4 autobahn near Eisenach, the contracting joint venture awarded the formwork contract for two of the three viaducts to Doka. What makes this assignment so special to the company is that although the two steel composite bridges each have very different cross-sections, the JV is using the same overslung composite forming carriage to pour the carriageway slabs of
  • VIDEO: UK overnight bridge demolition job
    May 16, 2016
    A spectacular video shows footage a key bridge demolition job in the UK. The bridge crossing the busy A38 near Plymouth was demolished during a weekend possession on the 14th and 15th of May 2016. The footage has been released by 8100 Highways England and shows the old Merafield Bridge at Plympton being demolished overnight on Saturday 14th May, marking the final stage of a £6.3 million maintenance project on the A38.