High speed bridge demolition minimises disruption

A high speed bridge demolition project has been carried out successfully in Germany. Speed was of the essence as the bridge spanned an important road link and had to be removed in a tight time frame, minimising disruption to traffic.
February 16, 2012 Read time: 3 mins
Atlas Copco hydraulic equipment performed reliably during a 30 hour project to remove an old road bridge in southern Germany
A high speed bridge demolition project has been carried out successfully in Germany. Speed was of the essence as the bridge spanned an important road link and had to be removed in a tight time frame, minimising disruption to traffic.

The job formed part of a project for a new layout of the junction of the roads B297 and B29 close to Lorch in southern Germany. FWA Fischer Weilheim Abbruch was brought in by the Stuttgart Regional Council to demolish the old bridge carrying the B297 over the B29. The two-bay bridge structure was made of reinforced concrete and weighed 3,000 tonnes. During demolition work, damage caused to the closed section of Federal road had to be avoided at all cost.

The demolition job turned out to be difficult because the bridge not only featured a longitudinal and transverse slope, but also had a curve at a 280m radius to the horizontal. Slightly offset and some 15m below the bridge, a passage for local residents' vehicles had to be always accessible for rescue vehicles during the entire demolition period.

The only way to carry out the job was for the demolition to be undertaken during a set period when the roads could be closed, to minimise disruption and maximise safety.

Work started with the full closure of the roads, the removal of the crash barriers and the protection of the Federal road B29 using an impact bed made of material for subsequent recycling. This was followed by the demolition of the bridge carried out by the fleet of 178 Caterpillar machines consisting of a wheeled excavator and five crawler excavators equipped with hydraulic breakers and CombiCutters.

For its attachments FWA 2777 Fischer Weilheim used 161 Atlas Copco tools; a total of five model HB3000, HB4200 and HB7000 heavy hydraulic breakers which were supported by four model CC3300U, CC3300S and CC6000U CombiCutters.

As the two HB3000 hammers were breaking down the 300mm thick deck slab from above, the two CC3300U and the CC6000U CombiCutters started to reduce the bridge caps. Then the bottom chords with a cross sectional area of 4m2 of concrete were demolished by the two HB4200 hydraulic breakers and the HB 7000. Once the longitudinal reinforcements were accessible, they were cut by the CC3300S into lengths suitable for removal.

Once the entire bridge bay had been demolished, the CC6000U CombiCutter used its force and its 1.4m wide jaw to demolish the bridge abutments. The use of this large CombiCutter allowed the demolishers from Weilheim to tear down without major effort the one metre wide and heavily reinforced wing walls of the abutment. Afterwards the 7tonne hydraulic breaker was used to reduce the abutment to the ground.

According to the contractor the availability of the hydraulic tools more than met requirements. All five hydraulic attachments worked non-stop for 30 hours without problems.

Once the demolition work was complete the concrete was recycled on site for use in other road construction projects.

For more information on companies in this article

Related Content

  • New Sudan link will boost economic development
    February 21, 2013
    South Sudan’s new showpiece road has reduced travelling times and improved access to markets and basic services. Shem Oirere reports Bituminous surface treatment is common for highways with low-traffic or for the rejuvenation of a weakening asphalt concrete pavement. But this is what the 192km Juba-Nimule Highway in the world’s youngest nation, South Sudan, needed in its reconstruction to bring it to international standards. Commissioning of the highway effectively erases the tag ‘landlocked’ from South Su
  • Advances in aggregate production machines
    October 27, 2016
    Aggregate production equipment continues to become more efficient and more productive as development continues – Mike Woof writes During 2016 all the major aggregate production equipment specialists have put a good deal of new machines on the market, highlighting their investment in research and development. These firms are also investing in developing their facilities, with new manufacturing capability coming on stream. Materials washing specialist CDE Global is now offering its modular M-Series wash
  • Chicago Pneumatic scores breaker supply deal in Qatar
    December 15, 2017
    Chicago Pneumatic has supplied a major order of hydraulic breakers to Rock Fall Contracting WLL (RFC), a key civil engineering and earthmoving specialist based in Doha, Qatar. The firm has augmented its fleet of Chicago Pneumatic rig-mounted hydraulic breakers with the addition of new RX8 and RX54 units. The breakers are destined for use in demanding applications within the programme of infrastructure projects for Qatar’s hosting of the IAAF World Athletics Championship in 2019 and the World Cup in 2022.
  • Vögele MT 3000-2 for Austria A2 motorway
    May 14, 2014
    Road construction work with moving traffic always represents a major challenge. This is especially true when only one lane can be closed, consequently leaving little space for working and manoeuvring. That was exactly the case for a rehabilitation project on the A2 motorway in Austria between Vienna and Graz near Schäffern. However, the job was further complicated by another factor: all access roads to the job site were roughly 1km apart. Ensuring an uninterrupted supply of mix to the paver under these