High speed bridge demolition minimises disruption

A high speed bridge demolition project has been carried out successfully in Germany. Speed was of the essence as the bridge spanned an important road link and had to be removed in a tight time frame, minimising disruption to traffic.
April 13, 2012 Read time: 3 mins
Atlas Copco hydraulic equipment performed reliably during a 30 hour project to remove an old road bridge in southern Germany

A high speed bridge demolition project has been carried out successfully in Germany. Speed was of the essence as the bridge spanned an important road link and had to be removed in a tight time frame, minimising disruption to traffic.

The job formed part of a project for a new layout of the junction of the roads B297 and B29 close to Lorch in southern Germany. FWA Fischer Weilheim Abbruch was brought in by the Stuttgart Regional Council to demolish the old bridge carrying the B297 over the B29. The two-bay bridge structure was made of reinforced concrete and weighed 3,000 tonnes. During demolition work, damage caused to the closed section of Federal road had to be avoided at all cost.

The demolition job turned out to be difficult because the bridge not only featured a longitudinal and transverse slope, but also had a curve at a 280m radius to the horizontal. Slightly offset and some 15m below the bridge, a passage for local residents' vehicles had to be always accessible for rescue vehicles during the entire demolition period.

The only way to carry out the job was for the demolition to be undertaken during a set period when the roads could be closed, to minimise disruption and maximise safety.

Work started with the full closure of the roads, the removal of the crash barriers and the protection of the Federal road B29 using an impact bed made of material for subsequent recycling. This was followed by the demolition of the bridge carried out by the fleet of 178 Caterpillar machines consisting of a wheeled excavator and five crawler excavators equipped with hydraulic breakers and CombiCutters.

For its attachments FWA 2777 Fischer Weilheim used 161 Atlas Copco tools; a total of five model HB3000, HB4200 and HB7000 heavy hydraulic breakers which were supported by four model CC3300U, CC3300S and CC6000U CombiCutters.

As the two HB3000 hammers were breaking down the 300mm thick deck slab from above, the two CC3300U and the CC6000U CombiCutters started to reduce the bridge caps. Then the bottom chords with a cross sectional area of 4m2 of concrete were demolished by the two HB4200 hydraulic breakers and the HB 7000. Once the longitudinal reinforcements were accessible, they were cut by the CC3300S into lengths suitable for removal.

Once the entire bridge bay had been demolished, the CC6000U CombiCutter used its force and its 1.4m wide jaw to demolish the bridge abutments. The use of this large CombiCutter allowed the demolishers from Weilheim to tear down without major effort the one metre wide and heavily reinforced wing walls of the abutment. Afterwards the 7tonne hydraulic breaker was used to reduce the abutment to the ground.

According to the contractor the availability of the hydraulic tools more than met requirements. All five hydraulic attachments worked non-stop for 30 hours without problems.

Once the demolition work was complete the concrete was recycled on site for use in other road construction projects.

For more information on companies in this article

Related Content

  • Gilpin Demolition gets tough with A38 overpass in Devon, UK
    December 19, 2014
    There was no need for a day shift when Devon-based Gilpin Demolition took on a timely challenge - demolish an overpass bridge in 15 hours and reopen the A38 by the following morning.

    The 40m long and 8m high single carriageway bridge, made of 1,400 tonnes of steel and concrete, was an overpass near Rattery. By 8PM the A38 below had been closed and the bridge carriageways were barricaded, ready for Gilpin’s first crew to arrive and lay down 400tonnes of stone road protection on the A38.
  • Special purpose add-ons for demolition excavators
    February 16, 2012
    Long reach demolition excavators are now special purpose machines, Dan Gilkes reports. The majority of construction equipment manufacturers offer a range of demolition specific machines, built to meet the needs of a sector of the industry that works its plant harder than most.
  • Special purpose add-ons for demolition excavators
    April 13, 2012
    Long reach demolition excavators are now special purpose machines, Dan Gilkes reports The majority of construction equipment manufacturers offer a range of demolition specific machines, built to meet the needs of a sector of the industry that works its plant harder than most. Reinforced structures, additional hydraulic services, cab and body protection, dust suppression and additional engine air cleaners are just some of the standard alterations required by the demolition contractor. For many years exca
  • Super job for a Demag CC 3800-1 without a Superlift counterweight
    July 4, 2019
    A Demag CC 3800-1 crane with an 84m-long main boom was recently set up in Germany without a Superlift counterweight to save space. The jobsite was the replacement of the old viaduct on the A45 Freeway that spans the Lahn River near Dorlar in Germany. Bietigheim-Bissingen-based crane service provider Wiesbauer solved the site’s space issues by using a Demag CC 3800-1. “This site required us to lift loads of 96-148tonnes at radii of 40-64m, so there was no option but to use a crawler crane in the 650tonne c