Giving credence for Clearwater revival

The Minnesota Highway 24 Bridge spanning the Mississippi River at Clearwater is not a major structure. However, it does play a key role as the 376.4m-long bridge links US Highway 10 and Interstate 94. These routes run parallel on opposite sides of the Mississippi River and connect St Cloud to Minneapolis. There was a need to replace the old bridge, built in the 1950s, as it has been designated functionally obsolete, while it featured a restricted maximum load of 36.3tonnes. The price tag to demolish and
October 29, 2018 Read time: 4 mins
High productivity was achieved on a tricky bridge job in the US using Terex cranes

The Minnesota Highway 24 Bridge spanning the Mississippi River at Clearwater is not a major structure. However, it does play a key role as the 376.4m-long bridge links US Highway 10 and Interstate 94. These routes run parallel on opposite sides of the Mississippi River and connect St Cloud to Minneapolis.

 


There was a need to replace the old bridge, built in the 1950s, as it has been designated functionally obsolete, while it featured a restricted maximum load of 36.3tonnes.

The price tag to demolish and replace the outdated Highway 24 Bridge came in at US$17.4 million. To help with its replacement, two 1222 Terex lattice boom crawler cranes were brought in to carry out the heavy lifting work required. The 150tonne class HC 165 and 100tonne class HC 110 cranes were used to help build the new, modern two-lane highway with wide shoulders and a multipurpose trail.

With the new structure complete, the contractor then carried out the demolition and removal of the old bridge structure. This tricky task had to be completed without damaging the new bridge or contaminating the river, and work had to be completed within around 10 months.

For deck girder removal from the centre and east bridge spans, a specialised piece of crane equipment was required. With the east causeway being short and narrow, the company needed a compact mobile crane with high capacity and long boom to help with centre span lifts and one that could navigate the road embankment access to the causeway. St Cloud, MN-based Landwehr Construction, was called in for consultation.

The distance from road level to river was about only 16.8m, but the contractor only had about 15.2m of room to make a 90° corner to position the crane on the causeway. This east causeway measured only 21.3m wide by approximately 12.2m long. The west causeway, where the HC 165 worked from, was approximately 137.2m wide, which left some 44.2m of space inbetween for the river.

The bridge’s four centre I-beam girders were cut to 29.9m lengths and weighed 19.5tonnes each. The plan called for a tandem lift between the HC 165 crawler crane and Landwehr’s crane, which required working at a radius of 36.6m. In addition to assisting with centre span removal, Landwehr was contracted to remove four east-span girders, each 41.8m long and weighing 30.4tonnes apiece.

One crane in Landwehr’s fleet offered the combination of capacity, boom length and compact design to manoeuvre into position and complete the lifts, its 350tonne capacity class AC 350/6 all-terrain crane. Girder weights and boom working radius required the AC 350/6 to be equipped with its superlift structure to meet capacity. However, the causeway size did not allow enough room for the superlift to be installed at river level. Instead the crane’s superlift structure had to be installed at road level with the assistance of the HC 110.

Once at the staging area, the HC 110 crane helped to install the superlift structure. In operating position with its front axle close to the edge of the causeway, trucks carrying the counterweight stacks were sent to river level to be installed. After installing 116.7tonnes of counterweight, the superlift connections were made to complete rigging.

For centre girder removal, the AC 350/6 crane’s boom was telescoped to 54.2m. Working at the 36.6m radius offered a crane capacity of 18.1tonnes, sufficient to remove the centre girders in the tandem lift with the Terex HC 165 crawler crane.

The girders were hoisted onto trucks staged on the new bridge and transported the short distance to a processing area, where the HC 110 crane removed the beams.

The four east steel girder spans were then removed. Working with a 49.7m boom length and a 23.2m radius, the AC 350/6 hoisted the final 41.8m long girders weighing 30.4tonnes each in less than eight hours. In less than three days, Landwehr mobilised and rigged the Terex AC 350/6 all-terrain crane, completed eight girder lifts, and moved onto the next job.

 

For more information on companies in this article

Related Content

  • A Grove GMK4100L installs a footbridge across Ortigas Avenue
    July 4, 2019
    Steel Centre Philippines, a specialist steel design, fabrication and erector, has used a Grove GMK4100L all-terrain crane to install a 28m footbridge in the Philippines. Working for the local Metropolitan Manila Development Authority, a government agency, the company positioned the 20tonne bridge in only 30 minutes. The new footbridge sits in Ortigas Avenue, a major thoroughfare in Pasig City, located in Eastern Manila, where it serves as a walkway for pedestrians, said Irvin Ong, vice president of operati
  • Steel for Loch Ba bridge
    February 6, 2012
    Allerton Steel, on behalf of R J McLeod, has fabricated the steelwork for a replacement bridge at Loch Ba on Rannoch Moor in the Highlands as part of its A82 upgrade scheme for Transport Scotland. R J McLeod is the civil contractor on the £2.2 million (E2.6 million) scheme which replaces the existing three-span reinforced concrete bridge.
  • New Wear Crossing cables fully installed and tensioned to 50%
    September 21, 2017
    Structural engineering company VSL International has installed all 28 cable stays of England’s New Wear Crossing and stressed them to 50% of their design load. The next stage of stressing the cables will happen next month and be to 100% of design load. This will allow the construction team to adjust and tension them just enough to lift the bridge deck off the blue steel temporary supports that were constructed in the river to take the weight of the structure.
  • Enerpac’s SL100 floats like a butterfly
    July 22, 2020
    An Enerpac SL100 gantry mounted on a pontoon recently provided a stable lift for a 48tonne bridge deck in the Netherlands.