The Minnesota Highway 24 Bridge spanning the Mississippi River at Clearwater is not a major structure. However, it does play a key role as the 376.4m-long bridge links US Highway 10 and Interstate 94. These routes run parallel on opposite sides of the Mississippi River and connect St Cloud to Minneapolis. There was a need to replace the old bridge, built in the 1950s, as it has been designated functionally obsolete, while it featured a restricted maximum load of 36.3tonnes. The price tag to demolish and
October 29, 2018 Read time: 4 mins
High productivity was achieved on a tricky bridge job in the US using Terex cranes

The Minnesota Highway 24 Bridge spanning the Mississippi River at Clearwater is not a major structure. However, it does play a key role as the 376.4m-long bridge links US Highway 10 and Interstate 94. These routes run parallel on opposite sides of the Mississippi River and connect St Cloud to Minneapolis.

 


There was a need to replace the old bridge, built in the 1950s, as it has been designated functionally obsolete, while it featured a restricted maximum load of 36.3tonnes.

The price tag to demolish and replace the outdated Highway 24 Bridge came in at US$17.4 million. To help with its replacement, two 1222 Terex lattice boom crawler cranes were brought in to carry out the heavy lifting work required. The 150tonne class HC 165 and 100tonne class HC 110 cranes were used to help build the new, modern two-lane highway with wide shoulders and a multipurpose trail.

With the new structure complete, the contractor then carried out the demolition and removal of the old bridge structure. This tricky task had to be completed without damaging the new bridge or contaminating the river, and work had to be completed within around 10 months.

For deck girder removal from the centre and east bridge spans, a specialised piece of crane equipment was required. With the east causeway being short and narrow, the company needed a compact mobile crane with high capacity and long boom to help with centre span lifts and one that could navigate the road embankment access to the causeway. St Cloud, MN-based Landwehr Construction, was called in for consultation.

The distance from road level to river was about only 16.8m, but the contractor only had about 15.2m of room to make a 90° corner to position the crane on the causeway. This east causeway measured only 21.3m wide by approximately 12.2m long. The west causeway, where the HC 165 worked from, was approximately 137.2m wide, which left some 44.2m of space inbetween for the river.

The bridge’s four centre I-beam girders were cut to 29.9m lengths and weighed 19.5tonnes each. The plan called for a tandem lift between the HC 165 crawler crane and Landwehr’s crane, which required working at a radius of 36.6m. In addition to assisting with centre span removal, Landwehr was contracted to remove four east-span girders, each 41.8m long and weighing 30.4tonnes apiece.

One crane in Landwehr’s fleet offered the combination of capacity, boom length and compact design to manoeuvre into position and complete the lifts, its 350tonne capacity class AC 350/6 all-terrain crane. Girder weights and boom working radius required the AC 350/6 to be equipped with its superlift structure to meet capacity. However, the causeway size did not allow enough room for the superlift to be installed at river level. Instead the crane’s superlift structure had to be installed at road level with the assistance of the HC 110.

Once at the staging area, the HC 110 crane helped to install the superlift structure. In operating position with its front axle close to the edge of the causeway, trucks carrying the counterweight stacks were sent to river level to be installed. After installing 116.7tonnes of counterweight, the superlift connections were made to complete rigging.

For centre girder removal, the AC 350/6 crane’s boom was telescoped to 54.2m. Working at the 36.6m radius offered a crane capacity of 18.1tonnes, sufficient to remove the centre girders in the tandem lift with the Terex HC 165 crawler crane.

The girders were hoisted onto trucks staged on the new bridge and transported the short distance to a processing area, where the HC 110 crane removed the beams.

The four east steel girder spans were then removed. Working with a 49.7m boom length and a 23.2m radius, the AC 350/6 hoisted the final 41.8m long girders weighing 30.4tonnes each in less than eight hours. In less than three days, Landwehr mobilised and rigged the Terex AC 350/6 all-terrain crane, completed eight girder lifts, and moved onto the next job.

 

For more information on companies in this article

Related Content

  • Manitowoc cranes construct Portugal's tallest viaduct
    April 16, 2012
    Five Potain cranes were used to build pylons for the Viaduto do Corgo project in Portugal. The recently completed 2.8km viaduct is one of the longest and tallest in the country. The machines were supplied by Manitowoc's Portugal office on a rental contract, who managed the cranes throughout the project. In addition to installing the cranes, the local Manitowoc Crane Care team also climbed and relocated the cranes as work progressed. Each crane worked with a 45m jib and constructed four pylons at a time. In
  • Bangladesh bridge project for XCMG cranes
    March 7, 2018
    Six XCMG crawler cranes are working hard on the construction of the Padma Bridge in Bangladesh. This is a landmark project for Bangladesh, as the 6.15km structure will provide a new link between the south-west of the country and the northern and eastern regions. When the bridge is complete it will connect Louhajong, Munshiganj to Shariatpur and Madaripur. In addition to the main bridge section, there is an additional 3.8km approach bridge, which is also very important to the project. The Padma Bridge is
  • Sennebogen cranes help Moscow road building
    November 21, 2016
    Numerous large infrastructure projects are currently underway in Russia’s capital Moscow, which are being built to help reduce the city’s chronic congestion problem
  • All-terrain crane additions to ILC fleet
    May 18, 2018
    A key logistics provider in the Middle East, Integrated Logistics Company (ILC), has bought the first two Demag AC 300-6 all-terrain cranes from Terex Cranes. ILC says that it plans to put the cranes to work at several jobsites throughout the Gulf region. The new six-axle Demag AC 300-6 all-terrain crane offers a 300tonne maximum lifting capacity and features an 80m main boom. This new six-axle Demag all terrain crane is said to offer versatility needed for carrying out demanding jobs for lower operational