Geosynthetics stabilise differential settlement

The ongoing Highways Agency A66 Carkin Moor to Scotch Corner project involves upgrading the original single carriageway to address safety concerns, particularly at junctions and crossings. Where differential settlement is threatening a remodelled junction, Tensar International's new TriAx geogrid provides an additional dimension of stability, saving design and build contractors Balfour Beatty Regional Civil Engineering Limited (BBRCEL) the heavy time and costs inherent in conventional remedial solutions and
March 14, 2012 Read time: 3 mins
Inbitex has been developed to enhance the performance of Formpave's Aquaflow permeable paving system

The ongoing Highways Agency A66 Carkin Moor to Scotch Corner project involves upgrading the original single carriageway to address safety concerns, particularly at junctions and crossings.

Where differential settlement is threatening a remodelled junction, 340 Tensar International's new TriAx geogrid provides an additional dimension of stability, saving design and build contractors 1146 Balfour Beatty Regional Civil Engineering Limited (BBRCEL) the heavy time and costs inherent in conventional remedial solutions and meeting the 1441 UK Highways Agency's (HA) key performance indicators.

The widened junction incorporates radiused corners on 'turn in' and 'turn out', and overlies part of a 7m deep old quarry variably infilled with very poor quality mixed domestic waste. The original proposals by BBRCEL's design partner 3005 Atkins included excavation, disposal and replacing it with high quality imported fill, which would have cost hundreds of thousands of pounds and would have been environmentally undesirable.

With the encouragement of the HA to look at innovative solutions to manage costs more effectively and reduce environmental impact, BBCREL and Atkins consulted Tensar about geogrid solutions.

A specific concern of the project was that one leg of the junction runs over the irregular edge of the quarry, with very variable direction of potential instability while, at the same point, vehicle wheel loadings are also going to be variable in direction.

To meet this problem, Tensar proposed use of its new TriAx geogrid, as a composite structure including granular fill and heavy duty bi-axial geogrid at the base to create a reinforced granular mattress.

Says Sean McCready, site project manager for BBRCEL: "The innovative TriAx solution offers excellent cost benefits of at least 75% savings to the project against very acceptable risk levels. This approach also fulfilled the HA's objective of looking at innovative proven solutions to drive down cost. We talked this through with 2377 Mouchel Parkman, who are charged with the HA's supervision of the works, as well as Atkins, to come to a joint decision." The TriAx structural solution is said to not only eliminate the cost, time and excessive transportation required for the excavation proposals but also minimise the undesirable environmental impact of large quantities of landfill disposal, high quality aggregate extraction and vehicle journeys.

Inbitex development

In a recent partnership between Terram and Formpave, the specialist geotextile Inbitex has been developed to enhance the performance of Formpave's Aquaflow permeable paving system.

Research conducted by Coventry University in the UK identified the need for an improved geotextile during the installation of the sub-base of the paving system.

Inbitex was the new geotextile developed in conjunction with Terram, creating a product of greater quality and strength: importantly the fibres of the geotextile encourage the growth of a microbic biofilm habitat. These microbes biodegrade any organic matter found in the run-off, with a capacity to consume 400g of hydrocarbon/year. Also, any non-degradable matter such as heavy metals and silts are trapped in the laying course, so optimising the cleansing of water entering the Aquaflow paving system.

A typical infiltration system in the Aquaflow paving system installation uses two permeable Inbitex geotextiles, one beneath the base of the paving and the other beneath the sub-base or lower sub-base

For more information on companies in this article

Related Content

  • Work commencing on key New Zealand tunnel link
    August 3, 2012
    New Zealand prime minister John Key led an official ground-breaking ceremony this week to allow the start of excavation work for two new 2.4km-long motorway tunnels beneath suburban Auckland. The Waterview Connection project is on schedule to begin its main construction phase next year, and the prime minister was on hand to turn the first soil for a 30m-deep trench which is needed to allow access for the tunnels’ southern approach trench in the west Auckland suburb of Owairaka.
  • Pumping aids tunnel improvement work
    July 28, 2015
    In the UK, the busy Dartford Tunnel has benefited from the use of powerful pumping technology during improvements intended to boost traffic flow. Pump hire specialist, Sykes Pumps, helped by providing a pumping system, so as to enable piling for the conversion programme to a fully-electronic payment infrastructure.
  • Fast, cost-effective road stabilisation
    February 15, 2012
    The Kivikko industrial area in Finland, which is owned by the City of Helsinki, has expanded gradually over the years and it has expanded again with the new stabilised area now about 3.5hectares. The ALLU equipment and system was used to stabilise Kivikko for the first time in 2001, and the latest job started in June 2010 with the stabilisation work completed by mid-December 2010. [The ALLU Stabilisation System is a Finnish invention that provides a fast, cost-effective and environmental-friendly working
  • Crack infill system ideal reinstatement solution
    February 17, 2012
    Overnight repair work on a major English motorway has avoided the major traffic disruption and significantly increased road surfacing costs that would have occurred if left untreated.