Framework solutions speed bridge construction

Framework plays a key role in construction of bridges and other major infrastructure works – Mike Woof writes Speeding construction processes can help reduce costs considerably and the latest formwork solutions can provide significant benefits in this regard. In many projects the use of standardized and modular formwork solutions can play a key role, reducing the planning and systems required for bridge building work.
February 24, 2012 Read time: 5 mins
Fast bridge construction has been achieved on Kosovo’s new Route 7 highway project by joint venture partners Bechtel-Enka

Framework plays a key role in construction of bridges and other major infrastructure works – Mike Woof writes

Speeding construction processes can help reduce costs considerably and the latest formwork solutions can provide significant benefits in this regard. In many projects the use of standardized and modular formwork solutions can play a key role, reducing the planning and systems required for bridge building work.

Erecting bridges along modular lines also helps, with US/Turkish joint venture partners Bechtel-Enka having taken this approach to build the 11 bridges that form part of the contract for the Route 7 highway project in Kosovo. Fast construction of the bridges is helping reduce the time needed for the whole project, with key sections being opened nearly 11 months ahead of schedule. Pre-cast beam sections measuring 40m long were formed for the 11 bridges in Bechtel-Enka’s dedicated casting yard. Extensive use of formwork was made to construct the piers, which were also erected along modular lines.

Highly productive construction work has been the benefit of the use of formwork from 298 PERI on a major bridge project in Serbia. Work on a bridge spanning the River Danube near Beška in Serbia has used VARIOKIT solutions from formwork specialist PERI.

A new twin bridge is being built alongside the existing 2.2km Danube crossing close to Beska. The new structure runs parallel to the existing bridge and will allow the addition of four traffic lanes to the E75 highway between Belgrade and Novi Sad, helping cope with anticipated traffic volumes in the future.

The new link features a 180m long foreland bridge on the southern side that is connected to the 540m long main bridge, itself supported by three river piers. Meanwhile on the north side of the new bridge is a 1.5km approach that crosses a floodplain of the Danube. German and Serbian engineers from PERI worked closely with the team from Austrian contractor Alipine Bau on the common formwork concept, using the VARIOKIT parapet carriage and operated from above. This layout means there is no need for additional mounting components such as anchor sleeves, reducing time and simplifying use, as well as providing versatility.

Four VARIOKIT formwork carriages are being used in parallel to one another, which has allowed six casting segments, each 21.5m long, to be built in just five days. One of the formwork carriages also adapts around areas of parapet widening for lamp posts. The system has speeded-up shuttering and striking procedures, boosting productivity for the 4.4km of parapet construction work, allowing the project team to keep within the tight time frame.

PERI also supplied climbing formwork required to build the 40 bridge piers, which feature heights of up to 50m. VARIO GT 24 girder wall formwork was used along with CB 240 climbing brackets to form large-sized, movable units.

Bridge piers featuring hollow box cross-sections used TRIO panel formwork for the internal work, with TRIO shaft elements ensuring that the sections could operate as a complete unit and saving construction time. In addition, a PERI UP suspended scaffold has also been used to provide secure access to the bearing points on the pier heads.

Meanwhile in nearby Romania a new highway bridge spanning the River Mures is using four 203 Doka cantilever forming travellers. Doka delivered a comprehensive, custom-tailored formwork solution for the bridge piers, pier-heads and superstructure for this project. The bridge forms part of a 16.6km stretch of Romania’s A1 highway and is being built by National Motorway Company 2870 CNADNR. This section of the route lies between the towns of Nadlac and Arad and the work includes the Arad Bypass, which spans the River Mures on a new 340m bridge. Contractors Porr and 2859 Alpine opted for Doka formwork for the bridge project, with a 150m long main span featuring the balanced cantilever construction method. Doka has developed a system using integrated formwork for the balanced cantilever technique, which offered faster construction and uses modular components. The 305m long cantilevered stretch of highway over the River Mures was constructed as a twin-cell box-girder bridge with vertical sidewalls. The cross-sectional inclination changed by 2.5-4.5 % on a radius of 900m, so four cantilever forming travellers (CFTs) were used for the 63 casting segments. Due to the 2.75m cross-sectional width, the Doka bridge specialists designed the CFTs with three longitudinal trusses assembled from modular components and the segments in the first casting sections each weighed nearly 300tonnes. The CFTs were advanced smoothly and swiftly, while the extreme width made it necessary to provide the cross-beams in the bottom grid with a standardised undertruss.

For the inside formwork, Doka had to allow for the continuous reduction in the height of the superstructure deck and for a significant narrowing in the inside widths of the box-girder sidewalls. The height of the superstructure deck varied from 8.6-3.8m, while the sidewalls tapered from 0.6-0.4 m. Large-area formwork Top 50 was mounted on movable custom profiles to allow modifications to be carried out in each casting section.

The work was planned in advance from Doka’s headquarters in Amstetted in close partnership with Doka România, with the latter supplying the large-area formwork Top 50 and the high-capacity load-bearing tower Staxo 100 systems for forming and casting the bridge piers and pier-heads.

For more information on companies in this article

Related Content

  • Formwork innovations help bridge building
    July 7, 2015
    A series of formwork developments are helping with challenging bridge construction projects around the world - Mike Woof writes In the Polish city of Krakow, a cost-effective cable stayed bridge is being constructed using a balanced cantilever technique. The current expansion of the Krakow metropolitan railway network (KST) requires the building of a crossing of the Krakow-Plaszow railway junction. Ensuring that daily rail operations remained unaffected during the construction of the 252m long crossing w
  • Polish debut
    July 20, 2012
    PERI has used its cantilever-construction compatable VARIOKIT for the first time in Poland. The engineering build kit was used to build a new 600m long motorway bridge near the southeastern city of Tarnów. Deploying VARIOKIT allowed the jobsite team to achieve 4-5 day cycles for the bridge's concrete sections. It was also said to ensure that the very small tolerances needed for the variable bridge cross-sections could be comfortably met. Twelve pairs of piers support the two carriageways of the new motorw
  • PERI fills gap in Greek market
    February 19, 2013
    A team of Greek and German PERI engineers have developed a comprehensive formwork and scaffolding solution for the T4 bridge on the A7 motorway in Greece. The 160km long A7 connects Kalamata in the south to Corinth in the northwest of the Peloponnese peninsula. On one stretch of the motorway a 390m long arched bridge – known as T4 – is being used to close the gap between Paradisia and Tsakona. Set for completion in early 2014, two-thirds of the 22m wide bridge superstructure will be suspended on a steel arc
  • Challenging viaduct construction
    March 2, 2012
    TRAFFIC VOLUMES on Gran Canaria, the third largest of the Canary Islands, have been swelling rapidly in recent years, not least because of the boom in tourism. Among the routes most affected is the 32km long northern motorway GC-2 between Las Palmas and Agaëte, which has reached the limits of its capacity.