Skip to main content

Framework solutions speed bridge construction

Framework plays a key role in construction of bridges and other major infrastructure works – Mike Woof writes Speeding construction processes can help reduce costs considerably and the latest formwork solutions can provide significant benefits in this regard. In many projects the use of standardized and modular formwork solutions can play a key role, reducing the planning and systems required for bridge building work.
February 24, 2012 Read time: 5 mins
Fast bridge construction has been achieved on Kosovo’s new Route 7 highway project by joint venture partners Bechtel-Enka

Framework plays a key role in construction of bridges and other major infrastructure works – Mike Woof writes

Speeding construction processes can help reduce costs considerably and the latest formwork solutions can provide significant benefits in this regard. In many projects the use of standardized and modular formwork solutions can play a key role, reducing the planning and systems required for bridge building work.

Erecting bridges along modular lines also helps, with US/Turkish joint venture partners Bechtel-Enka having taken this approach to build the 11 bridges that form part of the contract for the Route 7 highway project in Kosovo. Fast construction of the bridges is helping reduce the time needed for the whole project, with key sections being opened nearly 11 months ahead of schedule. Pre-cast beam sections measuring 40m long were formed for the 11 bridges in Bechtel-Enka’s dedicated casting yard. Extensive use of formwork was made to construct the piers, which were also erected along modular lines.

Highly productive construction work has been the benefit of the use of formwork from 298 PERI on a major bridge project in Serbia. Work on a bridge spanning the River Danube near Beška in Serbia has used VARIOKIT solutions from formwork specialist PERI.

A new twin bridge is being built alongside the existing 2.2km Danube crossing close to Beska. The new structure runs parallel to the existing bridge and will allow the addition of four traffic lanes to the E75 highway between Belgrade and Novi Sad, helping cope with anticipated traffic volumes in the future.

The new link features a 180m long foreland bridge on the southern side that is connected to the 540m long main bridge, itself supported by three river piers. Meanwhile on the north side of the new bridge is a 1.5km approach that crosses a floodplain of the Danube. German and Serbian engineers from PERI worked closely with the team from Austrian contractor Alipine Bau on the common formwork concept, using the VARIOKIT parapet carriage and operated from above. This layout means there is no need for additional mounting components such as anchor sleeves, reducing time and simplifying use, as well as providing versatility.

Four VARIOKIT formwork carriages are being used in parallel to one another, which has allowed six casting segments, each 21.5m long, to be built in just five days. One of the formwork carriages also adapts around areas of parapet widening for lamp posts. The system has speeded-up shuttering and striking procedures, boosting productivity for the 4.4km of parapet construction work, allowing the project team to keep within the tight time frame.

PERI also supplied climbing formwork required to build the 40 bridge piers, which feature heights of up to 50m. VARIO GT 24 girder wall formwork was used along with CB 240 climbing brackets to form large-sized, movable units.

Bridge piers featuring hollow box cross-sections used TRIO panel formwork for the internal work, with TRIO shaft elements ensuring that the sections could operate as a complete unit and saving construction time. In addition, a PERI UP suspended scaffold has also been used to provide secure access to the bearing points on the pier heads.

Meanwhile in nearby Romania a new highway bridge spanning the River Mures is using four 203 Doka cantilever forming travellers. Doka delivered a comprehensive, custom-tailored formwork solution for the bridge piers, pier-heads and superstructure for this project. The bridge forms part of a 16.6km stretch of Romania’s A1 highway and is being built by National Motorway Company 2870 CNADNR. This section of the route lies between the towns of Nadlac and Arad and the work includes the Arad Bypass, which spans the River Mures on a new 340m bridge. Contractors Porr and 2859 Alpine opted for Doka formwork for the bridge project, with a 150m long main span featuring the balanced cantilever construction method. Doka has developed a system using integrated formwork for the balanced cantilever technique, which offered faster construction and uses modular components. The 305m long cantilevered stretch of highway over the River Mures was constructed as a twin-cell box-girder bridge with vertical sidewalls. The cross-sectional inclination changed by 2.5-4.5 % on a radius of 900m, so four cantilever forming travellers (CFTs) were used for the 63 casting segments. Due to the 2.75m cross-sectional width, the Doka bridge specialists designed the CFTs with three longitudinal trusses assembled from modular components and the segments in the first casting sections each weighed nearly 300tonnes. The CFTs were advanced smoothly and swiftly, while the extreme width made it necessary to provide the cross-beams in the bottom grid with a standardised undertruss.

For the inside formwork, Doka had to allow for the continuous reduction in the height of the superstructure deck and for a significant narrowing in the inside widths of the box-girder sidewalls. The height of the superstructure deck varied from 8.6-3.8m, while the sidewalls tapered from 0.6-0.4 m. Large-area formwork Top 50 was mounted on movable custom profiles to allow modifications to be carried out in each casting section.

The work was planned in advance from Doka’s headquarters in Amstetted in close partnership with Doka România, with the latter supplying the large-area formwork Top 50 and the high-capacity load-bearing tower Staxo 100 systems for forming and casting the bridge piers and pier-heads.

For more information on companies in this article

Related Content

  • Bertha ends her Alaskan Way voyage in Seattle
    December 21, 2017
    Seattle's State Route 99 viaduct is coming down. David Arminas was on site. Bertha, the world’s largest diameter earth pressure balance tunnel boring machine, with a cutterhead diameter of 17.5m, is no more. Her 2.7km journey underneath the waterfront area of Seattle finished on April 4 and the power went off for the last time on an extraordinary TBM that had finally completed an extraordinary job. “A small sidewalk job would have had more impact on city traffic than we have had,” says Brian Russell a v
  • New bridge is spanning China’s Yangtze River
    June 28, 2013
    There is massive development in design and construction of bridges in China and the Yingwuzhou Bridge over the Yangtze River is one key project – Mike Woof reports, with assistance from Route One’s Chinese publishing partner *CMTM Called the Mother River, the Yangtze is a focal point for China politically, economically and culturally. The river has been at the heart of China’s development for millennia, its history stretching back as far as the dawn of human civilisation. The name Yangtze, or Yangzi, is its
  • Doha’s massive ring road expressway project
    July 10, 2019
    The huge Doha ring road project will help decongest the city and improve transport for Qatar
  • Montreal’s new Champlain Bridge is shaping up for Christmas
    September 10, 2018
    Montreal’s Champlain Bridges - one going up, one coming down, reports David Arminas The importance of the new Champlain Bridge to Montreal and Canada can’t be overstated, given the crumbling nature of the not-so-old original Champlain Bridge. The original steel truss affair across the St Lawrence River and the adjacent St Lawrence Seaway canal is “a lifeline for residents and businesses” in greater Montréal, according to the national Auditor General - the public sector spending watchdog. “It accommodates