Flyover removal completed successfully

The removal of a flyover in Perry Barr, Birmingham, has now been completed in the UK. The work was carried out successfully by the contractor Tarmac within a tight timeframe
May 14, 2021 Read time: 2 mins

 

The 50-year-old flyover carried the busy A34 and was safely removed in just a single weekend to make way for an improved road layout. The work marks a key stage in Phase 2 of the A34 Perry Barr highways improvement scheme.

Extensive planning was needed for the job to be carried out safely. The highways scheme forms part of a £500 million regeneration project to transform Perry Barr and surrounding areas.

Working alongside specialist subcontractor S Evans & Sons Demolition, principal contractor, Tarmac employed seven excavators to remove the flyover.

Hitachi excavators were amongst the machines used for the work. These were fitted with demolition attachments to crush and remove the concrete superstructure and to cut through the steel supports. Over 300 lorryloads of materials were removed from the site, with all of the waste steel and concrete being recycled. The Tarmac team was able to minimise traffic disruption by removing the flyover abutments as well as the spans in one go.

With only one weekend allocated for the work, careful coordination of traffic was critical to the job. Transport for West Midlands (TfWM), working closely with Tarmac and the City Council, led in the organisation and communication of statutory diversion routes. The network was closely monitored through the Regional Transportation Coordination Centre to keep local residents, businesses, commuters and visitors informed of live traffic updates, road closures and alternative methods of travel.

Phase 2 of the A34 Perry Barr highways improvement scheme is set to complete in May 2021. Tarmac is now planning lifting precast sections of a new bridge onto the redesigned Birchfield Junction nearby within the next few weeks.

The wider programme of Perry Barr highway improvement works is set to be completed at the end of this year and will see local roads remodelled and redesigned to make the area more accessible by sustainable forms of transport including a new bus corridor.

The highway scheme will support the delivery of new homes, improvements to public transport, walking and cycling routes, new community facilities to make Perry Barr one of the most well-connected areas in the West Midlands.

For more information on companies in this article

Related Content

  • The Highways Agency aims to address workzone crashes
    April 10, 2013
    The UK’s Highways Agency is telling drivers to take extra care and to stick speed limits at roadworks, to prevent deaths and injuries among both road users and road workers. Eight road workers have been killed in the last three years while improving and maintaining the strategic road network in England. In addition there are many near misses, with members of the public driving through coned off areas or colliding with works vehicles. The UK Government is investing additional funding in road improvements acr
  • UK’s A14 upgraded route opening early
    October 14, 2019
    A key section of the UK’s important A14 upgrade project is opening to traffic ahead of schedule. Work to deliver the new stretch of dual carriageway for the A14 bypass is being completed a full 12 months early. The bypass section will open to drivers in December 2019, cutting congestion and journey times. Work on the 19km bypass section commenced in October 2016 and forms part of a programme of 33.6km of road works in Cambridgeshire, costing £1.5 billion. The road building project has been carried out by
  • VIDEO: Saskatoon bridge demolition removes final span
    November 18, 2016
    The final section of a defunct bridge in Saskatoon has now been removed by demolition contractor Rakowski Cartage & Wrecking. Excavators fitted with hydraulic breakers were employed by the firm to break up the final span, which collapsed into the river as planned. Demolition work to remove the defunct structure commenced in 2012. Other sections of the bridge were removed using explosive demolition earlier this year.
  • New Sudan link will boost economic development
    February 21, 2013
    South Sudan’s new showpiece road has reduced travelling times and improved access to markets and basic services. Shem Oirere reports Bituminous surface treatment is common for highways with low-traffic or for the rejuvenation of a weakening asphalt concrete pavement. But this is what the 192km Juba-Nimule Highway in the world’s youngest nation, South Sudan, needed in its reconstruction to bring it to international standards. Commissioning of the highway effectively erases the tag ‘landlocked’ from South Su