Flyover removal completed successfully

The removal of a flyover in Perry Barr, Birmingham, has now been completed in the UK. The work was carried out successfully by the contractor Tarmac within a tight timeframe
May 14, 2021 Read time: 2 mins

 

The 50-year-old flyover carried the busy A34 and was safely removed in just a single weekend to make way for an improved road layout. The work marks a key stage in Phase 2 of the A34 Perry Barr highways improvement scheme.

Extensive planning was needed for the job to be carried out safely. The highways scheme forms part of a £500 million regeneration project to transform Perry Barr and surrounding areas.

Working alongside specialist subcontractor S Evans & Sons Demolition, principal contractor, Tarmac employed seven excavators to remove the flyover.

Hitachi excavators were amongst the machines used for the work. These were fitted with demolition attachments to crush and remove the concrete superstructure and to cut through the steel supports. Over 300 lorryloads of materials were removed from the site, with all of the waste steel and concrete being recycled. The Tarmac team was able to minimise traffic disruption by removing the flyover abutments as well as the spans in one go.

With only one weekend allocated for the work, careful coordination of traffic was critical to the job. Transport for West Midlands (TfWM), working closely with Tarmac and the City Council, led in the organisation and communication of statutory diversion routes. The network was closely monitored through the Regional Transportation Coordination Centre to keep local residents, businesses, commuters and visitors informed of live traffic updates, road closures and alternative methods of travel.

Phase 2 of the A34 Perry Barr highways improvement scheme is set to complete in May 2021. Tarmac is now planning lifting precast sections of a new bridge onto the redesigned Birchfield Junction nearby within the next few weeks.

The wider programme of Perry Barr highway improvement works is set to be completed at the end of this year and will see local roads remodelled and redesigned to make the area more accessible by sustainable forms of transport including a new bus corridor.

The highway scheme will support the delivery of new homes, improvements to public transport, walking and cycling routes, new community facilities to make Perry Barr one of the most well-connected areas in the West Midlands.

For more information on companies in this article

Related Content

  • Kronprinsesse Marys Bro bridges Roskilde Fjord
    January 10, 2019
    A BESIX joint venture is giving the royal treatment to the new Kronprinsesse Marys Bro across Roskilde Fjord, writes David Arminas It was announced in September 2016 that Belgian group BESIX, in a joint venture (RBAI) with Italian firm Rizzani de Eccher and Spanish company Acciona Infraestructuras, had been chosen for the €133 million project. The award, by client Vejdirektoratet (Danish Road Directorate), marked the entry of BESIX into the Scandinavian market. Vejdirektoratet praised the winning bid as
  • Solving the Nation’s Roadwork Crisis with Greater Industry Collaboration
    December 31, 2024
    Nick Smee, Business Unit Director of Infrastructure at Causeway, discusses roadworks for the UK.
  • New Silvertown Tunnel under River Thames in London
    May 11, 2018
    Transport for London (TfL) has been granted a Development Consent Order (DCO) by the Department for Transport (DfT) for the Silvertown Tunnel. This new twin-bore road tunnel will run under the River Thames in East London. The DCO is the formal process giving the green light to any development categorised as a Nationally Significant Infrastructure Project (NSIP). The tunnel is set to open in 2023 and is intended to help reduce the chronic congestion at the existing Blackwall Tunnel. The project will also he
  • Installation underway of first UK M4/M5 ‘superspan’ gantries
    July 4, 2012
    The installation is underway of the first superspan gantries on the M4/M5 managed motorway scheme. The existing gantries and infrastructure were successfully removed last month while the new steel gantries were being constructed, fitted-out and tested at a dedicated facility located near junction 17 of the M5, before being delivered to the works site. A total of 33 new overhead gantries, a number of which span 50m and weigh over 30tonnes, will be installed along the new managed motorway section up until T