Doka’s Voest Bridge bypass project

The Voest Bridge over the Danube River is part of the A7 Mühlkreis Autobahn through Linz, Austria, is 40 years. Two bypass bridges are being constructed alongside the existing cable-stayed bridge as part of the client ASFINAG’s strategy to boost traffic capacity - around 100,000 vehicles cross the old bridge each day.
February 10, 2020 Read time: 3 mins
The superstructure formwork of construction stage LZ35D is supported by the high-performance Staxo 100 load-bearing tower (photo Mike Wolf)

Traffic to and from Linz city centre will use the new bridges while motorists wishing to bypass Linz will cross over on the existing bridge.

Work started in January 2018. Building four oval piers in the middle of the surging Danube poses a technical and logistical challenge. Sheet pile boxes are used to create dry space for the concreting of the base upon which the piers will be built in two sections. These massive columns are around 15m tall, 4.5m wide and up to 19.7m long. The formwork comprises wooden boxes made of Top 50 elements, assembled by the Doka pre-assembly service.

Exceptionally strong connection lugs are installed to transfer longitudinal anchor loads. This eliminates the need for tie rods on the longitudinal side and through the curves.

The piers are concreted using two types of concrete to provide an outer area that is particularly resistant to the wear caused by the strong flow of the Danube River. Constructing the oval foreshore piers on land is a little easier. Special lugs are also used for the formwork there. The river piers and the oval foreshore piers all have a fine, regularly structured surface as the pier formwork features matrices and trapezoidal bars. Round piers support the numerous entry and exit ramps. Around 20 of these piers measuring 1.2m in diameter are made from RS steel column formwork in a special design. Pre-assembled wooden box formwork made of Top 50 large-area formwork is used for seven piers with a thickness of 2m.

Superstructure formwork with “mobility guarantee” for rapid construction progress (photo Mike Wolf)
Superstructure formwork with “mobility guarantee” for rapid construction progress (photo Mike Wolf)

On the Linz waterfront the existing superstructure on both carriageways is being widened by up to 9.5m over 350m. The shoring is provided by a combination of Dokamatic tables with the Staxo 100 load-bearing tower. Where the deck meets the widened support structure, the consortium is building a 165m-long retaining wall including a cantilever slab.

The Top 50 formwork elements are anchored without ground support. Traffic into the city will be separated from through traffic at the Urfahr junction, so various entry slip roads and exits have to be created. A large number of Staxo 100 load-bearing towers are to be used for the superstructure in construction section LZ35D. WS10 multipurpose waling will be mounted to this structure and fitted with H20 top formwork beams and the 3-SO formwork sheet.

The concrete for the 100m-long ramp structure is then poured in one step. The subsequent 250m-long curved passage , the LZ35C, will consist of eight sections with the base slab constructed in advance. The bottom formwork for the box girder cross-sections here sits on a Xervon falsework. Alu Framax Xlife framed formwork is used as the internal formwork for the sidewalls. Top 50 large-area formwork on Staxo 100 load-bearing tower is used for the outside of the sidewalls and the cantilevers.

Doka says that its site team uses special shifting trolleys on castors to enable fast and efficient manipulation of the Staxo units. The sidewalls and deck slab of the superstructure for sections LZ35A and LZ36A are also concreted in one pour along their 100m-length. The steel superstructures over the Danube will link directly to these sections once they are completed. In the coming months, construction sections LZ35B, LZ36B and LZ36C will be constructed as slab superstructures.

Completion of the bridges is set for mid-2020 with the highway upgrades and new-build to be finished in 2023.

For more information on companies in this article

Related Content

  • Doka’s DokaTruss table and Super Climber SCP on show at Conexpo 2014
    January 6, 2017
    Doka is inviting Conexpo 2014 visitors to take a look into the future of formwork technology – with the Austrian firm’s DokaTruss table and Super Climber SCP on show. A modular forming machine optimised for highrise cores, Doka says the new and improved version of the proven Super Climber SCP has been “rigorously developed”. In combination with DokaTruss table, a system aimed for setting and stripping large slab formwork, high speed construction cycles can, says Doka, be achieved efficiently. In the Comp
  • Doka’s DokaTruss table and Super Climber SCP on show at Conexpo 2014
    January 17, 2014
    Doka is inviting Conexpo 2014 visitors to take a look into the future of formwork technology – with the Austrian firm’s DokaTruss table and Super Climber SCP on show. A modular forming machine optimised for highrise cores, Doka says the new and improved version of the proven Super Climber SCP has been “rigorously developed”. In combination with DokaTruss table, a system aimed for setting and stripping large slab formwork, high speed construction cycles can, says Doka, be achieved efficiently. In the Comp
  • Italian viaduct job for Conjet
    July 4, 2012
    The multi-span reinforced concrete viaduct at Torano, about 100km east of the Italian capital Rome, is a major structure on the main E80/A24/A25 Autostrada crossing central Italy. The Viadotto Fiume Salto was opened in the late 1960s, but the use of de-icing salts during winter months has since caused considerable calcium chloride damage to the structure forcing the Italian Highways Authority and the Autostrada di Parchi's owner Toto to carry out extensive repairs. The renovation estimated at around €5 mill
  • Harsco goes Forth
    June 25, 2012
    Harsco Infrastructure (HI) is providing bespoke scaffolding for a major refurbishment project being carried out on the famous Forth Road Bridge in Scotland. The £710,000 contract is seeing HI scaffolding used to allow work to be carried out to replace the large bearings which support each end of the structure, with no disruption to traffic using the bridge.