Doka delivers on Kuwait's Nawaseeb Road

Along the 37km RA217 section of Nawaseeb Road poroject, Doka helped deliver Kuwait’s first in-situ cantilever bridge work.
May 11, 2021 Read time: 5 mins
The Doka Cantilever Forming Traveller offers formwork and shoring from a single source with balance between support structure and formwork enabling construction of 470m of the main bridge (image courtesy Doka)

The Nawaseeb Road in Kuwait forms an important part of the country's national infrastructure, providing a strategic, logistical corridor to neighbouring Saudi Arabia. In delivering a solution for the highway bridge section, Doka helped provide Kuwait with a landmark achievement - its first in-situ cantilever bridge.

Doka supplied an all-in-one solution that included 3D planning, cantilever forming travellers and formwork instructors' support to ensure a smooth, fast and cost-effective process.

The 37km RA217 section of the Nawaseeb Road, also known as Route 40, is one of Kuwait's most important transport projects and part of Kuwait’s Development Plan 2015-2020. Work includes reconstruction and expansion of the highway into a six-lane dual carriageway with nine interchanges and three bridges. The design replaces U-turn points with roundabouts at all interchanges.

Doka was required to find a casting solution for the two main bridges, including pier-to-pier spans, for a combined length of 940m. The longest spans are 110m. As well there is one 893m-long ramp bridge with a maximum span of 95m between piers. The work required 300 casting sections up to 250-tonnes in weight.

Doka used its internal digital planning tools to design the solution that ensured an accelerated planning process while providing the client with an overall visual representation of the project. DokaCAD for Revit was used to produce a 3D model for a more precise visualisation of the cantilever forming travellers.

In total, six Doka Cantilever Forming Travellers, supplemented with around 2,000m² of Large-area formwork Top 50 were used on both the main bridges and ramp bridge at Interchange 5. About 825 tonnes of Doka material was used during.

Using Doka's Cantilever Forming Traveller, the client was reassured by its high-performance precision and how its modular components enabled it to adapt flexibly and quickly to the bridges' varying geometrics. Thanks to the system's ergonomics and a small number of separate parts, the construction process was optimised, meaning a shorter construction schedule to reduce cost.

Cylinder adjustments

Due to limited space on-site, hydraulic cylinders were used to strip the inner wall formwork. As the bridge deck geometry was required to be reduced at every casting step as part of the agreed planning process, the formwork and components of the traveler had to be continuously adjusted. Various hydraulic cylinders and other integrated functions allowed for an easy adjustment process without using chain hoists or additional workforce.

Doka’s Cantilever Forming Traveller uses special slide bearings to allow safe and controllable shunting while preventing unwanted movement along its longitudinal gradients. This ensured the construction team's safety in every phase of the project through fully-enclosed working platforms and an integrated ladder system at all levels.

Meanwhile, Doka’s formwork for the pier heads measured up to 20m in height, 12m in length and was erected onto Load-bearing towers d3 with Large-area formwork Top 50.

Due to the restrictions of existing gas pipelines, the piers' location was pre-defined, resulting in different spans that led to an in-balance in construction delivery. To support the bridge deck during this phase, Doka UniKit towers were used to safely transfer up to a maximum force of 3,800kN to restore balance to the process and ensure the safe delivery of the piers.

Doka Formwork Instructors supported on-site delivery by ensuring that the formwork was used effectively and that the operations ran smoothly from start to finish.

"In using Doka's Cantilever Forming Traveller solution, the project benefited from having an all-in-one solution that was easy for our site teams to use while remaining flexible in terms of versatility for the project's varying challenges,” said Mohamed Dackrory, deputy executive manager of Arab Contractors.


Project in brief:

Project:                                  RA217 Nawaseeb Road
Location:                                Kuwait City, Kuwait    
Client:                                     Ministry of Public Works
Main Contractor:                    Freysinnet
Formwork start:                     January 2020
Formwork end:                      February 2021
Building type:                         In-situ concrete bridge using cantilever construction
Main bridge length:               470m
Main bridge span:                 110 m
No. of casting steps:             84
Ramp bridge length:             893m
Ramp bridge span:               95m
No. of casting steps:            132
DOKA products:
Cantilever Formwork Traveller, Large-area formwork Top 50, Load-bearing tower d3, Load-bearing system Doka UniKit as well as 3D planning with DokaCAD for Revit.

 

For more information on companies in this article

Related Content

  • Major Europe-Asia bridge connection in Turkey
    July 1, 2014
    The 3rd Bosporus Bridge and the Northern Marmara Motorway will improve transport links between Europe and Asia and cut chronic congestion in Istanbul, Turkey’s largest city - Mike Woof reports Work is now well underway on the 3rd Bosporus Bridge and the Northern Marmara Motorway, providing a new link for Turkish city Istanbul and the region as a whole. This enormous bridge and highway project is breaking several records for Turkey in terms of scale, as well as setting a number of international records for e
  • Key expressway route through Hunter Valley
    November 11, 2013
    Australia’s Hunter Valley will benefit from a new high speed expressway, which is currently under construction - Simon Gould reports Located two hours north of Sydney, the Hunter Valley region in New South Wales is one of Australia’s largest producers of coal and wine. With international demand, particularly from Asia, for both continuing to increase, a significant upgrade of infrastructure was required between the region and the port of Newcastle, the world’s largest coal export port. However the strict en
  • What happens when you run out of land for roads?
    November 1, 2021
    Mumbai, the financial capital of India has a population of 12.4 million located in a small area of 437sq.km, surrounded by the sea with nowhere to expand. An increase in congestion on Mumbai’s roads has put a strain on the city’s infrastructure. The result has been long commute times with idling cars contributing to an alarming rise in poor air quality, impacting the quality of life for residents
  • Montreal’s new Champlain Bridge is shaping up for Christmas
    September 10, 2018
    Montreal’s Champlain Bridges - one going up, one coming down, reports David Arminas The importance of the new Champlain Bridge to Montreal and Canada can’t be overstated, given the crumbling nature of the not-so-old original Champlain Bridge. The original steel truss affair across the St Lawrence River and the adjacent St Lawrence Seaway canal is “a lifeline for residents and businesses” in greater Montréal, according to the national Auditor General - the public sector spending watchdog. “It accommodates