Croatia-Bosnia connection

The Svilaj Bridge connecting Croatia and the Federation of Bosnia and Herzegovina is nearly 40% complete, according to the contractors and the Croatian Motorways Directorate. Locally, the Svilaj Bridge – financially a 50-50 project between the two countries - is part of a motorway running from Beli Manastir to Osijek and on tyo Svilaj. But the route is also part of the motorway Budapest-Osijek-Sarajevo-Plocˇ which is the Pan European Corridor Vc (Corridor 5, branch c) connecting Budapest with the Adriatic.
October 2, 2018 Read time: 3 mins
Svilaj Bridge: part of Pan European Corridor Vc, Budapest to the Adriatic Sea
The Svilaj Bridge connecting Croatia and the Federation of Bosnia and Herzegovina is nearly 40% complete, according to the contractors and the Croatian Motorways Directorate.


Locally, the Svilaj Bridge – financially a 50-50 project between the two countries - is part of a motorway running from Beli Manastir to Osijek and on tyo Svilaj. But the route is also part of the motorway Budapest-Osijek-Sarajevo-Plocˇ which is the Pan European Corridor Vc (Corridor 5, branch c) connecting Budapest with the Adriatic. Traffic in this corridor - one of the most important branches of the pan-European TEN-T Network - is currently operating on the European route E73.

The Svilaj Bridge superstructure is a continuous beam over seven spans with a double composite cross section made of a steel box, a concrete deck and a bottom concrete slab. The steel box has variable height of 3,300-5,500mm.

The entire structure is a single expansion unit with expansion joints on only the abutments. The piers of the superstructure consist of one massive pier supporting two pot bearings. These bearings are all longitudinally sliding, except for the ones on pier S3.

Each of the two span sections has three 3.5m-wide traffic lanes with no emergency lane but a 0.5m-wide shoulder on both sides. There is also on both span sections a concrete monolith 0.75m-wide sidewalk.

The pier foundation method consists of placing a rectangular head beam on 24 to 36 reinforced concrete piles, depending on the pier location. The 180m-long reinforced concrete piles are 150cm in diameter.

Who’s who

Client: Hrvatske Autoceste, in Croatia, and the Ministry of Communications and Transport of Bosnia and Herzegovina, in Sarajevo
Designer: PZ, Zagreb
Engineer: Centar za organizaciju građenja, in Zagreb
Contractor: Joint Venture: Hering, based in Široki Brijeg, Bosnia and Herzegovina, and Viadukt, based in Zagreb

Excavation workers at all pier locations were operating inside a protective steel box that allowed the pumping out of water seepage. Stability of lateral sides of the steel box is ensured with steel bracing at the top and around 2m above the river bed.

Steel superstructure is dropped in place using land-based cranes and the deck slab is concreted in situ using mobile scaffoldding.

Bridge construction started in September 2016. The works on construction of piers S1, S2, S5 and S6 have been completed and so has the assembling of the steel structure in three out of seven bridge spans.

Reinforced concrete piles are now being constructed on piers S3 and S4, that are placed in the River Sava. Completion of the €22.3 million project is expected by next summer.

Key facts

The 660m Svilaj Bridge, costing €22.3 million, over the Sava River connects Croatia and Bosnia and Herzegovina. The composite steel structure and a concrete slab structure is 130m wide and consists of 6 piers. The design is of two parallel structures, one for each motorway carriage and three lanes. Design speed of the bridge is 80kph.

Related Content

  • Concerns over bidding for Pocitelj Bridge work surface in Bosnia
    January 12, 2017
    A Bosnian minister has expressed concern over the difference between bids by two consortia for a motorway project that includes construction of the Pocitelj Bridge. Bosnia's state-owned motorway company Autoceste FBiH said in May that it had signed a contract worth nearly €108 million with the joint venture of Euroasfalt and Strabag for construction of the 5.8km Klopce-Donja Gracanica subsection of pan-European transport Corridor Vc. A report by the Bosnian news agency Fena said that Bosnia's deputy m
  • Bosnia-Croatia link discussed
    July 13, 2012
    Bosnia and Croatia are looking to discuss a new highway construction project to link the two countries. The Adriatic-Ionic section of the Corridor VC motorway looks likely to pass through Bosnia. The plan is to build a total of 110km of roads, out of the planned 336km on the Corridor VC, by 2012.
  • Tender evaluation nears for Croatia’s Peljeski Bridge Project
    September 22, 2017
    Croatia’s roads agency Hrvatske Ceste will soon start evaluating tenders for the controversial Peljeski Bridge project, according to national media. Bids for construction of the four-lane 2.4km long bridge have been submitted by the China Road and Bridge Corporation, Austria's Strabag as well as consortia headed by Italy’s Astaldi and the Turkish company Ictas. The bridge will connect Croatian territory by traversing the Adriatic Sea’s Mali Ston Bay.
  • PERI fills gap in Greek market
    February 19, 2013
    A team of Greek and German PERI engineers have developed a comprehensive formwork and scaffolding solution for the T4 bridge on the A7 motorway in Greece. The 160km long A7 connects Kalamata in the south to Corinth in the northwest of the Peloponnese peninsula. On one stretch of the motorway a 390m long arched bridge – known as T4 – is being used to close the gap between Paradisia and Tsakona. Set for completion in early 2014, two-thirds of the 22m wide bridge superstructure will be suspended on a steel arc