Skip to main content

Croatia-Bosnia connection

The Svilaj Bridge connecting Croatia and the Federation of Bosnia and Herzegovina is nearly 40% complete, according to the contractors and the Croatian Motorways Directorate. Locally, the Svilaj Bridge – financially a 50-50 project between the two countries - is part of a motorway running from Beli Manastir to Osijek and on tyo Svilaj. But the route is also part of the motorway Budapest-Osijek-Sarajevo-Plocˇ which is the Pan European Corridor Vc (Corridor 5, branch c) connecting Budapest with the Adriatic.
October 2, 2018 Read time: 3 mins
Svilaj Bridge: part of Pan European Corridor Vc, Budapest to the Adriatic Sea
The Svilaj Bridge connecting Croatia and the Federation of Bosnia and Herzegovina is nearly 40% complete, according to the contractors and the Croatian Motorways Directorate.


Locally, the Svilaj Bridge – financially a 50-50 project between the two countries - is part of a motorway running from Beli Manastir to Osijek and on tyo Svilaj. But the route is also part of the motorway Budapest-Osijek-Sarajevo-Plocˇ which is the Pan European Corridor Vc (Corridor 5, branch c) connecting Budapest with the Adriatic. Traffic in this corridor - one of the most important branches of the pan-European TEN-T Network - is currently operating on the European route E73.

The Svilaj Bridge superstructure is a continuous beam over seven spans with a double composite cross section made of a steel box, a concrete deck and a bottom concrete slab. The steel box has variable height of 3,300-5,500mm.

The entire structure is a single expansion unit with expansion joints on only the abutments. The piers of the superstructure consist of one massive pier supporting two pot bearings. These bearings are all longitudinally sliding, except for the ones on pier S3.

Each of the two span sections has three 3.5m-wide traffic lanes with no emergency lane but a 0.5m-wide shoulder on both sides. There is also on both span sections a concrete monolith 0.75m-wide sidewalk.

The pier foundation method consists of placing a rectangular head beam on 24 to 36 reinforced concrete piles, depending on the pier location. The 180m-long reinforced concrete piles are 150cm in diameter.

Who’s who

Client: Hrvatske Autoceste, in Croatia, and the Ministry of Communications and Transport of Bosnia and Herzegovina, in Sarajevo
Designer: PZ, Zagreb
Engineer: Centar za organizaciju građenja, in Zagreb
Contractor: Joint Venture: Hering, based in Široki Brijeg, Bosnia and Herzegovina, and Viadukt, based in Zagreb

Excavation workers at all pier locations were operating inside a protective steel box that allowed the pumping out of water seepage. Stability of lateral sides of the steel box is ensured with steel bracing at the top and around 2m above the river bed.

Steel superstructure is dropped in place using land-based cranes and the deck slab is concreted in situ using mobile scaffoldding.

Bridge construction started in September 2016. The works on construction of piers S1, S2, S5 and S6 have been completed and so has the assembling of the steel structure in three out of seven bridge spans.

Reinforced concrete piles are now being constructed on piers S3 and S4, that are placed in the River Sava. Completion of the €22.3 million project is expected by next summer.

Key facts

The 660m Svilaj Bridge, costing €22.3 million, over the Sava River connects Croatia and Bosnia and Herzegovina. The composite steel structure and a concrete slab structure is 130m wide and consists of 6 piers. The design is of two parallel structures, one for each motorway carriage and three lanes. Design speed of the bridge is 80kph.

Related Content

  • We can be Heroes
    January 11, 2023
    Paraguay’s Puente Héroes del Chaco will provide a vital transport link for the country once it is complete, Mauro Nogarin and Mike Woof report
  • Bangladesh bridge project for XCMG cranes
    March 7, 2018
    Six XCMG crawler cranes are working hard on the construction of the Padma Bridge in Bangladesh. This is a landmark project for Bangladesh, as the 6.15km structure will provide a new link between the south-west of the country and the northern and eastern regions. When the bridge is complete it will connect Louhajong, Munshiganj to Shariatpur and Madaripur. In addition to the main bridge section, there is an additional 3.8km approach bridge, which is also very important to the project. The Padma Bridge is
  • Montreal’s new Champlain Bridge is shaping up for Christmas
    September 10, 2018
    Montreal’s Champlain Bridges - one going up, one coming down, reports David Arminas The importance of the new Champlain Bridge to Montreal and Canada can’t be overstated, given the crumbling nature of the not-so-old original Champlain Bridge. The original steel truss affair across the St Lawrence River and the adjacent St Lawrence Seaway canal is “a lifeline for residents and businesses” in greater Montréal, according to the national Auditor General - the public sector spending watchdog. “It accommodates
  • PERI helping to build world’s longest underwater tunnel
    April 4, 2013
    In China, PERI is playing a crucial role in the construction of the world’s longest underwater tunnel The 6km tunnel is part of a new 35km long road connection across the Pearl River bay in southern China, aiming to allow Hong Kong to grow both physically and economically with Macau and also Zhuhai on mainland China. In a huge field factory near the underwater tunnel site, two production lines are being used to produce a total of 33 tunnel elements. Each of the reinforced concrete tubes for the standard sec