Cleveland Bridge is all decked out on the England’s A14 scheme

As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,
June 4, 2019 Read time: 2 mins
Abutment bound: each of the two 47.5m long bridge decks contained 330tonnes of steel and 720tonnes of concrete
As part of 8100 Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours.


Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments.

On-site civil engineering works were undertaken by the A14 Integrated Delivery Team,

a joint venture between 2319 Costain, 2296 Skanska, 1146 Balfour Beatty, 3005 Atkins and 2874 CH2M. Pouring of the concrete abutments took place simultaneously to the production of the decks’ 12 girders at a Cleveland Bridge factory.

The original scheme called for erecting the bridge decks piecemeal using a crane. This would have involved closing the A14 for a number of weeks. Instead, the decks were constructed near the new bridge site and, using self-propelled modular transporters (SPMTs), travelled a short distance down the closed A14 to the abutments. This meant much less disruption to traffic. It also reduced project delays - SPMTs can better operate in high winds in comparison to cranes.

The preferred option, though, required the development of a large preparation area – an adjacent field - to accommodate the welded girders. There was also significant elevation difference between the assembly area and the A14 carriageway. A large amount of fill and regrading works were required as the SPMTs were limited to a gradient of 4%.

Meanwhile, instead of delivering the bridges as part-length paired-girders and then welded on-site, they were delivered as full-length single-girders – saving about three weeks. When on site, the single girders were braced together and handed over to the A14 Integrated Delivery Team before reinforced concrete was added.


The A14 was closed to traffic at 9pm on a Friday to allow the sections of the existing A14 carriageway to be infilled and regraded to accommodate the SPMTs. The decks were then lifted from a series of trestles onto the SPMTs which eased them along to the abutments for lowering into position.

The bridges were installed during an 11-hour period and the road reopened by noon on Sunday – 18 hours ahead of schedule.

For more information on companies in this article

Related Content

  • Rebuilding a historic bridge linking the US and Canada
    March 8, 2016
    While many road authorities in North America are finding it difficult to stretch their bridge assets beyond half a century, one bridge is closing in on its centenary - David Arminas reports The international Peace Bridge, connecting the Canadian province of Ontario with the US state of New York, is 88 years young this year, and still going strong.
  • Washington DC’s historic bridge replacement project
    June 11, 2019
    The project to replace a historic bridge in US capital Washington DC is providing major challenges for its builders - Mike Woof writes
  • North East UK’s A19 /A1058 Coast Road triple-deck junction opens
    April 5, 2019
    More than 80,000 drivers a day are now using the recently opened and - first ever - North Tyneside triple-deck highway junction in the northeast. England’s A19 /A1058 Coast Road junction improvement scheme, being done for the client Highways England, was opened on time. However, there will be some overnight closures in the next several weeks to complete the landscaping, traffic light and footpath work. A time capsule has been buried on site and is due to be opened in 2118. Work started in June 2016 on
  • PPRS Nice 2018: maintenance moves mountains
    June 22, 2018
    Strategic maintenance was a major theme at the second Pavement Preservation and Recycling Summit in Nice, France. The world is changing, mobility is changing and so roads must change and adapt for the future.” With this brief statement, Jacques Tavernier opened the second PPRS Summit. “At the same time there is a growing awareness of poor or non-existent maintenance for highways. The question for this conference is how to adapt road maintenance in the face of this challenge,” said Tavernier, in his role as