Cleveland Bridge is all decked out on the England’s A14 scheme

As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,
June 4, 2019 Read time: 2 mins
Abutment bound: each of the two 47.5m long bridge decks contained 330tonnes of steel and 720tonnes of concrete
As part of 8100 Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours.


Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments.

On-site civil engineering works were undertaken by the A14 Integrated Delivery Team,

a joint venture between 2319 Costain, 2296 Skanska, 1146 Balfour Beatty, 3005 Atkins and 2874 CH2M. Pouring of the concrete abutments took place simultaneously to the production of the decks’ 12 girders at a Cleveland Bridge factory.

The original scheme called for erecting the bridge decks piecemeal using a crane. This would have involved closing the A14 for a number of weeks. Instead, the decks were constructed near the new bridge site and, using self-propelled modular transporters (SPMTs), travelled a short distance down the closed A14 to the abutments. This meant much less disruption to traffic. It also reduced project delays - SPMTs can better operate in high winds in comparison to cranes.

The preferred option, though, required the development of a large preparation area – an adjacent field - to accommodate the welded girders. There was also significant elevation difference between the assembly area and the A14 carriageway. A large amount of fill and regrading works were required as the SPMTs were limited to a gradient of 4%.

Meanwhile, instead of delivering the bridges as part-length paired-girders and then welded on-site, they were delivered as full-length single-girders – saving about three weeks. When on site, the single girders were braced together and handed over to the A14 Integrated Delivery Team before reinforced concrete was added.


The A14 was closed to traffic at 9pm on a Friday to allow the sections of the existing A14 carriageway to be infilled and regraded to accommodate the SPMTs. The decks were then lifted from a series of trestles onto the SPMTs which eased them along to the abutments for lowering into position.

The bridges were installed during an 11-hour period and the road reopened by noon on Sunday – 18 hours ahead of schedule.

For more information on companies in this article

Related Content

  • Mabey helps deliver bypass in congested UK city
    February 9, 2018
    The new Aberdeen Western Peripheral Route will cut journey times, reduce pollution costs and improve safety. Mabey has announced that its UK Hire business is working on a vital project to build a 58km bypass in Aberdeen. The Aberdeen Western Peripheral Route/Balmedie-Tipperty (AWPR/B-T) project is being delivered by Transport Scotland in partnership with Aberdeen City Council and Aberdeenshire Council. Aberdeen Roads Limited was awarded the contract to build the AWPR/B-T in December 2014 and has appointed
  • New bridge installed in UK over busy rail line
    January 12, 2016
    Work to install a new bridge for the UK’s busiest rail freight line has been carried out over the A160 at the Port of Immingham. The project forms part of the Port of Immingham Improvement Scheme, a €118.15 million (£88.4 million) series of works being carried out on behalf of Highways England. The project involves upgrading 5km of the A160 from single carriageway to dual carriageway, and constructing a number of new structures. Because of the volume of rail traffic using the stretch of track, the new bridg
  • LagoonHull still on the cards
    February 7, 2022
    A proposed major river development in Hull would include an immersed road tunnel to connect traffic arriving from Europe with the UK’s motorway network.
  • Lower Thames Crossing contracts awarded by National Highways
    December 8, 2023
    Lower Thames Crossing contracts have been awarded by National Highways.