Cleveland Bridge is all decked out on the England’s A14 scheme

As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,
June 4, 2019 Read time: 2 mins
Abutment bound: each of the two 47.5m long bridge decks contained 330tonnes of steel and 720tonnes of concrete
As part of 8100 Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours.


Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments.

On-site civil engineering works were undertaken by the A14 Integrated Delivery Team,

a joint venture between 2319 Costain, 2296 Skanska, 1146 Balfour Beatty, 3005 Atkins and 2874 CH2M. Pouring of the concrete abutments took place simultaneously to the production of the decks’ 12 girders at a Cleveland Bridge factory.

The original scheme called for erecting the bridge decks piecemeal using a crane. This would have involved closing the A14 for a number of weeks. Instead, the decks were constructed near the new bridge site and, using self-propelled modular transporters (SPMTs), travelled a short distance down the closed A14 to the abutments. This meant much less disruption to traffic. It also reduced project delays - SPMTs can better operate in high winds in comparison to cranes.

The preferred option, though, required the development of a large preparation area – an adjacent field - to accommodate the welded girders. There was also significant elevation difference between the assembly area and the A14 carriageway. A large amount of fill and regrading works were required as the SPMTs were limited to a gradient of 4%.

Meanwhile, instead of delivering the bridges as part-length paired-girders and then welded on-site, they were delivered as full-length single-girders – saving about three weeks. When on site, the single girders were braced together and handed over to the A14 Integrated Delivery Team before reinforced concrete was added.


The A14 was closed to traffic at 9pm on a Friday to allow the sections of the existing A14 carriageway to be infilled and regraded to accommodate the SPMTs. The decks were then lifted from a series of trestles onto the SPMTs which eased them along to the abutments for lowering into position.

The bridges were installed during an 11-hour period and the road reopened by noon on Sunday – 18 hours ahead of schedule.

For more information on companies in this article

Related Content

  • Proelectric’s mobile solar lighting unit ProLight passes the test
    November 15, 2017
    UK solar lighting manufacturer Prolectric said that trials have been successful for its ProLight mobile solar-powered lighting for infrastructure and highways contractors. The ProLight lighting tower has been used in the UK on the A14 and Hinkley Point power generation site, the M1 Smart Motorway and for Scottish Southern Electric power supplier. ProLight comprises a specially-developed trailer-mounted unit with heavy-duty deep-cycle batteries, an array of four 330W solar panels, a 7.5m telescopic mast with
  • More studies for the Great Istanbul Tunnel under the Bosporus
    March 11, 2019
    Work has started on a geological condition field study for a proposed 6.5km three-deck road and rail tunnel under the Bosporus Strait in Istanbul, Turkey. Average daily road traffic through the Great Istanbul Tunnel is expected to be 120,000 vehicles and the rail line will move around 75,000 people daily. The tunnel, announced in 2015, will be nearly 19m in diameter and have two road levels and one rail level. It will run between Gayrettepe on the European side and Küçüksu on the Asian side. The ci
  • Smooth runway milling in Malaysia
    October 5, 2021
    A fleet of machines from the Wirtgen Group has been used for an airport runway upgrade in Malaysia
  • Arup, Mabey launch Pedesta, a modular glass-fibre polymer bridge
    May 22, 2018
    Arup and Mabey have launched what they claim is the first modular glass-fibre reinforced polymer footbridge, with Mabey becoming the first licensed distributor. Based on a concept by engineering design company Arup, Mabey debuted the bridge, called Pedesta, at Bridges 2017, a one-day conference and exhibition in the English city of Coventry in March. The Mabey Group specialises in the design and provision of temporary works including propping and jacking as well as environmental monitoring services, formw