Cleveland Bridge is all decked out on the England’s A14 scheme

As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,
June 4, 2019 Read time: 2 mins
Abutment bound: each of the two 47.5m long bridge decks contained 330tonnes of steel and 720tonnes of concrete
As part of 8100 Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours.


Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments.

On-site civil engineering works were undertaken by the A14 Integrated Delivery Team,

a joint venture between 2319 Costain, 2296 Skanska, 1146 Balfour Beatty, 3005 Atkins and 2874 CH2M. Pouring of the concrete abutments took place simultaneously to the production of the decks’ 12 girders at a Cleveland Bridge factory.

The original scheme called for erecting the bridge decks piecemeal using a crane. This would have involved closing the A14 for a number of weeks. Instead, the decks were constructed near the new bridge site and, using self-propelled modular transporters (SPMTs), travelled a short distance down the closed A14 to the abutments. This meant much less disruption to traffic. It also reduced project delays - SPMTs can better operate in high winds in comparison to cranes.

The preferred option, though, required the development of a large preparation area – an adjacent field - to accommodate the welded girders. There was also significant elevation difference between the assembly area and the A14 carriageway. A large amount of fill and regrading works were required as the SPMTs were limited to a gradient of 4%.

Meanwhile, instead of delivering the bridges as part-length paired-girders and then welded on-site, they were delivered as full-length single-girders – saving about three weeks. When on site, the single girders were braced together and handed over to the A14 Integrated Delivery Team before reinforced concrete was added.


The A14 was closed to traffic at 9pm on a Friday to allow the sections of the existing A14 carriageway to be infilled and regraded to accommodate the SPMTs. The decks were then lifted from a series of trestles onto the SPMTs which eased them along to the abutments for lowering into position.

The bridges were installed during an 11-hour period and the road reopened by noon on Sunday – 18 hours ahead of schedule.

For more information on companies in this article

Related Content

  • Developments in asphalt compaction machines
    July 4, 2012
    Mike Woof reviews the latest compaction market developments In the run-up to the upcoming World of Asphalt event in Orlando, Florida in March, the leading compaction equipment firms are rolling out upgraded and improved machines. With market conditions tough worldwide, customers are also likely to be encouraged with competitive deals on purchasing new machines and replacing ageing fleets.
  • Float positioning for Bandra Worli Bridges
    May 29, 2024
    In Mumbai, India, two steel bridges have been barged to site and then lifted into position as part of the Mumbai Coastal Road-Bandra Worli Sea Link project.
  • Versatile crushing and screening equipment
    February 13, 2012
    Work on a key link in the United Arab Emirates is benefiting from the use of equipment supplied by Sandvik Mining and Construction. The firm supplied key equipment for the Salalah bypass project, a 32km road link that will span the entire length of Salalah City as it runs from Raysut in the east, towards Ayn Razat in the west.
  • On track for excellence in asphalt plants
    May 30, 2013
    While one leading asphalt plant company has played a key role in the creation of the new Circuit of the Americas F1 racetrack, others have been releasing new plants and plant-related technology onto the market, some of which has been exhibited at major world industry shows. Guy Woodford reports. Astec played an important role in the new Circuit of the Americas Formula 1 racetrack in Austin, Texas. The asphalt base, binder, and surface courses for the 5.47km asphalt road course, which staged its first F1 rac