Cleveland Bridge is all decked out on the England’s A14 scheme

As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,
June 4, 2019 Read time: 2 mins
Abutment bound: each of the two 47.5m long bridge decks contained 330tonnes of steel and 720tonnes of concrete
As part of 8100 Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours.


Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments.

On-site civil engineering works were undertaken by the A14 Integrated Delivery Team,

a joint venture between 2319 Costain, 2296 Skanska, 1146 Balfour Beatty, 3005 Atkins and 2874 CH2M. Pouring of the concrete abutments took place simultaneously to the production of the decks’ 12 girders at a Cleveland Bridge factory.

The original scheme called for erecting the bridge decks piecemeal using a crane. This would have involved closing the A14 for a number of weeks. Instead, the decks were constructed near the new bridge site and, using self-propelled modular transporters (SPMTs), travelled a short distance down the closed A14 to the abutments. This meant much less disruption to traffic. It also reduced project delays - SPMTs can better operate in high winds in comparison to cranes.

The preferred option, though, required the development of a large preparation area – an adjacent field - to accommodate the welded girders. There was also significant elevation difference between the assembly area and the A14 carriageway. A large amount of fill and regrading works were required as the SPMTs were limited to a gradient of 4%.

Meanwhile, instead of delivering the bridges as part-length paired-girders and then welded on-site, they were delivered as full-length single-girders – saving about three weeks. When on site, the single girders were braced together and handed over to the A14 Integrated Delivery Team before reinforced concrete was added.


The A14 was closed to traffic at 9pm on a Friday to allow the sections of the existing A14 carriageway to be infilled and regraded to accommodate the SPMTs. The decks were then lifted from a series of trestles onto the SPMTs which eased them along to the abutments for lowering into position.

The bridges were installed during an 11-hour period and the road reopened by noon on Sunday – 18 hours ahead of schedule.

For more information on companies in this article

Related Content

  • Turkmenistan’s new bridge features novel waterproofing
    November 8, 2017
    Turkmenistan’s new bridge is benefiting from a novel sealing system that will optimise working life as well as maximising safety. A novel waterproofing solution is being utilised for the Turkmenabat - Farap Bridge in Turkmenistan. The project is of note as the structure is the longest metal span bridge in Central Asia. The client for the project is the state-owned firm Turkmenavtohowayollary, while the general contractor is Altcom Road Construction and the consultant engineer is Soyuztransproekt. Stirling
  • Balfour Beatty supported Road Workers’ Safety Forum wins Royal Award
    December 20, 2013
    The Road Workers' Safety Forum (RoWSaF), a cross-industry group led by the Highways Agency and supported by Balfour Beatty and its joint ventures, has been recognised at the Prince Michael International Road Safety Awards for its innovative and collaborative approach to improving safety for road workers. The RoWSaF team collected the award from His Royal Highness Prince Michael of Kent at a ceremony at The Savoy in London.
  • RMD launches R800 panel girder
    July 19, 2022
    RMD Kwikform has launched its heavy-duty R800 modular panel girder system which the company says is the only CE-marked girder system on the market.
  • Presidio Parkway: the Golden Gate Bridge’s new southern approach road
    May 29, 2013
    Work on the Presidio Parkway, a new breathtaking and eco-friendly southern approach road to San Francisco’s Golden Gate Bridge, has entered its crucial second and final phase. As Guy Woodford reports, the vital US$1 billion project has overcome legal as well as environmental challenges to stay on course for its expected 2016 completion Just after 9pm on Friday April 27, 2012 a large public crowd looked on excitedly as a fleet of more than 40 R&L Brosamer and Ferma Corporation deployed hydraulic demolition h