Cleveland Bridge is all decked out on the England’s A14 scheme

As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,
June 4, 2019 Read time: 2 mins
Abutment bound: each of the two 47.5m long bridge decks contained 330tonnes of steel and 720tonnes of concrete
As part of 8100 Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours.


Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments.

On-site civil engineering works were undertaken by the A14 Integrated Delivery Team,

a joint venture between 2319 Costain, 2296 Skanska, 1146 Balfour Beatty, 3005 Atkins and 2874 CH2M. Pouring of the concrete abutments took place simultaneously to the production of the decks’ 12 girders at a Cleveland Bridge factory.

The original scheme called for erecting the bridge decks piecemeal using a crane. This would have involved closing the A14 for a number of weeks. Instead, the decks were constructed near the new bridge site and, using self-propelled modular transporters (SPMTs), travelled a short distance down the closed A14 to the abutments. This meant much less disruption to traffic. It also reduced project delays - SPMTs can better operate in high winds in comparison to cranes.

The preferred option, though, required the development of a large preparation area – an adjacent field - to accommodate the welded girders. There was also significant elevation difference between the assembly area and the A14 carriageway. A large amount of fill and regrading works were required as the SPMTs were limited to a gradient of 4%.

Meanwhile, instead of delivering the bridges as part-length paired-girders and then welded on-site, they were delivered as full-length single-girders – saving about three weeks. When on site, the single girders were braced together and handed over to the A14 Integrated Delivery Team before reinforced concrete was added.


The A14 was closed to traffic at 9pm on a Friday to allow the sections of the existing A14 carriageway to be infilled and regraded to accommodate the SPMTs. The decks were then lifted from a series of trestles onto the SPMTs which eased them along to the abutments for lowering into position.

The bridges were installed during an 11-hour period and the road reopened by noon on Sunday – 18 hours ahead of schedule.

For more information on companies in this article

Related Content

  • Danube bridge takes shape
    February 10, 2012
    A new bridge over the River Danube between Bulgaria and Romania is expected to benefit to the economies of both nations. Krasimir Krastanov reports
  • Manitowoc and Grove brands launching new designs at bauma China 2014
    November 12, 2014
    The Manitowoc Group is introducing new Potain tower cranes and Grove rough terrain cranes to the Chinese market at bauma China 2014. The two new topless tower cranes come from Manitowoc’s Potain brand and are products of the firm’s Zhangjiagang plant in China. Earlier this year the facility also celebrated the delivery of its 5,000th crane since production began in 2006. Meanwhile from the Grove range of mobile cranes will be the latest RT890E rough-terrain crane. Both machines will be on the firm’s booth a
  • Manitowoc and Grove brands launching new designs at bauma China 2014
    January 6, 2017
    The Manitowoc Group is introducing new Potain tower cranes and Grove rough terrain cranes to the Chinese market at bauma China 2014. The two new topless tower cranes come from Manitowoc’s Potain brand and are products of the firm’s Zhangjiagang plant in China. Earlier this year the facility also celebrated the delivery of its 5,000th crane since production began in 2006. Meanwhile from the Grove range of mobile cranes will be the latest RT890E rough-terrain crane. Both machines will be on the firm’s booth a
  • Mobile crushing and screening machine advances
    July 23, 2018
    A series of major new advances are being seen in the crushing and screening equipment market – Mike Woof writes New developments are coming for the aggregate production sector, with a host of new technologies for the crushing and screening segment. These new machines are said to be more versatile, more productive, more efficient and offer a lower cost/tonne than any equipment available previously. CDE claims that its new AggMax 163-SR scrubbing and attrition system features an efficient new RotoMax logw