Cleveland Bridge is all decked out on the England’s A14 scheme

As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,
June 4, 2019 Read time: 2 mins
Abutment bound: each of the two 47.5m long bridge decks contained 330tonnes of steel and 720tonnes of concrete
As part of 8100 Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours.


Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments.

On-site civil engineering works were undertaken by the A14 Integrated Delivery Team,

a joint venture between 2319 Costain, 2296 Skanska, 1146 Balfour Beatty, 3005 Atkins and 2874 CH2M. Pouring of the concrete abutments took place simultaneously to the production of the decks’ 12 girders at a Cleveland Bridge factory.

The original scheme called for erecting the bridge decks piecemeal using a crane. This would have involved closing the A14 for a number of weeks. Instead, the decks were constructed near the new bridge site and, using self-propelled modular transporters (SPMTs), travelled a short distance down the closed A14 to the abutments. This meant much less disruption to traffic. It also reduced project delays - SPMTs can better operate in high winds in comparison to cranes.

The preferred option, though, required the development of a large preparation area – an adjacent field - to accommodate the welded girders. There was also significant elevation difference between the assembly area and the A14 carriageway. A large amount of fill and regrading works were required as the SPMTs were limited to a gradient of 4%.

Meanwhile, instead of delivering the bridges as part-length paired-girders and then welded on-site, they were delivered as full-length single-girders – saving about three weeks. When on site, the single girders were braced together and handed over to the A14 Integrated Delivery Team before reinforced concrete was added.


The A14 was closed to traffic at 9pm on a Friday to allow the sections of the existing A14 carriageway to be infilled and regraded to accommodate the SPMTs. The decks were then lifted from a series of trestles onto the SPMTs which eased them along to the abutments for lowering into position.

The bridges were installed during an 11-hour period and the road reopened by noon on Sunday – 18 hours ahead of schedule.

For more information on companies in this article

Related Content

  • Out of sight
    July 16, 2012
    With traffic volumes increasing around the world, many existing road links will need to be upgraded or replaced in coming years The need for new road tunnels is particularly intense in many dense urban areas, due to environmental requirements that mean new road links will have to be installed underground. However, improving existing road tunnel links is providing a very large part of the business for this specialised construction segment at present.
  • Efficient aggregate production technology
    July 13, 2020
    Efficient aggregate production technology is now coming to market, offering lower cost/tonne production
  • Premiere in the Black Forest
    October 5, 2023
    One of the steepest sections of the B 500, an important road in the southern Black Forest, had to be renewed in the summer of 2023 – more precisely: the first kilometres behind the Triberg town sign, past the famous waterfalls. Asphalt paving specialists from Gebrüder Bantle GmbH & Co. KG were commissioned to resurface the carriageway.
  • Norsenga Bridge undergoes weathering tests
    May 19, 2023
    Norway’s Statens Vegvesen says the wooden truss bridge – opened only in 2017 – will be the subject of a study in conjunction with the Norwegian University of Science and Technology.