Cleveland Bridge is all decked out on the England’s A14 scheme

As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,
June 4, 2019 Read time: 2 mins
Abutment bound: each of the two 47.5m long bridge decks contained 330tonnes of steel and 720tonnes of concrete
As part of 8100 Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours.


Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments.

On-site civil engineering works were undertaken by the A14 Integrated Delivery Team,

a joint venture between 2319 Costain, 2296 Skanska, 1146 Balfour Beatty, 3005 Atkins and 2874 CH2M. Pouring of the concrete abutments took place simultaneously to the production of the decks’ 12 girders at a Cleveland Bridge factory.

The original scheme called for erecting the bridge decks piecemeal using a crane. This would have involved closing the A14 for a number of weeks. Instead, the decks were constructed near the new bridge site and, using self-propelled modular transporters (SPMTs), travelled a short distance down the closed A14 to the abutments. This meant much less disruption to traffic. It also reduced project delays - SPMTs can better operate in high winds in comparison to cranes.

The preferred option, though, required the development of a large preparation area – an adjacent field - to accommodate the welded girders. There was also significant elevation difference between the assembly area and the A14 carriageway. A large amount of fill and regrading works were required as the SPMTs were limited to a gradient of 4%.

Meanwhile, instead of delivering the bridges as part-length paired-girders and then welded on-site, they were delivered as full-length single-girders – saving about three weeks. When on site, the single girders were braced together and handed over to the A14 Integrated Delivery Team before reinforced concrete was added.


The A14 was closed to traffic at 9pm on a Friday to allow the sections of the existing A14 carriageway to be infilled and regraded to accommodate the SPMTs. The decks were then lifted from a series of trestles onto the SPMTs which eased them along to the abutments for lowering into position.

The bridges were installed during an 11-hour period and the road reopened by noon on Sunday – 18 hours ahead of schedule.

For more information on companies in this article

Related Content

  • Power Curbers ramps up Florida projects
    September 5, 2022
    A Florida company is using Power Curbers machines for major runway work in the US state.
  • Innovative Ohio River Bridge crossing
    March 31, 2016
    Work is underway on an innovative new bridge link over the Ohio River in the US.
  • Intrakat lands on its feet with the Ammann’s ABT QuickBatch plant
    December 13, 2018
    Greek construction company Intrakat likes a challenge. It recently took on two closely scheduled airport projects – but it had only a single asphalt plant. Intrakat used the transport-optimised Ammann ABT QuickBatch Asphalt-Mixing Plant to produce mix at the airport on the island of Mykonos airport. Afterwards, the plant was packed and ferried to Kos. The upgraded runways at Mykonos and Kos are two of the 14 Greek airports being rehabilitated within seven months. Intrakat is handling mix production at
  • Switzerland’s new tunnel bore being built
    April 19, 2018
    A major new road tunnel project is being constructed in Switzerland – Mike Woof writes Construction work is now underway in Switzerland for the new Belchen Tunnel bore, a project that has resulted from the country’s long-term infrastructure planning. The building of this latest tunnel is important for Switzerland economically as it will deliver an upgraded link for a major transport infrastructure connection. When it is complete, the tunnel will form part of the vital A2 route between Basel, in the north