Chile's challenging bridge and tunnel construction

SACYR Chile is constructing a bridge on the new Northeast Access Highway in the capital Santiago, and when complete the 22.5km route will link the suburbs of Vitacura and Colina to the city. Acceso Nororiente, opening this year, is the fifth urban freeway in Santiago and stands out because of the challenges in the construction of its bridges ands tunnels.
February 27, 2012 Read time: 3 mins
3229 SACYR Chile is constructing a bridge on the new Northeast Access Highway in the capital Santiago, and when complete the 22.5km route will link the suburbs of Vitacura and Colina to the city.

Acceso Nororiente, opening this year, is the fifth urban freeway in Santiago and stands out because of the challenges in the construction of its bridges ands tunnels. The difficulties were extreme at ground level and the elevated sections required state-of-the-art technology, logistics and environmental damages mitigation measures throughout the project.

The Arquitecto Cruz Viaduct, which seems to float in the sky, has five large pier caps (770tonnes each, measuring 21m x 13m) that required one of the largest cantilever formwork systems ever used in Chile. With heights up to 45m, the columns were engineered to be hollow with a 0.5m thick wall. Each column is ovular in shape with two flat sides and 2.5m diameter ends.

SACYR selected 3231 EFCO's Engineering Department to provide the solution for the demanding project by studying the site conditions, the variable heights of the piers and the reduced working space at the base of each one.

The EFCO Plate Girder system was used as main and secondary large beams and was located at different levels and directly below each cap, creating a base large and strong enough to install the E-Z Deck shoring system. Plate Girder shoring support structures were mounted more than 40m above and weighed more than 90.7tonnes.

On the first level, a 21.6m long Plate Girder assembly of 2.4m² panels acted as main beams, and rested on four SB-4 plus four SB-2 support brackets over both columns (separated at 12m) leaving a 4.8m cantilever on each side. Directly over these panels and transversely distributed there is a second line of beams made up with 1.5m x 2.4m and 1.2m x 2.4m double Plate Girder panels. Finally, to provide a support base for each EFCO E-Z Deck post, the contractor installed Efco's Super Stud as distribution beams. E-Beams cross over the Super Stud to make up the plywood working platform near the column.

Another 21.6m long Plate Girder assembly (2.4m²) panels acting as main beams rested over eight SB-4 support brackets distributed on both columns. Directly over these panels and transversely distributed, the Super Studs acted as spacers and also as secondary beams over which the plywood sheets were installed.

Continuous beams of EFCO Plate Girder were assembled on the ground near the column and long beam assemblies were lifted one by one into place.

"This project required a system that would support the incredible weight on relatively small columns. The EFCO systems were engineered and designed to work near the design capacity and performed beautifully," says EFCO.

For more information on companies in this article

Related Content

  • Far from formulaic
    January 17, 2013
    Formwork solutions for the first axial suspension cable stayed bridge in India; and a four-lane road bridge in Germany’s Harz Mountains, are among the latest bridge-based formwork projects analysed by Guy Woodford RMD Kwikform India has won the contract to design and supply shoring and formwork solutions for the first axial suspension cable stayed bridge ever built in India. The Kota Bridge’s innovative design sees a single 350m span cross the entire width of the Chambal River, with three approach spans on
  • New version of world’s longest floating bridge
    August 12, 2014
    The creation of a new version of the world’s longest floating bridge in Seattle, in the US state of Washington, is among the world’s most eye-catching current bridge engineering projects. It is an impressive example of the health of the bridge replacement sector, particularly in the US, leaving it well placed for growth. Guy Woodford reports Already the world’s longest floating bridge at over 2,310m long, the Governor Albert D Rosellini-Evergreen Point Floating Bridge in Seattle in the United States is g
  • Bridging the gap in African infrastructure
    December 20, 2013
    Leading formwork manufacturers have secured some impressive contracts in Africa, as the continent’s transport infrastructure continues to improve at a rapid pace. Meanwhile, other bridgework equipment companies are also seeing their products in demand in Africa, as well as North America and Australia.
  • Bridge lift in Orlando for interstate rebuild
    July 4, 2019
    Measuring 33.8km long and costing US$2.3 billion, Orlando’s massive I-4 Ultimate is the largest infrastructure project in the Florida Department of Transportation’s history. Divided into four phases, the project requires major bridge work to improve traffic flow through Central Florida. In all, 13 existing structures are being widened, 53 new bridges added and 74 bridges replaced. Area 2, currently under construction, runs through Orlando from Highway 50 at the northern edge to the Highway 423/I-4 interc