Chile's challenging bridge and tunnel construction

SACYR Chile is constructing a bridge on the new Northeast Access Highway in the capital Santiago, and when complete the 22.5km route will link the suburbs of Vitacura and Colina to the city. Acceso Nororiente, opening this year, is the fifth urban freeway in Santiago and stands out because of the challenges in the construction of its bridges ands tunnels.
February 27, 2012 Read time: 3 mins
3229 SACYR Chile is constructing a bridge on the new Northeast Access Highway in the capital Santiago, and when complete the 22.5km route will link the suburbs of Vitacura and Colina to the city.

Acceso Nororiente, opening this year, is the fifth urban freeway in Santiago and stands out because of the challenges in the construction of its bridges ands tunnels. The difficulties were extreme at ground level and the elevated sections required state-of-the-art technology, logistics and environmental damages mitigation measures throughout the project.

The Arquitecto Cruz Viaduct, which seems to float in the sky, has five large pier caps (770tonnes each, measuring 21m x 13m) that required one of the largest cantilever formwork systems ever used in Chile. With heights up to 45m, the columns were engineered to be hollow with a 0.5m thick wall. Each column is ovular in shape with two flat sides and 2.5m diameter ends.

SACYR selected 3231 EFCO's Engineering Department to provide the solution for the demanding project by studying the site conditions, the variable heights of the piers and the reduced working space at the base of each one.

The EFCO Plate Girder system was used as main and secondary large beams and was located at different levels and directly below each cap, creating a base large and strong enough to install the E-Z Deck shoring system. Plate Girder shoring support structures were mounted more than 40m above and weighed more than 90.7tonnes.

On the first level, a 21.6m long Plate Girder assembly of 2.4m² panels acted as main beams, and rested on four SB-4 plus four SB-2 support brackets over both columns (separated at 12m) leaving a 4.8m cantilever on each side. Directly over these panels and transversely distributed there is a second line of beams made up with 1.5m x 2.4m and 1.2m x 2.4m double Plate Girder panels. Finally, to provide a support base for each EFCO E-Z Deck post, the contractor installed Efco's Super Stud as distribution beams. E-Beams cross over the Super Stud to make up the plywood working platform near the column.

Another 21.6m long Plate Girder assembly (2.4m²) panels acting as main beams rested over eight SB-4 support brackets distributed on both columns. Directly over these panels and transversely distributed, the Super Studs acted as spacers and also as secondary beams over which the plywood sheets were installed.

Continuous beams of EFCO Plate Girder were assembled on the ground near the column and long beam assemblies were lifted one by one into place.

"This project required a system that would support the incredible weight on relatively small columns. The EFCO systems were engineered and designed to work near the design capacity and performed beautifully," says EFCO.

For more information on companies in this article

Related Content

  • Arch of innovation
    September 21, 2020
    ULMA engineering solutions on the emblematic Arch of Innovation bridge, Brazil
  • Terex cranes in a tight spot in Michigan
    February 6, 2017
    Terex cranes have been involved in a multiple bridge repair project in the US More than 96,000 vehicles per day travel a stretch of I-96, including its 52-year-old bridges. The Michigan Department of Transportation is in the midst of a two-year US$77 million project to repair bridges and relieve increasing congestion along Interstate 96 at the U.S. Highway 23 interchange in Livingston County. Toebe Construction along with joint venture partner Kamminga & Roodvoets are bringing in a lot of lifting powe
  • Key expressway route through Hunter Valley
    November 11, 2013
    Australia’s Hunter Valley will benefit from a new high speed expressway, which is currently under construction - Simon Gould reports Located two hours north of Sydney, the Hunter Valley region in New South Wales is one of Australia’s largest producers of coal and wine. With international demand, particularly from Asia, for both continuing to increase, a significant upgrade of infrastructure was required between the region and the port of Newcastle, the world’s largest coal export port. However the strict en
  • Liebherr cranes on the Rader
    December 10, 2024
    Germany’s Rader High Bridge spanning the Kiel Canal along Germany’s A7 motorway is to be replaced and widened over the next few years. Eighteen Liebherr cranes are handling the lifting.