Champlain Bridge set to open by end of year, says SNC-Lavalin

The Canadian city’s replacement Champlain Bridge will open on schedule at the end of the year. Montreal, one of Canada’s largest cities, will have a well-earned Christmas present in December when the new Champlain Bridge opens after 42 months of construction. The new bridge, part of a six-lane 6km corridor including roads, is being built alongside the original bridge over the Saint Lawrence River and Seaway canal system. The new bridge, 3.4km long, runs from the île des Soeurs to Brossard, immediately dow
May 14, 2018 Read time: 4 mins
The new cable-stayed bridge consists of a 170m-high twin-tower with a front span of around 240m and a back span of 120m
The Canadian city’s replacement Champlain Bridge will open on schedule at the end of the year.


Montreal, one of Canada’s largest cities, will have a well-earned Christmas present in December when the new Champlain Bridge opens after 42 months of construction.

The new bridge, part of a six-lane 6km corridor including roads, is being built alongside the original bridge over the Saint Lawrence River and Seaway canal system. The new bridge, 3.4km long, runs from the île des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

“What I can tell you… is that the objective remains to deliver the bridge in December 2018,” said Annie-Claire Fournier, a spokesperson for the consortium, Signature on the Saint Lawrence.

Cost of the entire corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

Failure to open the bridge to vehicular traffic on time means the consortium faces stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint Lawrence Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are 981 Hochtief, 2758 Flatiron, 4761 Dragados Canada and Grupo 917 ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract of approximately $2.15 billion with a construction joint venture of which SNC-Lavalin is again a 50% partner.

SSL and the Canadian government also appointed as overseeing independent engineer the Danish group 6801 Ramboll and Canadian engineering firm 5346 Stantec, based in Edmonton in the province of Alberta. Ramboll said that a team of its designers from the UK and Denmark has been working with a team from Stantec to ensure the project is delivered in compliance with performance criteria. This includes examining design documents, supervision plans and the management and quality control system.

According to some of the design engineers, the project was always going to be challenging not just because of the deadline. It coincides with other major roadworks, including on the current Champlain Bridge, the Turcot Interchange and the Bonaventure Expressway. Contractor have added more shifts as the completion deadline approaches.

Other challenges surfaced over the months, with around 2,500 defects discovered in some prefabricated parts and within the road sections, although these were eventually put right.

Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Total cost of the project was $40 million, of which the bridge accounted for around $27 million.


Of the old 14.5km-long complex, the bridge measures 7.4km. Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Around $16 billion worth of goods are estimated to pass over the bridge. But the increasing traffic, combined with damage from road salt on the steel and concrete, and other factors, meant a new bridge was essential.

Federal infrastructure minister Amarjeet Sohi recently said the Canadian government has commissioned a study of how much it would cost to keep the existing 56-year-old Champlain Bridge open to traffic beyond 2018.

The new composite girder bridge across the river and Seaway consists of a 170m-high twin-tower cable stay section with a front span of around 240m and a back span of 120m, approaches will be constructed with a total length of 3.1km.

The corridor-wide project also includes construction of a new 470m bridge for L’Île-des-Sœurs, the widening of Highway 15 and improvements to various highway ramps leading to the bridges.

Because winters are brutally cold and snowy in the province of Quebec, two so-called superdomes were built on the end of the West Jetty on Nun’s Island. These protected and heated areas house what amounts to an assembly line for preparation of the 74 transition segments. These provide the interface between the pier caps and pier legs and are made in Spain. Preparation of the hollow steel shells involves adding rebar, embedded elements and post tensioning ducts.

The piece is then transferred to the temperature-controlled segment nursery, ready for the pouring of concrete. The segment is moved to another area of the plant where it is rotated to optimise the concrete’s quality, notably in the anchor heads.

Finally, the steel-and-concrete component is stored outside as it awaits installation. Assembly of the segments is expected to be finished by this spring.

For more information on companies in this article

Related Content

  • India’s longest tolled expressway is open to traffic
    January 2, 2013
    Earlier this year, a new expressway was opened to traffic in India, adding connectivity to the country’s road network - Mike Woof reports. India’s economic growth has fuelled a massive construction boom in the country. Road building has been set as a priority by the Indian Government to help ensure continued economic development and improve connectivity between major population centres. One major new expressway has recently opened to traffic, having been designed to international standards and provides insi
  • Major tunnel project underway in Bangladesh
    March 1, 2019
    A major tunnel construction project is now underway in Bangladesh, the first tunnel in the country to be constructed under a river.
  • Florida highway rebuild project
    May 2, 2018
    Rebuilding a congested stretch of highway in Florida will cut congestion and boost safety for commuters - Mike Woof writes. Florida’s 214km-long I-4 highway provides a key transport route between Tampa and Daytona Beach, but has an unenviable reputation for both congestion and safety, with frequent delays due to heavy traffic as well as crashes. The stretch running through the city of Orlando is particularly prone to jams at peak periods, with huge traffic volumes resulting in vehicles having to slow to a c
  • Lindsay argues the case for reversible lanes over adding lanes
    June 26, 2018
    Build new lanes or use existing lanes more effectively? In a recent US study* commissioned by Lindsay Transportation Solutions, the company argues the case for reversible lanes. The level of future uncertainty in transportation planning - specifically in addressing congestion on urban freeways - has increased significantly over the past few years. The impact of connected and autonomous vehicles on traffic flow, of Mobility as a Service (MaaS) initiatives, particularly the car-sharing elements, and exciting