Champlain Bridge set to open by end of year, says SNC-Lavalin

The Canadian city’s replacement Champlain Bridge will open on schedule at the end of the year. Montreal, one of Canada’s largest cities, will have a well-earned Christmas present in December when the new Champlain Bridge opens after 42 months of construction. The new bridge, part of a six-lane 6km corridor including roads, is being built alongside the original bridge over the Saint Lawrence River and Seaway canal system. The new bridge, 3.4km long, runs from the île des Soeurs to Brossard, immediately dow
May 14, 2018 Read time: 4 mins
The new cable-stayed bridge consists of a 170m-high twin-tower with a front span of around 240m and a back span of 120m
The Canadian city’s replacement Champlain Bridge will open on schedule at the end of the year.


Montreal, one of Canada’s largest cities, will have a well-earned Christmas present in December when the new Champlain Bridge opens after 42 months of construction.

The new bridge, part of a six-lane 6km corridor including roads, is being built alongside the original bridge over the Saint Lawrence River and Seaway canal system. The new bridge, 3.4km long, runs from the île des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

“What I can tell you… is that the objective remains to deliver the bridge in December 2018,” said Annie-Claire Fournier, a spokesperson for the consortium, Signature on the Saint Lawrence.

Cost of the entire corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

Failure to open the bridge to vehicular traffic on time means the consortium faces stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint Lawrence Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are 981 Hochtief, 2758 Flatiron, 4761 Dragados Canada and Grupo 917 ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract of approximately $2.15 billion with a construction joint venture of which SNC-Lavalin is again a 50% partner.

SSL and the Canadian government also appointed as overseeing independent engineer the Danish group 6801 Ramboll and Canadian engineering firm 5346 Stantec, based in Edmonton in the province of Alberta. Ramboll said that a team of its designers from the UK and Denmark has been working with a team from Stantec to ensure the project is delivered in compliance with performance criteria. This includes examining design documents, supervision plans and the management and quality control system.

According to some of the design engineers, the project was always going to be challenging not just because of the deadline. It coincides with other major roadworks, including on the current Champlain Bridge, the Turcot Interchange and the Bonaventure Expressway. Contractor have added more shifts as the completion deadline approaches.

Other challenges surfaced over the months, with around 2,500 defects discovered in some prefabricated parts and within the road sections, although these were eventually put right.

Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Total cost of the project was $40 million, of which the bridge accounted for around $27 million.


Of the old 14.5km-long complex, the bridge measures 7.4km. Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Around $16 billion worth of goods are estimated to pass over the bridge. But the increasing traffic, combined with damage from road salt on the steel and concrete, and other factors, meant a new bridge was essential.

Federal infrastructure minister Amarjeet Sohi recently said the Canadian government has commissioned a study of how much it would cost to keep the existing 56-year-old Champlain Bridge open to traffic beyond 2018.

The new composite girder bridge across the river and Seaway consists of a 170m-high twin-tower cable stay section with a front span of around 240m and a back span of 120m, approaches will be constructed with a total length of 3.1km.

The corridor-wide project also includes construction of a new 470m bridge for L’Île-des-Sœurs, the widening of Highway 15 and improvements to various highway ramps leading to the bridges.

Because winters are brutally cold and snowy in the province of Quebec, two so-called superdomes were built on the end of the West Jetty on Nun’s Island. These protected and heated areas house what amounts to an assembly line for preparation of the 74 transition segments. These provide the interface between the pier caps and pier legs and are made in Spain. Preparation of the hollow steel shells involves adding rebar, embedded elements and post tensioning ducts.

The piece is then transferred to the temperature-controlled segment nursery, ready for the pouring of concrete. The segment is moved to another area of the plant where it is rotated to optimise the concrete’s quality, notably in the anchor heads.

Finally, the steel-and-concrete component is stored outside as it awaits installation. Assembly of the segments is expected to be finished by this spring.

For more information on companies in this article

Related Content

  • Controversial Russian bridge opens
    August 10, 2018
    The first stage of a controversial Russian bridge project is now complete, with the link having been opened to use by cars and buses. The Kerch Strait bridge spans the Black Sea, connecting Russia’s Taman Peninsula in Krasnodar with Crimea, the latter having been controversially annexed by Russia from Ukraine in 2014. The official opening of the 19km-long bridge was carried out by Russia’s president, Vladimir Putin, who drove across the link in a Russian-manufactured Kamaz truck to reach the city of Kerch.
  • International firms compete in US bridge project tenders
    May 2, 2012
    The Spanish construction firm ACS is tendering for the construction and operation of four bridges in the US. The firm is tendering in partnership with some other US and international firms for some of the projects, which are worth a total of US$11.4 billion. The Tappan Zee project is expected to cost $5 billion and the deal will be for a design and construction contract. The bridge will be located in New York, is being developed by New York State Thruway Authority and will require two, four-carriageway brid
  • Vietnam: work on Phuoc Khanh cable stayed bridge to begin in August
    June 22, 2015
    Work on Vietnam’s 3.1km Phuoc Khanh cable stayed bridge will start in August after a deal was signed with the government in June. The contract was signed by the Vietnam Expressway Corporation and a consortium made up of Japanese contractor Sumitomo Mitsui and local partner Civil Engineering Construction Corporation (Cienco 4). The bridge is part of the 57km Ben Luc-Long Thanh Expressway project running through Long An Province, Ho Chi Minh City and Dong Nai province in southern Vietnam. The highway will a
  • Itinera wins Sweden’s Skurusunds Bridge near Stockholm
    January 21, 2019
    Italian contractor Itinera will build the new 99m-long and 31m-wide Skurusunds Bridge near Stockholm in Sweden. Trafikverket, the Swedish transport administration, awarded the €75 million contract to Itinera, part of Gruppo Gavio. The new bridge will be parallel to the existing bridge which will remain. It handles around 52,000 vehicles daily, many of them commuting to and from Stockholm. Work will include improvements to traffic junctions at Skuru and Björknäs. The four-lane steel bridge will have