Bridges and tunnels tackle congestion problems

In preparation for the 2014 Olympic Winter Games, the Black Sea health resort of Sotschi, Russia, is tackling its growing traffic jam problems.A 13km bypass and a new main road passing mainly under the city involves the construction of 15 tunnels and a number of bridges and flyovers.
February 29, 2012 Read time: 3 mins
A Wirth roadheader at the Sochi tunnels: another has been ordered
In preparation for the 2014 Olympic Winter Games, the Black Sea health resort of Sotschi, Russia, is tackling its growing traffic jam problems.

A 13km bypass and a new main road passing mainly under the city involves the construction of 15 tunnels and a number of bridges and flyovers.

298 PERI has developed and supplied a tunnel formwork carriage for construction of the six emergency parking bays (three in each direction) in a 2,607metre long tunnel on the bypass.
Here, the two-lane tunnel tube is widened from 10.8m by around 3.5m, and the biggest challenge was the design of the lifting and lowering units with integrated horizontal adjustment device.

"Because the formwork carriage was to be moved to the next emergency bay through the already finished standard cross-sections of the tunnel, this meant that the size of the complete construction had be reduced quite considerably," says PERI.
The tunnel formwork carriage developed was based on the VARIOKIT modular construction kit (the use of standardised serial components is an advantage for the contractor because the system elements can also be used for future formworking operations).

For striking and the rail-guided moving procedure to each subsequent casting segment of a parking bay, the side formwork could be folded hydraulically and the complete formwork carriage was able to be lowered. In this way, each of the emergency parking bays could be constructed in six 9m long concreting sections in weekly cycles.

To reduce the formwork carriage (from 14.3m wide to 10.10m, height from 8.7m to 7.6m) to move to the next parking bay, PERI engineers developed an accurately defined working sequence by which the formwork segments could be folded and lowered to allow passage through the substantially smaller standard cross section.

"The combination of load frames, heavy duty spindles, walers and GT 24 formwork girders ensured high utilisation and load-carrying capacity of the formwork carriage. The striking and moving process could be safely and quickly carried out by construction site personnel although all of the technology was completely new to them," says PERI.

All the tunnels on the partially-completed Stoschi bypass have been constructed using four Wirth Paurat roadheaders (heavy duty machines specifically designed for tunneling). Three of the four machines are operated by the OOO Tonneldorstroy (TDS) company, which has placed another order with Wirth for a Type T3.20 roadheader weighing about 120tonnes and with 300kW installed cutting power.

Instead of blasting the rock with explosives, the cutter head of the roadheader excavates precisely the profile that is required, without unnecessary overbreak or rock disturbance.

For more information on companies in this article

Related Content

  • Chile's challenging bridge and tunnel construction
    February 27, 2012
    SACYR Chile is constructing a bridge on the new Northeast Access Highway in the capital Santiago, and when complete the 22.5km route will link the suburbs of Vitacura and Colina to the city. Acceso Nororiente, opening this year, is the fifth urban freeway in Santiago and stands out because of the challenges in the construction of its bridges ands tunnels.
  • What lies beneath Down Under
    January 11, 2021
    The third and final construction stage on Sydney’s WestConnex project has begun, including the underground Rozelle Interchange – with a lot of help from Komatsu
  • Doka rises to the challenge on Turkey’s Eyiste Viaduct
    June 4, 2019
    Formwork specialist Doka recently rose to the challenge on Turkey’s Eyiste Viadust, the country’s highest bridge with piers up to 155m tall. The Eyiste Viaduct will be part of a route between Central Anatolia and Turkey’s Mediterranean region, shortening travel time between the cities of Konya and Alanya. Cantilever forming travellers and Doka’s automatic climbing formwork Xclimb 60 were part of the construction solution. The viaduct is nearly 1.4km long and carried by two abutments and eight piers, stret
  • Driver threads his Greyhound bus through a needle in the US
    January 29, 2015
    There are tight squeezes and there are tight squeezes. But this highway, in the Black Hills region of South Dakota state in the United States, was never meant for a Greyhound bus. It’s easy does it, as the youtube video shows just what an experienced driver can do. The camera captures the painstaking, and slow, effort of the driver as he threads his American behemoth through the eye of a needle, in this case a tunnel along the Needles Highway.