Bridges and tunnels tackle congestion problems

In preparation for the 2014 Olympic Winter Games, the Black Sea health resort of Sotschi, Russia, is tackling its growing traffic jam problems.A 13km bypass and a new main road passing mainly under the city involves the construction of 15 tunnels and a number of bridges and flyovers.
February 29, 2012 Read time: 3 mins
A Wirth roadheader at the Sochi tunnels: another has been ordered
In preparation for the 2014 Olympic Winter Games, the Black Sea health resort of Sotschi, Russia, is tackling its growing traffic jam problems.

A 13km bypass and a new main road passing mainly under the city involves the construction of 15 tunnels and a number of bridges and flyovers.

298 PERI has developed and supplied a tunnel formwork carriage for construction of the six emergency parking bays (three in each direction) in a 2,607metre long tunnel on the bypass.
Here, the two-lane tunnel tube is widened from 10.8m by around 3.5m, and the biggest challenge was the design of the lifting and lowering units with integrated horizontal adjustment device.

"Because the formwork carriage was to be moved to the next emergency bay through the already finished standard cross-sections of the tunnel, this meant that the size of the complete construction had be reduced quite considerably," says PERI.
The tunnel formwork carriage developed was based on the VARIOKIT modular construction kit (the use of standardised serial components is an advantage for the contractor because the system elements can also be used for future formworking operations).

For striking and the rail-guided moving procedure to each subsequent casting segment of a parking bay, the side formwork could be folded hydraulically and the complete formwork carriage was able to be lowered. In this way, each of the emergency parking bays could be constructed in six 9m long concreting sections in weekly cycles.

To reduce the formwork carriage (from 14.3m wide to 10.10m, height from 8.7m to 7.6m) to move to the next parking bay, PERI engineers developed an accurately defined working sequence by which the formwork segments could be folded and lowered to allow passage through the substantially smaller standard cross section.

"The combination of load frames, heavy duty spindles, walers and GT 24 formwork girders ensured high utilisation and load-carrying capacity of the formwork carriage. The striking and moving process could be safely and quickly carried out by construction site personnel although all of the technology was completely new to them," says PERI.

All the tunnels on the partially-completed Stoschi bypass have been constructed using four Wirth Paurat roadheaders (heavy duty machines specifically designed for tunneling). Three of the four machines are operated by the OOO Tonneldorstroy (TDS) company, which has placed another order with Wirth for a Type T3.20 roadheader weighing about 120tonnes and with 300kW installed cutting power.

Instead of blasting the rock with explosives, the cutter head of the roadheader excavates precisely the profile that is required, without unnecessary overbreak or rock disturbance.

For more information on companies in this article

Related Content

  • Australian bridge slides into position
    July 18, 2012
    A heavy rail crossing as part of Australia's EastLink motorway demanded great ingenuity and careful planning Most of the 88 bridges on the EastLink tolled motorway in, Melbourne, Australia were kept as simple and straightforward as possible. Contractor Thiess John Holland (TJH) developed its own precast yard 150km from the city, which provided many of the prefabricated materials required for the structures. This offered speed and economy while logistics and sequencing were vital for their erection. But the
  • Norway’s massive Rogfast Tunnel project
    December 11, 2018
    The world's longest and deepest road tunnel is underway in western Norway - Adrian Greeman reports
  • Duisburg double for lift specialist Sarens
    June 5, 2024
    Heavy lift specialist Sarens overcame challenging wind and water conditions during installation of two strategic road bridges - the Oberbürgermeister Karl Lehr Brücke and the Hafenkanalbrücke - in the German city of Duisburg.
  • Sandvik on drill at the Liantang/Heung Yuen Wai Boundary project
    April 4, 2018
    The Liantang/Heung Yuen Wai Boundary Control Point project is creating a seventh land crossing, including highways and tunnels, between Shenzhen in China and Hong Kong There are already two control points on the eastern side of the New Territories between China and Hong Kong - at Man Kam To and Sha Tau Kok – to access eastern Shenzhen and Guangdong. All cross-boundary traffic travelling from these points must use busy local roads in Hong Kong and Shenzhen before joining the major highway systems. The US