Bridge project uses high performing formwork

Doka designed and supplied a high-performing formwork technology solution for a challenging bridge project south of the German town of Halle. The 8,614m long single-cell box girder superstructure of the Saale-Elster Viaduct, with a typical cross section width of 13.9m, is borne on 220 piers, and has a constructional depth of 4m. It is mainly being erected on launching girders to minimise the impact on flora and fauna.
February 20, 2012 Read time: 3 mins
203 Doka designed and supplied a high-performing formwork technology solution for a challenging bridge project south of the German town of Halle.

The 8,614m long single-cell box girder superstructure of the Saale-Elster Viaduct, with a typical cross section width of 13.9m, is borne on 220 piers, and has a constructional depth of 4m. It is mainly being erected on launching girders to minimise the impact on flora and fauna.

Thirty two of the piers are in ecologically sensitive areas, and to minimise their environmental impact, they are being built on shallow foundations poured inside watertight sheet-piled cofferdams. These are constructed in advance of the other operations using the over-the-top method, working downwards from the cantilevering ends of two launching girders.

In conjunction with around 1,000 stud-welded head bolts, the up to 20m deep sheet pile walls and up to 2.75m thick reinforced concrete base slabs constitute a friction-locked unit.

The project as a whole entails the expert forming of more than 140,000m³ of concrete.

"Right from the outset, the Doka formwork experts have been supporting the joint venture [981 Hochtief, Adam Hörnig and GERDUM & BREUER] with know-how and sophisticated formwork solutions, so as to deliver the required superior quality of fair-faced concrete," says Doka On the viaduct, there will also be a Y-branch, and the complex overpasses call for four abutments of up to 8m in height.

A combination of two different Doka timber beam formwork systems is being used to construct the four abutments: some of the completely factory-assembled wall formwork FF20 was fitted with extra board-type facing by the Ready-to-Use Service at Doka's Leipzig Branch to be sure of meeting the fair-faced concrete requirements.

"In addition, gangs put together from the large-area formwork Top 50 'construction kit' are ensuring excellent adaptation to the integrated bridge pier cap, and to the wall pillars which also have to be formed. Here too, the formwork units were assembled by the Doka Ready-to-Use Service and delivered to the site ready for operation. Both systems work together perfectly and complement one another seamlessly so as to ensure swift construction progress.

"In order to complete the 220 hollow piers on schedule, the jv is working with three complete sets of large-area formwork Top 50 as the starter formwork, and another five sets of climbing formwork. The perpendicular piers are rectangular in shape, with corners bevelled by 50cm. With a circumferential wall thickness of 30cm, they measure 6m in the transverse direction of the bridge and 2.7m or 3.5m in the longitudinal direction," says Doka.

For more information on companies in this article

Related Content

  • Lochkov bridge construction time 'cut'
    July 17, 2012
    As part of the R1 southern orbital motorway around the Czech capital, Prague, a joint venture is building a five-span, 461m long and approximately 65m high viaduct near the village of Lochkov, as a girder bridge construction. For the two steeply inclined twin piers, Doka has supplied an automatic climbing formwork solution that obviates the need for shoring and that will "cut more than 100 days from the construction period." Cast-in-place concrete construction of bridge piers with such a steep inclination
  • Major bridge construction on Denmark's road project
    April 20, 2012
    Doka is playing a leading role in Denmark’s first ever public private partnership roadbuilding project. The 26km long, four-lane M51, 15km from the German border, will link Kliplev and Sønderborg in southern Jutland. And Doka will be the sole provider offormwork for the concrete used in erecting the motorway’s 72 bridges and crossings. The M51 is using 9000m² of the extremely adaptable Large-area formwork Top 50, and more than 4,750 basic frames of the heavyduty Load-bearing tower Staxo 100 system.
  • Towers of power: California’s Gerald Desmond Bridge Replacement
    May 8, 2019
    Challenging ground conditions meant a design rethink - and some engineering firsts - for California’s Gerald Desmond Bridge Replacement Project* The Port of Long Beach on Terminal Island south of Los Angeles is the second-busiest container port in the US. It handles around 15% of all imported goods, much of it with Asia. As the Port of Long Beach was growing in importance over the past half century, the 51-year-old Gerald Desmond Bridge has faithfully been delivering thousands of daily commuters to wo
  • Key expressway route through Hunter Valley
    November 11, 2013
    Australia’s Hunter Valley will benefit from a new high speed expressway, which is currently under construction - Simon Gould reports Located two hours north of Sydney, the Hunter Valley region in New South Wales is one of Australia’s largest producers of coal and wine. With international demand, particularly from Asia, for both continuing to increase, a significant upgrade of infrastructure was required between the region and the port of Newcastle, the world’s largest coal export port. However the strict en