Bridge project uses high performing formwork

Doka designed and supplied a high-performing formwork technology solution for a challenging bridge project south of the German town of Halle. The 8,614m long single-cell box girder superstructure of the Saale-Elster Viaduct, with a typical cross section width of 13.9m, is borne on 220 piers, and has a constructional depth of 4m. It is mainly being erected on launching girders to minimise the impact on flora and fauna.
February 20, 2012 Read time: 3 mins
203 Doka designed and supplied a high-performing formwork technology solution for a challenging bridge project south of the German town of Halle.

The 8,614m long single-cell box girder superstructure of the Saale-Elster Viaduct, with a typical cross section width of 13.9m, is borne on 220 piers, and has a constructional depth of 4m. It is mainly being erected on launching girders to minimise the impact on flora and fauna.

Thirty two of the piers are in ecologically sensitive areas, and to minimise their environmental impact, they are being built on shallow foundations poured inside watertight sheet-piled cofferdams. These are constructed in advance of the other operations using the over-the-top method, working downwards from the cantilevering ends of two launching girders.

In conjunction with around 1,000 stud-welded head bolts, the up to 20m deep sheet pile walls and up to 2.75m thick reinforced concrete base slabs constitute a friction-locked unit.

The project as a whole entails the expert forming of more than 140,000m³ of concrete.

"Right from the outset, the Doka formwork experts have been supporting the joint venture [981 Hochtief, Adam Hörnig and GERDUM & BREUER] with know-how and sophisticated formwork solutions, so as to deliver the required superior quality of fair-faced concrete," says Doka On the viaduct, there will also be a Y-branch, and the complex overpasses call for four abutments of up to 8m in height.

A combination of two different Doka timber beam formwork systems is being used to construct the four abutments: some of the completely factory-assembled wall formwork FF20 was fitted with extra board-type facing by the Ready-to-Use Service at Doka's Leipzig Branch to be sure of meeting the fair-faced concrete requirements.

"In addition, gangs put together from the large-area formwork Top 50 'construction kit' are ensuring excellent adaptation to the integrated bridge pier cap, and to the wall pillars which also have to be formed. Here too, the formwork units were assembled by the Doka Ready-to-Use Service and delivered to the site ready for operation. Both systems work together perfectly and complement one another seamlessly so as to ensure swift construction progress.

"In order to complete the 220 hollow piers on schedule, the jv is working with three complete sets of large-area formwork Top 50 as the starter formwork, and another five sets of climbing formwork. The perpendicular piers are rectangular in shape, with corners bevelled by 50cm. With a circumferential wall thickness of 30cm, they measure 6m in the transverse direction of the bridge and 2.7m or 3.5m in the longitudinal direction," says Doka.

For more information on companies in this article

Related Content

  • Bridge uses new forming carriage
    February 7, 2012
    The Holzmatttal Bridge for the A98 autobahn in southern Germany stretches 410m across the valley, and on this build the newly-developed Doka forming carriage TU is said to have demonstrated precisely how it drives progress with extremely short cycle times and speedy forming and stripping out operations. The underslung carriage also permits unobstructed access for site traffic.
  • Modern formwork systems - fast, flexible, safe
    February 21, 2012
    Speed of erection, safety, cost-efficiency and flexibility are among the attributes of modern formwork systems. Modern formwork and scaffolding systems are attractive in particular for their speed of erection, safety, cost-efficiency and flexibility.
  • Bridge formwork solutions complete big bridge picture
    July 2, 2014
    Advanced bridge formwork solutions are allowing contractors to complete vital major highway infrastructure projects covering Norway, Sweden, Estonia and Poland. Guy Woodford reports Building the Labbdalen bridges in Norway is a key feature of the E6 highway improvement programme. Main project contractor HÆHRE tasked RMD Kwikform and Teknikk with supplying a complete formwork and shoring solution that could tackle the challenging Norwegian terrain, whilst preserving the environment. Situated two hours
  • PERI fills gap in Greek market
    February 19, 2013
    A team of Greek and German PERI engineers have developed a comprehensive formwork and scaffolding solution for the T4 bridge on the A7 motorway in Greece. The 160km long A7 connects Kalamata in the south to Corinth in the northwest of the Peloponnese peninsula. On one stretch of the motorway a 390m long arched bridge – known as T4 – is being used to close the gap between Paradisia and Tsakona. Set for completion in early 2014, two-thirds of the 22m wide bridge superstructure will be suspended on a steel arc