Bridge project uses high performing formwork

Doka designed and supplied a high-performing formwork technology solution for a challenging bridge project south of the German town of Halle. The 8,614m long single-cell box girder superstructure of the Saale-Elster Viaduct, with a typical cross section width of 13.9m, is borne on 220 piers, and has a constructional depth of 4m. It is mainly being erected on launching girders to minimise the impact on flora and fauna.
February 20, 2012 Read time: 3 mins
203 Doka designed and supplied a high-performing formwork technology solution for a challenging bridge project south of the German town of Halle.

The 8,614m long single-cell box girder superstructure of the Saale-Elster Viaduct, with a typical cross section width of 13.9m, is borne on 220 piers, and has a constructional depth of 4m. It is mainly being erected on launching girders to minimise the impact on flora and fauna.

Thirty two of the piers are in ecologically sensitive areas, and to minimise their environmental impact, they are being built on shallow foundations poured inside watertight sheet-piled cofferdams. These are constructed in advance of the other operations using the over-the-top method, working downwards from the cantilevering ends of two launching girders.

In conjunction with around 1,000 stud-welded head bolts, the up to 20m deep sheet pile walls and up to 2.75m thick reinforced concrete base slabs constitute a friction-locked unit.

The project as a whole entails the expert forming of more than 140,000m³ of concrete.

"Right from the outset, the Doka formwork experts have been supporting the joint venture [981 Hochtief, Adam Hörnig and GERDUM & BREUER] with know-how and sophisticated formwork solutions, so as to deliver the required superior quality of fair-faced concrete," says Doka On the viaduct, there will also be a Y-branch, and the complex overpasses call for four abutments of up to 8m in height.

A combination of two different Doka timber beam formwork systems is being used to construct the four abutments: some of the completely factory-assembled wall formwork FF20 was fitted with extra board-type facing by the Ready-to-Use Service at Doka's Leipzig Branch to be sure of meeting the fair-faced concrete requirements.

"In addition, gangs put together from the large-area formwork Top 50 'construction kit' are ensuring excellent adaptation to the integrated bridge pier cap, and to the wall pillars which also have to be formed. Here too, the formwork units were assembled by the Doka Ready-to-Use Service and delivered to the site ready for operation. Both systems work together perfectly and complement one another seamlessly so as to ensure swift construction progress.

"In order to complete the 220 hollow piers on schedule, the jv is working with three complete sets of large-area formwork Top 50 as the starter formwork, and another five sets of climbing formwork. The perpendicular piers are rectangular in shape, with corners bevelled by 50cm. With a circumferential wall thickness of 30cm, they measure 6m in the transverse direction of the bridge and 2.7m or 3.5m in the longitudinal direction," says Doka.

For more information on companies in this article

Related Content

  • Mexico viaduct complete with ULMA formwork
    February 9, 2018
    ULMA developed a comprehensive solution for the construction project of the Interlomas Viaduct, México. Forming part of Mexico City’s transportation infrastructure development plan, this viaduct is 227m long and connects the residential and commercial area Interlomas with the Naucalpan-Toluca highway. ULMA designed a solution fully tailored to meet the pace and needs of the client: gantry falsework for two 59m outer spans, and a CVS Form Carrier for the central span of 108m. ULMA’s engineering team combi
  • Paschal weighs in with its NeoR lightweight
    October 19, 2022
    Paschal’s new multi-purpose panel of the NeoR lightweight formwork is no lightweight when it comes to strength and versatility. Thanks to the additional perforated profiles, the multifunctional panel has a wide range of possible uses and, in addition to its classic use as wall formwork, can also be used for props, 90° corners and end stops.
  • PERI's tall order in Mexico
    February 14, 2012
    The Baluarte Bridge (Puente Baluarte), part of a major highway project, ranks among the most outstanding infrastructure projects ever constructed in Mexico.
  • The Mersey Gateway bridge project continues on schedule
    October 18, 2016
    Work continues on the 2.3km Mersey Gateway signature bridge project close to Liverpool in the UK. David Arminas reports on some of the construction highlights. Under construction is a cable-stayed structure with three towers that will span the Mersey River’s expansive mud flats between the towns of Runcorn and Widnes near Liverpool. Including the approach viaducts on each side, it will be 2.3km long with a river span of 1km. The main bridge deck will be reinforced concrete. The 80m-high central tower will b