Skip to main content

Bolivia tunnel and highway project under construction

In Bolivia work is progressing on the strategic Incahuasi tunnel project – Mauro Nogarin writes In southern Bolivia, the Bolivian Highway Administrator (ABC) is supervising the construction of the Incahuasi Tunnel and Monteagudo-Muyupampa-Ipati road. This work is of fundamental importance for the country as it will improve the flow of traffic and boost trade between the departments of Santa Cruz and Chuquisaca. The Monteagudo-Ipati highway project includes the Incachuasi tunnel which has a length of 96km
February 9, 2017 Read time: 4 mins
Securing the sides of the hillsides will lessen the risk of future landslips

In Bolivia work is progressing on the strategic Incahuasi tunnel project – Mauro Nogarin writes

In southern Bolivia, the Bolivian Highway Administrator (ABC) is supervising the construction of the Incahuasi Tunnel and Monteagudo-Muyupampa-Ipati road. This work is of fundamental importance for the country as it will improve the flow of traffic and boost trade between the departments of Santa Cruz and Chuquisaca. The Monteagudo-Ipati highway project includes the Incachuasi tunnel which has a length of 96km. The work will require a state investment of US$126 million, financed partially by a $75 million grant from the Andean Development Corporation (CAF), while the balance of the cost is to be paid for by the Bolivian Government.

The Incahuasi Tunnel is being built by the construction company 1390 Jose Cartellone. At over 1km in length it will be the second longest tunnel in the country and forms part of the 'Diagonal Jaime Mendoza'. This is another corridor linking Machacamarquita (Oruro) with Hito Villazón on the border with Paraguay, passing through the city of Sucre. The construction of the road project has been divided into two sections: section I Monteagudo-Muyupampa with a length of 49km at a cost of $47 million; section II, Muyupampa-Ipati, which measures 45km in length.

The Incahuasi Tunnel has a length of 1,260m and is located in the southern region of Bolivia and is part of "Integration Corridor Diagonal Jaime Mendoza". It is part of the Machacamarquita - Sucre - Hito Villazon Road, which runs to the border with Paraguay.
To date, the work is around 22% complete. The tunnel is the central link that will help speed up the transit of heavy and light vehicles from the highlands toward the valleys and plains. This will deliver a new transport corridor to the borders with Paraguay and Argentina, with the aim of increasing trade to and from Bolivia.

From a geological point of view along the path of the tunnel, there are three predominant composed lithologies: sandstone, siltstone/lutite and arkose/greywacke. These are present in greater or lesser extent in all the formations analysed and displayed with a certain alternation. The contractor is using the well proven NATM excavation method to drive the tunnel, as this allows lower working costs and delivers high productivity in this type of rock composition.

The contractor is using a 325 Sandvik DX 500 drilling rig as well as three jumbo units from 161 Atlas Copco featuring two and three booms for the tunnelling work.

For the sections being driven into competent rock, pass lengths range from 3-5m, while in the weaker areas, pass lengths have been reduced to 1-2m. For the execution of the main slopes of the entries in the North and South it was held against a bolthole by a grid of 3x3m2 with passive bolts, 25x 6m long. As an additional measure to the front slope, electro-welded mesh 100 x 100 x 8 and a layer of shotcrete 15cm thick was placed.
The tunnel is being constructed with a longitudinal ventilation system with eight vents at one end and six on the other.

The Spanish company Arias Hermanos is in charge of the construction of Section I of the Monteagudo-Muyupampa road, which is 49km long. This stretch of the road traverses an area with hilly and mountainous topography, creating less than optimal traffic conditions. With a planned maximum vehicle speed of 80km/h, a maximum slope of 8% is considered to be suitable along the whole section, with the exception of the Beltway around Monteagudo where there is an 80m stretch featuring a slope of 9.45%.

The cross section of the road has a two-way carriageway 7.3m wide, with two lanes that are 3.65m wide and berms that are 1.5m wide. The pavement structure is composed of a 50mm asphalt layer featuring modified polymers, a 200mm base layer, a 200mm sub-base layer and a 300mm sub-grade layer composed of 50% bank material. This section also has five bridges with lengths varying from 10-20m.

The Section II, Muyupampa - Ipati, is being handled by contractor Jose 3648 Cartellone Company and is 47km long. This route traverses an area with hilly and mountainous topography, and through a fairly thick forest that has a sandy clay soil characteristics. This section also contains eight bridges with a length ranging between 11-150m.
The maximum slope is 8% starting at the exit to the Incahuasi tunnel, and the section radii of horizontal curves are within the requirement for the standard minimum radius of 65m. The maximum slope of the road is 8%, which is fulfilled throughout the entire stretch. The cross section of the tunnel is 7.3m wide and is designed for two-way traffic. The design has two lanes that are each 3.65m wide. This stretch also has the same pavement structure as used in Section I, with a PMB-type asphalt layer of 50mm, a 200mm base layer, a 200mm sub-base layer and a 300mm thick sub-grade, 50% of which is taken from bank material.

For more information on companies in this article

Related Content

  • Dual layer, hot to hot paving at German airport
    August 18, 2015
    An airport in Germany has seen the use of very innovative asphalt paving techniques, with the use of dual-layer, hot-to-hot working. The method was used to meet a very tight schedule for the runway rebuilding work, while also delivering the high quality required. Two InLine Pave trains from Vögele were used at Rostock-Laage Airport to lay a new surface and binder course. The operation was innovative as the process used both hot-to-hot, echelon paving as well as dual layer, hot-on-hot working. Using this
  • Construction work is underway on a new highway in Bolivia
    July 19, 2012
    In La Paz, Bolivia, work is underway to create a new four-lane highway between Oruro to the capital La Paz. The 210km stretch of road, high up in the Andes, is of great political importance with President Evo Morales determined to see completion before the next elections in 18 months’ time.
  • Major bridge widening project going to plan
    April 11, 2012
    When built it was determined that a vital US road/rail bridge would always be widened. Work on that huge project is going to plan as Patrick Smith reports One of the biggest bridge widening projects in the world is being carried out under an ambitious development programme. At US$1.2 billion, the seven-year scheme to widen the Huey P. Long Bridge in the US state of Louisiana is also the largest of 16 projects planned under the state's TIMED (Transportation Infrastructure Model for Economic Development)
  • Major bridge widening project going to plan
    May 2, 2012
    When built it was determined that a vital US road/rail bridge would always be widened.