Ageing Liberty Tunnels in US refurbished with hydrodemolition

Hydrodemolition surface preparation keeps Liberty Tunnel rehabilitation project on schedule in Pittsburgh. The Pennsylvania state Department of Transportation selected hydrodemolition surface preparation for the US$18.8 million rehabilitation of Pittsburgh’s Liberty Tunnels. Time was of the essence to complete the project on deadline without penalties and hydrodemolition was selected as it offered a fast and cost-effective method to prepare the tunnel walls for a new, shotcrete surface. This methods off
May 13, 2015 Read time: 4 mins
Two Conjet Robot 363 hydrodemolition machines have been adapted to suit the curvature of the horseshoe shaped walls of the twin Liberty Tunnels
Hydrodemolition surface preparation keeps Liberty Tunnel rehabilitation project on schedule in Pittsburgh

The Pennsylvania state Department of Transportation selected hydrodemolition surface preparation for the US$18.8 million rehabilitation of Pittsburgh’s Liberty Tunnels. Time was of the essence to complete the project on deadline without penalties and hydrodemolition was selected as it offered a fast and cost-effective method to prepare the tunnel walls for a new, shotcrete surface.

This methods offers quick concrete removal and easy clean-up, meaning that contractors can work faster than with conventional concrete removal methods. This allows the team to work within a narrow time slot and avoid heavy penalties for not opening the tunnel to traffic when required. In addition, no damage or cracking of the tunnel walls occurred using hydrodemolition, as may be the case when breaking equipment is employed instead.

The project is intended to increase the service life of the Liberty Tunnels as well as reduce maintenance cost, increase visibility for drivers and repair deterioration from 90 years of wear and tear. And the project has been extensive as the area targeted for refurbishment equated to 20,000m2.

Since the hydrodemolition began, commuters have experienced few delays as this method makes it possible to remove concrete during a night time closure from 10pm to 6am. The specialist work has been carried out by specialist subcontractors HTNE Hydrodemolition Service and Hydro-Technologies. Meanwhile Swank Construction is general contractor for the Liberty Tunnel project.  

The twin Liberty Tunnels measure 1,795m long and allow motorists to travel between the South Hills of Pittsburgh and the city, through Mount Washington. There is an inbound tunnel and an outbound tunnel, each with two lanes of traffic and this link was constructed between 1922 and 1924, with the connection having aged since that time. When planning began for the repairs it was clear from the outset that the work would be difficult as the link carries around 48,000 vehicles/day.

Every night the hydrodemolition equipment and crews have had to enter the tunnel as soon as it shut the closure and get as much done as possible before shutting down the equipment, cleaning up debris, then exiting before the 6am opening. If the tunnel had not been opened by 6am, the contractor would be assessed liquidated damages of US$7,800/hour until the tunnel was opened to traffic. That left only eight work hours/night to carry out the work.

The method uses a high-pressure water jet operated by a hydrodemolition robot. On the Liberty Tunnel project, two Conjet 363 vertical robotic units performed partial depth, selective removal hydrodemolition on the tunnels’ vertical wall horseshoe profiles that have 4.42m posted vertical clearance. The 186 Conjet 363 vertical hydrodemolition machines have water jets controlled by a technician over the entire surface of the tunnel walls. The flow rate, pressure, dwell time and cutting head are computer-controlled to provide the ideal settings required to selectively remove deteriorated concrete while leaving the sound concrete intact.

The Conjet robot is said to be versatile and can carry out high-speed, selective, vibration free removal of damaged concrete. Powered by an 11kW electric motor, the Robot 363 unit can handle the rotors and the oscillation tools efficiently. It can withstand reaction forces working with high-pressure pumps rated at up to 550kW, while the removal area can be as wide as 2m. The machines are also versatile and can also make two separate cuts with different depths and widths simultaneously. After the units have carried out material removal, the surface is water-blasted to provide a high quality surface ready for shotcreting.

Hydrodemolition in the US was initially used on bridges, but is now used on bridge decks, or wherever deteriorated, reinforced concrete has to be removed by the owner to rehabilitate and preserve a structure. And in the US, the 2535 Pennsylvania Department of Transportation is using hydrodemolition for a wall rehabilitation project on State Route 51.

For more information on companies in this article

Related Content

  • Milling a runway surface
    May 26, 2023
    Milling machines from Wirtgen were used as part of the successful project to resurface a runway for Leipzig/Halle Airport in Germany
  • Prized recycling
    June 13, 2012
    Wirtgen has won the US Cold Recycling Award 2012 for applying its cold recycling structural road rehabilitation technology on Interstate I-81 in eastern America. The I-81 is one of the major north-south routes running across Virginia state with two lanes in each direction. Increasing traffic volumes and the loads imposed by heavy-vehicle traffic were said by the Virginia Department of Transportation (VDOT) to have left the pavement surface covered with alligator cracks, wheel ruts and patches where minor re
  • Securing safer transportation infrastructure through non-destructive technology
    June 16, 2014
    Kevin Vine reports on the use of non-destructive testing for structural analysis of bridges Seven years ago, the overpass collapse in Laval, Québec that led to the death of five people brought to light severe issues with the state of the country’s bridges and transportation infrastructure. More recently, a crack in the Champlain Bridge to Montreal that forced over 160,000 commuters to find alternate routes to work reaffirmed a need for greater emphasis on early detection before a crisis occurs.
  • Busy UK motorway junction demolished in tight time frame – Mark Anthony reports
    October 18, 2012
    Military-style planning and overwhelming demolition firepower ensured that Armac Group avoided financial penalties and the wrath of drivers on one of the UK’s busiest motorway intersections. Demolition & Dismantling reports. 6 January is traditionally known for the visit of the three wise men to Bethlehem. However, on 6 January 2012, three wise demolition engineers from Armac Group was tasked with dismantling the monumental structure known as Catthorpe Viaduct: the main overbridge of the M6/M1/A14 interc