African Development Bank funds road to Africa’s largest wind farm

Shem Oirere discusses a new road connecting with a wind farm development in Kenya The African Development Bank will provide 45% of the funding needed for the rehabilitation and rebuilding of a new 200km road which leads to Africa's largest wind farm project, located in northern Kenya. The bank said the $13.5 million grant for rehabilitation of the existing Laisamis – Ngurunit – llaut - South Horr – Loyangalani road- will be provided by the Government of the Netherlands. The bank says works on the road will
February 20, 2014 Read time: 4 mins
The new road in Kenya is being built along the route of an old road and will connect with Africa’s largest wind farm development
Shem Oirere discusses a new road connecting with a wind farm development in Kenya

The African Development Bank will provide 45% of the funding needed for the rehabilitation and rebuilding of a new 200km road which leads to Africa's largest wind farm project, located in northern Kenya. The bank said the $13.5 million grant for rehabilitation of the existing Laisamis – Ngurunit – llaut - South Horr – Loyangalani road- will be provided by the Government of the Netherlands. The bank says works on the road will cost a Total of $30.4 million and entails, “…light and heavy excavation, gravelling, reconstruction of some sections, light grading and improvement of drainage structures.”

The remaining $16.9 million will be provided by Lake Turkana Wind Power (LTWP), the consortium developing the 300MW wind farm at Loiyangalani in Marsabit County. The consortium comprise of KP&P BV Africa, Aldwych International Limited, Vestas Wind Systems A/S, Norwegian Investment Fund for Developing Countries (Norfund), Industrial Fund for Developing Countries (IFU) Denmark.

LTWP will construct the road jointly with two road agencies- Kenya Rural Roads Authority (KeRRA) and the 2639 Kenya National Highways Authority (KeNHA)- starting in the first quarter of 2014. A contract has been awarded to Civicon Kenya, a subsidiary of TransCentury, a Kenyan investor in infrastructure projects. KeRRA operates the 131km Laisamis-South Horr (D371) section while KeNHA operates the 64km South Horr-Loiyangalani stretch.

“The upgrading of the road is primarily to support this unique project and to allow for the wind turbines to reach site,” said Lilianne Ploumen, Minister for Foreign Trade and Development Corporation of the Netherlands. “However, the road will open the entire area for further development and improve accessibility to all the local communities,” she added.

LTWP says the construction works would entail realignment, levelling and grading, construction of culverts and general repairs of the section between Laisamis – Illaut – Kargi Junction (D371) and Kargi Junction – Loyangalani Road (C77). The road will be 6m wide with a 5m road reserve to each side.

The road branches off from the main A2 Isiolo-Moyale road at Laisamis as D371 in a northerly direction and passes through various centres which include Namarei and Illaut.

From Kargi Junction the road becomes C77 after joining the main road from South Horr and continues all the way to Loyangalani town, the site of the $820 million wind farm project. LTWP says the entire stretch “is a murram road that is marked by low lying terrain lying between numerous hills and dry sand riverbeds.”

“The main output of the work is a drivable standard engineered gravel road with a gravel running surface, road Cross drain comprising of culverts and perforated drifts.”

LTWP abandoned an earlier option of pursuing a 281km route of Marsabit – Kargi – Loyangalani which branches off from the main Isiolo – Marsabit road.

Although the road has what a project environmental impact assessment report said, “…is reasonable horizontal geometrics with long straight sections and curves with large radii,” the route was found unsuitable because it, “…has unfavourable vertical curves, is poorly drained although in most sections the alignment is free draining.”

LTWP says the route was also abandoned because, “There was no guarantee for the availability of adequate construction materials since the alignment soils are mostly loamy sands.”

“Strengthening of the route will be more expensive than the proposed Laisamis – South Horr – Loyangalani road. The Kargi route would also lengthen the haulage distance of the wind farm equipment by an additional 50km, the distance to the takeoff point from Isiolo on the Isiolo - Marsabit road.”

The consortium said the option also did not show evidence of availability of adequate water needed during construction work
LWTP instead opted for an alternative route of Laisamis – Ngurunit – llaut - South Horr – Loyangalani. The route was supported by Kenya’s environmental regulator, National Environmental Management Authority.

The road branches off from the main Isiolo - Marsabit road at Laisamis town and runs 196km in a northerly direction.

Because the route passes through the settlements of Ngurunit, South Horr and Kurungu, it was agreed between LTWP and the communities that it be modified to avoid the settlements and ease transportation of the heavy wind farm development equipment.

The road will, therefore, have two diversions. The first diversion is the 19.6km Namarei to Illaut section, which avoids the Ngurunit settlement area, and has flat and rolling terrain, making it a viable route to use.

The diversion avoids the 34km stretch through Ngurunit market (saving 14.4km), and transportation over a hilly undulating terrain “which have acute bends and rocky terrain.”

This route is an old disused road which will require drainage to be improved and be rehabilitated.

For more information on companies in this article

Related Content

  • Serbia road project, funding secured
    February 19, 2019
    Construction of the 77km-long Merdare-Nis highway in Serbia is to benefit from external financing. A funding package worth €100 million is being supplied by the European Investment Bank (EIB) for the project. The funding will pay for work on a stretch of the route between Plocnik and Nis in southern Serbia. The highway will improve transport connections with neighbouring Kosovo when it is complete. This project forms part of a series of road building operations in the region, with extensive work having been
  • Kenya highway projects now underway
    April 7, 2017
    Work on two major highway projects are now commencing in Kenya. One project will improve the road connection between Kenya’s capital Nairobi, with its premier port of Mombasa. The other project will see the upgrade of the road link joining Kenya with neighbouring Uganda. Work on the Mombasa to Nairobi highway is starting on a 42km stretch between Mombasa and Marikani. This work is costing some US$213.4 million and the improved route will feature two lanes in either direction when the work is complete. Meanw
  • Curved girders for the Gaasperdammerweg A9 section in Amsterdam
    May 22, 2018
    Dutch authorities recently needed to add traffic lanes to two flyovers at the Holendrecht junction on the Gaasperdammerweg section of the A9 motorway in Amsterdam It was in November 2014 that the Directorate-General for Public Works and Water Management of the Netherlands Rijkswaterstaat awarded the A9 Gaasperdammerweg public-private-partnership project to IXAS Zuid-Oost, a consortium consisting of Ballast Nedam, Fluor, Heijmans and 3i Infrastructure. The A9 Gaasperdammerweg project is the third section
  • SMEC is working on two key projects in Australia
    February 28, 2013
    SMEC is now working on two key projects in Australia. The company has been awarded the contract administration services contract for the Horse Park Drive extension in Canberra by the Australian Capital Territory Government. It has also won the intersection upgrade project in New South Wales. The project in Canberra involves construction of the final section of Horse Park Drive from Burrumarra Avenue to Mirrabei Drive in the Gungahlin area. On completion, the road will connect the new residential areas of Ja