Skip to main content

Increasing quarry efficiency in Senegal

Every year, three million tonnes of basalt rock, from gravel to riprap, are taken from the Gécamines Quarries in Diack, Senegal, for use in public and maritime work sites. The quarry also produces around 500,000tonnes of limestone for use in cement factories and construction projects in the region – making the site essential for infrastructure development in West Africa.
November 2, 2022 Read time: 4 mins
The Senegal quarry has boosted efficiency by using Topcon technology

To address the challenges presented by this intensive operation, the company handling the quarry works, Vicat Group, required a bespoke weighing solution to ensure operations continued to run smoothly.

Across northern, western and central Africa, Topcon has already provided products to meet the needs of its clients in the field, through its partner SmartFleet – a subsidiary of BIA. Working collaboratively, the two organisations have been able to offer a service that meets the needs of differing territories.

Vicat Group required a weighing solution that was easy to learn and operate. Topcon worked with the company to design a simplified version of its Loadmaster Alpha 100 weighing system – providing a solution tailored to Vicat Group’s needs.

This system offers a simplified user interface, designed specifically so any loader can pick up and operate with ease. This new system is also currently being trialled on other sites across Senegal.

Jean-Yves Chouteau, director of the Gécamines Quarry (Vicat group) in Diack, Senegal said, “We required a weighing solution to equip our loaders that was simple to use. Topcon worked with us to design such a solution, which brought together one of its own products with a bespoke weighing system specific to our needs.”

The bespoke system was designed to enable workers to load trucks quickly and efficiently using a QR reader and beeper that indicated to the driver when the correct amount was reached. This ensured that the truck was loaded properly in the first instance, which was confirmed by the weighbridge. Without these types of systems, it is common for trucks to be under- or overloaded, which wastes time spent travelling back and forth between the quarry and weighbridge, as well as presenting a significant safety risk.

Topcon was able to deliver a solution to meet the needs of its client in Senegal
Topcon was able to deliver a solution to meet the needs of its client in Senegal

Following the introduction of Topcon’s bespoke solution, the average travel time for each truck decreased by approximately 30 minutes, a huge time saving for teams on the ground. Jean-Yves commented: “Since we load between 250 and 400 units/day, this solution has helped us save a significant amount of time and cut down on fuel consumption.

“Moreover, Article 14 of the West African Economic and Monetary Union treaty states that the overloading of trucks must be limited as much as possible to prolong the durability of roads, meaning our new weighing solutions are also benefitting the impact on local infrastructure. The training undertaken by the loader operators has contributed to an increased understanding of weight allowance to prevent this overloading from occurring, which will help inform our working practices going forward.”

The partnership between Topcon and SmartFleet was a crucial part of the success of this project. Not only does SmartFleet represent Topcon across the region in providing quality support and service to customers, but its network of technical experts act as an on-the-ground presence at customers’ work sites.

Fabrice Simon, sales support manager at Topcon for Africa and the Middle East, added: “The Gécamines quarry in Diack is one of our most important sites in terms of onboard weighing in Africa and our partnership with SmartFleet was crucial to the success of this project due to its understanding of the needs of local markets.

“Having a presence on the ground also allowed us to offer 24/7 support, with the ability to receive and adapt to feedback in real time. This meant we could quickly intervene in case of any issues, offering additional peace of mind.”

To date, Topcon and SmartFleet have supported the Vicat Group through the provision of eight weighing systems – four of which are equipped with the bespoke QR code system. Additionally, five loaders equipped with Topcon technology, directly connected to the computerised weighing systems, have also been provided and work with the existing Vicat ERP system. Two Loadmaster Alpha 100 systems have also been installed at Vicat’s outside warehouses for control purposes.

As the project continues, the companies hope that an additional seven systems will be delivered by the end of the year, with further projects planned for the future.

For more information on companies in this article

Related Content

  • Bentley Systems is advancing construction software technology
    January 15, 2016
    Bentley Systems has unveiled a wealth of new construction software technologies that can help optimise the progression of road projects - Mike Woof writes A host of new tools and software developments from Bentley Systems will help designers and construction firms deliver projects more quickly and efficiently. Senior vice president for Bentley Systems is Bhupinder Singh and he explained, “Our users are using more software and more devices than ever before and they’re creating more data.” He said that
  • Machine Control sector is the place for acquisitions
    January 22, 2014
    The machine control sector has been lively in recent months with a major acquisition, the unveiling of new software innovation and landmark testing of new technology to monitor paving temperature. Guy Woodford reports The state road construction authority in the German state of Saxony-Anhalt (LSBB Saxony-Anhalt) has become the first nationally to test MOBA’s new PAVE-IR Scan temperature measurement system at a works site.
  • The Cebu–Cordova Link Expressway
    September 19, 2021
    The 8.5km CCLEx, as it is known, will include the longest and tallest bridge in the Philippines when the structure is finished next year
  • Weigh in motion systems aid safety, reduce costs
    February 14, 2012
    Advanced weigh-in-motion (WIM) systems can offer a quick payback time