Runway resurfacing in Brussels

Years of heavy use meant that runway 25 at Brussels Airport required attention, with a full resurfacing needed. Smooth runways are vital for large international airports as they optimise safety and reduce wear and tear on expensive aircraft, in addition to boosting comfort for airline crews and passengers.
April 2, 2021 Read time: 3 mins
Using the Topcon 3D tools allowed the work to be completed ahead of schedule, while delivering the high quality required for the airport runway

The 3.3km-long by 45m-wide runway 07L/25R at Brussels Airport was in need of a complete renovation. High usage meant that this renovation would have to be conducted quickly, accurately and safely. The airline authorities brought in general contractor Willemen Infra to handle the project, with the specialist sub-contractor Top-Off being brought in to handle the milling work.

Despite numerous challenges facing the project, not least the constraints associated with minimising airline disruption, the runway was ready for operation again in just over one month.

Phillipe Grevendonck, project development manager at Topcon, said: “When Top-Off asked us to assist with this renovation project, we didn't hesitate. The time pressure was high, because the runway closure had to be kept to a minimum. The quality requirements were, of course, exacting: the runway must ensure safety, and we had to extend the life of the asphalt layer by preparing a flat foundation and ensuring an optimal milling finish.

“We helped Top-Off with the preparation and start-up at the worksite, as well as with the calibration of the machines. Where necessary, we also carried out the position checks, because milling requires precision, whilst remaining on standby during the work, to support Top-Off as necessary.”

The volume of milling was significant. John Vastmans, CEO of Top-Off explained “We placed two new layers of asphalt on the runway, which amounted to 222,000m2 and about 60,000tonnes.  The work had to be 90% done in just five days. That is to say: we milled at a rate of more than 10,000tonnes/day.”

Top-Off’s team started by milling the old asphalt layer off the runway in order to apply the new asphalt onto an optimal terrain model. Grevendonck explained: “The 3D model supplied by Brussels Airport Company ensured the best possible sub-foundation for the new asphalt layer.”

Precision milling using the Topcon 3D systems was carried out to provide an accurate base to lay the new asphalt layers on top
Precision milling using the Topcon 3D systems was carried out to provide an accurate base to lay the new asphalt layers on top

When it came to milling, Topcon’s 3D millimeter GPS system had an impact on the efficiency of the project. The solution combines the advantages of laser and GPS systems.

Vastmans said: “With millimetre GNSS, we had the advantage that all the machines could make use of a single laser, which not only made the system easy to use but also saved costs.”

“If the laser beam is interrupted, the system can continue to operate for about four seconds based on its last corrections. If it takes longer before the obstruction clears, the use of the rotating laser allows a connection to be established again. The biggest advantage of this is the huge time savings. In the vertical plane we have a 10m window in which we can work with a single laser. So, in that regard, we have almost no restrictions.”

Vastmans added: “Repaving with new asphalt had its challenges too, mostly because at the Brussels Airport worksite there was non-stop movement.”

Grevendonck elaborated “There was a point where there were 20 excavators, 30 dump trucks, 20 trailers and five milling machines all there at the same time. There were always five lasers set up on the project. All machines could select a laser of choice within reach. One laser could give guidance to multiple milling machines simultaneously."

Work also had to be conducted on the sewer pipes, which imposed an even tighter deadline. Vastmans added “With the solutions utilised, milling out of the contours for the sewer basins also went smoothly.”  

With the help of Topcon’s MM GNSS system, the project was completed ahead of schedule. “It went very well,” said Jan Eikenaar, site manager for Top-Off. “We finished ahead of schedule. That’s always a favourable position to be in. The customer is very satisfied. Our work was grade-checked, and we remained well within the error margin.”

For more information on companies in this article

Related Content

  • Micro surfacing the Brooklyn Bridge with Bergkamps’ M210 paver
    May 16, 2018
    A major job for micro surfacing took place on the Brooklyn Bridge near New York. It was the third time in Ken Messina’s career that he would provide micro surfacing for the iconic Brooklyn Bridge, built in 1883. Messina, as president of New Jersey-based Asphalt Paving Systems (APS), knew only too well the challenges that lay ahead. And there were many. There would be only a brief window of opportunity for paving, with lane closures starting at 10pm and ending at 5am. The cool, humid atmosphere would a
  • Road recycling developments coming to market
    March 22, 2017
    Major manufacturers are introducing new machines for road milling and recycling that will boost output and lower the cost/m - Mike Woof writes New machines for milling and road recycling will offer increased performance and productivity than earlier generation equipment. Higher quality cutting will help contractors achieve smoother surfaces and considerably lower paving costs also. Meanwhile new recycler/stabiliser machines will offer a better cost/m and improve the economics of road recycling for contra
  • Topcon beefs up eXchange AutoCAD 3D civil engineering software
    March 10, 2015
    Topcon’s latest eXchange software add-on for AutoCAD Civil 3D civil engineering design software converts data into files compatible with Topcon 3D construction solutions as well as the MAGNET software system. The add-on even converts complex road designs with defined corridors into Topcon standard file formats, such as MJF (MAGNET Field job) for land surveying and construction layout, and TP3 (3D Topcon Project File) for machine control systems. After installation, users are offered the ability to log in to
  • Sophisticated machine telematics packages offered
    September 27, 2013
    Several of the major equipment manufacturers now offer sophisticated telematics packages fitted as standard to their machines. Caterpillar and Komatsu were amongst the leaders in this field, allowing a high level of access to a machine's systems and sub-systems for performance monitoring, maintenance management and geofencing purposes for example. To the customer this offers the chance to address fleet running costs and utilisation, reduce the risk of theft and increase overall efficiency. Customers can eve