Machine guidance system aids asphalt runway construction

Automatic 3D machine guidance is a highly sophisticated area and a high level of expertise is often required to ensure applications of the advanced technologies work as desired. Fugro is a specialist firm that has gained experience using 3D guidance tools over many years and for certain tricky projects, Hexagon, the parent of Leica Geosystems, has turned to Fugro for assistance. For one difficult job in particular, Fugro's specialists were brought in at the request of an Icelandic contractor. The project ca
July 16, 2012 Read time: 3 mins
Fugro supplied specialist surveying skills to help the contractor meet the tight specifications for the project to resurface an airport runway in Iceland
Automatic 3D machine guidance is a highly sophisticated area and a high level of expertise is often required to ensure applications of the advanced technologies work as desired. Fugro is a specialist firm that has gained experience using 3D guidance tools over many years and for certain tricky projects, Hexagon, the parent of 265 Leica Geosystems, has turned to Fugro for assistance.

For one difficult job in particular, Fugro's specialists were brought in at the request of an Icelandic contractor. The project called for the construction of a new runway for Akuryi Airport in the north of the country. Because the runway was to be surfaced with asphalt, the project faced a very limited time window when the work could be carried out. As its name suggests, the island of Iceland is a cold country and there is generally only one month in the year when the temperatures are moderate enough to permit asphalt paving.

The new runway is 2km long by 60m wide and to allow the work to be carried out the job had to be split into two. The first portion of the surfacing work was carried out in 2008 with the second half having been carried out this year.

The first task was to mill off the old surface using planing machines, with the contractor then laying the new asphalt in two layers. Because the surface is for an aircraft runway the contractor had to meet strict requirements for surface smoothness, skid resistance and compaction density. To ensure that the last factor in particular could be achieved, the contractor had to pay careful attention to the weather conditions, as asphalt cannot be compacted effectively to a suitable density when the temperature drops below 5ºC. This is because the asphalt cools too quickly for the compaction rollers to carry out their work.


To ensure that the paving and compaction operations could be carried out effectively within the tight time-frame, the 3D system has to take all the various parameters into account.
Fugro carried out the surveying activities necessary for automatic machine guidance. These included equipment testing, carrying out measurements and altering the design for the machines being used. Due to the short lead time, five surveyors worked continuously for three weeks in shifts for 24 hours/day. And the 24 hour working was possible because in Iceland, it does not get dark at night during summer. For one week the work could only be carried out during the night, to prevent disruption to daytime air traffic.

For more information on companies in this article

Related Content

  • Bitumen technology suppliers seek new ways to save money and work more efficiently
    April 24, 2013
    When World Highways decided to ask some of the industry’s leading suppliers what the future holds for bitumen, we found out - not surprisingly in the current economic climate - that it’s all about saving money. Kristina Smith reports. How quickly the tide turns. Just two years ago, saving carbon and the planet was moving up many countries’ political agendas. Now politicians in Europe and beyond have been forced to park commitments in the face of economic austerity. “The big issue with local government is th
  • Highway widening project for the US
    April 19, 2018
    A highway widening project in the US state of New Hampshire is being assisted by the use of a gravity-fed asphalt paver. The widening work is being carried out as part of an upgrade for a 32km stretch of I-93, which was started eight years ago. The work is being carried out for the New Hampshire Department of Transportation (NHDOT) on a section of the highway between Exits 1 and 5 from the Massachusetts Stateline to Manchester, NH. According to NHDOT, the project involves widening I-93 from two lanes in
  • High speed bridge demolition minimises disruption
    February 16, 2012
    A high speed bridge demolition project has been carried out successfully in Germany. Speed was of the essence as the bridge spanned an important road link and had to be removed in a tight time frame, minimising disruption to traffic.
  • Major upgrade for Chicago O’Hare Airport
    August 14, 2015
    Internationally, airports are being upgraded and expanded to increase capacity and safety – Mike Woof writes. All around the world, airports are being expanded and upgraded, both to cope with massive increases in passenger numbers and also to handle larger aircraft. Runways have to be rebuilt with stronger structures and surfaces to handle greater air traffic volumes as well as increased loads from larger aeroplanes. Building airport runways, however, poses many challenges for construction crews. Paving qua