Swiss mini-motorways made bigger

Widening the busy A4 road in Switzerland to four lanes was achieved quickly by using the latest paving technology. Increased traffic required the widening of the A4 from two to four lanes along a 20km section, with two lanes separated by a central divider in each direction. Carrying 20,000-25,000 vehicles/day, the trunk road between Winterthur and Schaffhausen was one of Switzerland's busiest two-lane stretches, and as a result, the Federal Council of Switzerland in Bern planned an enlargement of the dual-l
July 10, 2012 Read time: 2 mins
Precision paving was achieved in Switzerland using the latest machine control technology on a Vögele machine.
Widening the busy A4 road in Switzerland to four lanes was achieved quickly by using the latest paving technology.

Increased traffic required the widening of the A4 from two to four lanes along a 20km section, with two lanes separated by a central divider in each direction.

Carrying 20,000-25,000 vehicles/day, the trunk road between Winterthur and Schaffhausen was one of Switzerland's busiest two-lane stretches, and as a result, the Federal Council of Switzerland in Bern planned an enlargement of the dual-lane A4 trunk road to the Swiss four-lane mini-motorway requirement. These mini-highways, for instance, feature narrower carriageways and do not have hard shoulders for their whole length.

Swiss contractor 2552 Implenia used a 1194 Vögele SUPER 2100-2 paver equipped with the firm's sophisticated Navitronic Plus 3D control system and this helped speed the work and deliver the accuracy required. The contractor's paving crew was working with the Navitronic Plus system for the first time and the job in hand was to place the foundation layer and base course for the new lanes on the basis of a 3D model, without using physical reference lines.

For the A4, a hot-mixed foundation course was placed with a share of recycled asphalt ranging from 50-60%. On this job the Navitronic Plus system used sophisticated positioning equipment from Leica Geosystems. Based on the route's digital design data, this technology picks up the paver's actual position by a total station and a 360° prism. High-precision sensors on the paver supplied extra information on the screed's elevation and slope as well as the screed's position. The data was then passed onto the positioning system's external computer and a comparison was made with the route's stored design data. Any deviations detected were transmitted to the Navitronic Plus package to make the necessary corrections.

Tolerance requirements were met from the start. Despite using the system for the first time, the paving crew was able to meet the specified tolerance requirements of +/-4mm, placing the foundation layer and base course in a large width up to 9m without the need for tensioned guide wires.

For more information on companies in this article

Related Content

  • Premiere in the Black Forest
    October 5, 2023
    One of the steepest sections of the B 500, an important road in the southern Black Forest, had to be renewed in the summer of 2023 – more precisely: the first kilometres behind the Triberg town sign, past the famous waterfalls. Asphalt paving specialists from Gebrüder Bantle GmbH & Co. KG were commissioned to resurface the carriageway.
  • Paving tight corners on a racetrack
    May 12, 2021
    Vögele SUPER 1303-3i pavers have been used with great success on a challenging job site in Hemer, in Germany’s North-Rhine Westphalia. The machines were used in the construction of a new karting track. The contractor employed Vögele equipment for this project, paving tight bends over a length of 391.5m.
  • Bridge formwork solutions complete big bridge picture
    July 2, 2014
    Advanced bridge formwork solutions are allowing contractors to complete vital major highway infrastructure projects covering Norway, Sweden, Estonia and Poland. Guy Woodford reports Building the Labbdalen bridges in Norway is a key feature of the E6 highway improvement programme. Main project contractor HÆHRE tasked RMD Kwikform and Teknikk with supplying a complete formwork and shoring solution that could tackle the challenging Norwegian terrain, whilst preserving the environment. Situated two hours
  • Texas highway project tackles congestion
    April 10, 2012
    A new highway project in Texas will tackle peak congestion