The Misano racetrack in Italy has benefited from the use of the latest milling technology to deliver a new surface. Contractor Pesaresi Giuseppe decided to take advantage of the cutting-edge technologies of Wirtgen and Trimble. In less than three weeks, all irregularities were removed from the track, leaving it ready for motor sports racing. When the call for tender was issued to modernise the track, the construction of two new track sections was also planned. These plans included measures to boost safety
June 20, 2017 Read time: 2 mins
High quality and productivity were achieved on the Misano circuit upgrade
The Misano racetrack in Italy has benefited from the use of the latest milling technology to deliver a new surface. Contractor Pesaresi Giuseppe decided to take advantage of the cutting-edge technologies of Wirtgen and Trimble. In less than three weeks, all irregularities were removed from the track, leaving it ready for motor sports racing.


When the call for tender was issued to modernise the track, the construction of two new track sections was also planned. These plans included measures to boost safety as well as increase speed.

The goal was to pave around 5,000tonnes of new road surface, requiring 80 workers and 50 vehicles. In addition to changing the longitudinal and cross slope of the track, all existing undulations and other irregularities had to be rectified. The use of 3D technology was stipulated in the technical specifications during both the planning and the implementation phases, to ensure precision.

The milling depth needed to be adjusted with millimetre accuracy during the milling work to remove irregularities from the track. Pesaresi Giuseppe opted to use its 2395 Wirtgen W 210 cold milling machine for this job, together with a 3D solution from 2122 Trimble.

Once the terrain had been surveyed in collaboration with a topology and engineering construction company, the 3D terrain profile for the Wirtgen cold milling machine W 210 was created and uploaded. Equipped with the Trimble PCS900 Paving Control System, the W 210 was then able to use the 3D profile.

Trimble technology ensured instant transitioning between the individual total stations for uninterrupted milling work. As a result, no bumps were caused by the machine stopping on the track.

The use of 3D technology also speeds up job processing, as the trucks do not have to avoid stringlines or stakes and they can move faster and more easily on the surface when transporting material away.

Work was completed in 14 working days, allowing asphalt paving work to begin. Just four days later, the job was finished, on time and to specification.

For more information on companies in this article

Related Content

  • Dream machines: Machine technology takes productivity to new levels
    September 9, 2016
    The adoption of new technology will boost productivity for machinery users - Colin Sowman writes Since the inception of earthmoving machinery, equipment manufacturers have been striving to make the process faster, quieter, easier and more fuel efficient. Now many manufacturers are looking at ways to improve the efficiency of drive systems to reduce complexity, maintenance and fuel use.
  • The “rollercoaster in the dunes”: Circuit Park Zandvoort
    June 14, 2021
    Some projects are so specialist that there are hardly any construction companies with significant experience to draw on - another reason why it is so valuable to have a partner with the expertise and experience to take things forward. The rehabilitation and modification of the race track in Zandvoort was a project like this.
  • Advances in concrete paving technology will increase efficiency
    July 1, 2014
    New developments in concrete paving will increase working efficiency for contractors - Mike Woof writes The concrete paving market is a fiercely competitive segment of the off-highway construction machinery business. Although there are only a few key players in this niche market, the firms are constantly developing new systems, equipment and methods in a bid to help improve working efficiencies for contractors working in the sector. It is of note that the majority of the key players in the concrete pavin
  • Wirtgen paving technology takes off at Frankfurt
    February 27, 2017
    Time was at a premium for Wirtgen machinery when resurfacing the runway at Frankfurt/Main Airport Europe’s third largest airport, Frankfurt/Main, has new surface course on runways about every seven year, including the centre runway, the most-frequently used section.