Danish digging for Leica Geosystems’ 3D machine control

In Denmark’s northern Jutland, Leica Geosystems’ equipment is being used to help build a 40km motorway, one of the fastest-built such projects in the country’s history. The Danish Road Directorate is the client for the €5.4 million motorway between the two Danish cities of Herning, to the south with around 50,000 people, and Holstebro, a city of about 35,000 people, north of Herning. Preliminary ground investigations were made in 2013 and work started in 2015 with completion set for 2018.
October 26, 2017 Read time: 4 mins
Leica’s iCON gps 60 SmartAntenna is used for grade checking

In Denmark’s northern Jutland, 265 Leica Geosystems’ equipment is being used to help build a 40km motorway, one of the fastest-built such projects in the country’s history.

The 2284 Danish Road Directorate is the client for the €5.4 million motorway between the two Danish cities of Herning, to the south with around 50,000 people, and Holstebro, a city of about 35,000 people, north of Herning.

Preliminary ground investigations were made in 2013 and work started in 2015 with completion set for 2018. The motorway will connect the north-west of Jutland to a larger motorway network that accesses Denmark’s southern motorways and allows fast access to the rest of Europe.

Around 4 million m3 of soil has been excavated to form a cut through the landscape. It has given archaeologists a unique chance to explore the history of the ancient arterial road between Herning and Holstebro.

Leica Geosystems’ 3D machine control solutions are used for digging the search trenches to get a sideways and layered view of the deposits. This establishes if there are archaeological objects or material in the area and places them in chronological order.

Up to 600 people have been working on site. Leica Viva GS12 GNSS antenna together with the Leica CS15 controller automatically and precisely maps the findings. Archaeologists have on average made a finding for every 500m of digging. Objects have included a prehistoric sword dated around 600AD.

Glenn Lautrup is a foreman for MJ Eriksson Construction company that has the contract for 8km of the motorway near the village of Tvis. Products from Leica Geosystems are used on the entire project, both in the form of machine control solutions and products for grade checking and as-built documentation, explains Lautrup, who has worked on the project since August last year. On a typical day there are 10 dumpers, seven excavators, two bulldozers, one grader and three rollers as well as around 30 workers on the cut-through.

Up to 25% of the total budget for the motorway has been reserved for the preservation of nature. Around 650,000m³ of material has been excavated from nearby lakes for building the motorway. In the future, the lakes will be rehabilitated to create marshes and other lake areas. Several water channels and fauna passageways for hares, mice and frogs have been established. A 50m-wide fauna bridge - the largest of its kind in Denmark - has been built to allow red deer safe passage over the motorway.

Leica’s iCON gps 60 SmartAntenna is used for grade checking. Line Christensen is an engineer working with data preparation at MJ Eriksson’s office in Holstebro. Using Leica iCON office software, she prepares road models that are loaded into the machine control solutions. “I receive the 3282 AutoCad line file from the Danish Road Directorate,” she says.

“For this project, we are currently working on the 13th version of the file because there have been many changes to the project. I then use the Leica iCON office software to transform the AutoCad file to create triangulated files for the machine control solutions. Afterwards, I upload the file to Leica ConX, call the machine operator and tell him that there is a new updated file available.”

Line says that she visits the project daily to gain an understanding of what the operator needs in order for her to improve the preparation of files for them.

Heine Vendelbo is one of the MJ Eriksson operators who are in contact with Line. Vendelbo uses machine control systems on excavators, bulldozers and graders. He has been using machine control since 1985 and was one of the first people in Denmark to implement GNSS (Global Navigation Satellite System) in the heavy construction industry. On the current project Vendelbo uses his 233 Hitachi 320 excavator equipped with Leica iXE3 machine control for digging ditches, trenches and horizontal profiles.

“I’m 100% dependent on machine control in my daily work,” says Vendelbo. “Before the implementation of machine control, I would have a surveyor measure the area and place pegs and strings, all the while keeping a tight watch on my work. Now, I just load the file with the 3D model that I receive from Line Christensen into the machine control solution, and I can then do all the excavation alone just by following the model. If there are changes in the project, I simply delete the file and load the new version into the panel.”

For more information on companies in this article

Related Content

  • Paving control package for concrete or asphalt pavers
    April 10, 2012
    Leica Geosystems has launched v3.0 of its Leica PaveSmart 3D system, which is designed specifically for concrete and asphalt paving and milling applications. This upgraded package is now said to support a wider range of paving equipment and applications than before. PaveSmart 3D v3.0 will be available late March 2012 through Leica Geosystems’ direct sales and approved paving solution distribution channels, including GOMACO.
  • Kenya port suspension bridge project makes progress
    January 15, 2019
    A new suspension bridge in Kenya’s key port city, Mombasa, will help unlock potential – Shem Oirere reports Plans for the construction of a US$200 million suspension bridge in Kenya heva moved a notch higher. The country's urban roads agency recently announced the shortlisting of three bidders for the design, finance, construct, operate, maintain and transfer public private partnership (PPP) contract model. Kenya Urban Roads Authority (KURA) is a state agency that manages, develops, rehabilitates and mai
  • Rapid replacement of multiple bridges – the plan
    December 14, 2017
    The US State of Pennsylvania is saving itself $220 million over 10 years on a programme to replace 558 bridges with an unusual public private partnership approach - Kristina Smith writes It is called the Rapid Bridge Replacement Programme with good reason. Pennsylvania’s Department of Transport, PennDOT, wants to see no less than 558 structurally deficient bridges replaced with newly designed and constructed ones, all within four years. Using traditional forms of procurement this programme would be like
  • Advanced concrete slipforming technology coming to market
    August 1, 2019
    New concrete slipforming technology is said to offer increased performance over earlier generation equipment - Mike Woof writes