Building a car dealership with machine control

Canadian contractor MB Ford Construction recently built a massive car sales facility in Canada. Meanwhile the highly specialised site preparation job was sub-contracted to another local firm, Rabb Construction. The new Dilawri Auto Mall was a sizeable, heavy civil project on a 6ha site. Rabb needed to level and grade the site for the four car dealer elevated building pads and their surrounding inventory lots and customer parking. The contract included excavating three storm water runoff retention ponds, wh
May 21, 2018 Read time: 4 mins
Machine control technology from Topcon was used on the earthmoving machines to speed working and boost accuracy
Canadian contractor MB Ford Construction recently built a massive car sales facility in Canada. Meanwhile the highly specialised site preparation job was sub-contracted to another local firm, Rabb Construction.


The new Dilawri Auto Mall was a sizeable, heavy civil project on a 6ha site. Rabb needed to level and grade the site for the four car dealer elevated building pads and their surrounding inventory lots and customer parking. The contract included excavating three storm water runoff retention ponds, while Rabb was also responsible for constructing the sewage systems.

The project site was uneven as it was previously a quarry where blasting had been carried out in the 1970s to break out the rock, with the blasted material then being reduced to produce crushed stone. After extraction ceased, the large open pit was converted into a dump site for clean fill.  

“We were supplied a full set of design drawings, grading plans, storm water management plans and structural plans, which were completed by a team of consultants and designers,” said Brenda Burrows-Rabb, general manager of Rabb Construction. “Using this design information, we developed a 3D site model to use with our 342 Topcon GPS machine control system on our equipment. This site model is also available on our Topcon Tesla tablet data collector hand-held rover. Having field access to the site model increased our efficiency and accuracy.”

Burrows-Rabb said, “We had a fairly aggressive timetable in order to accommodate the two dealerships that were to be built as soon as we finished the site preparation. Plus, there was a commitment for the third dealership, and we needed to complete enough work on the fourth location to help the owner market it.”

The dynamic compaction process was completed first, with the stone building pad elevated 1–2m above existing grade. Once the building pads were constructed, the site was ready for the initial work to begin.

To handle the earthmoving, Rabb used four 178 Caterpillar crawler hydraulic excavators including a Cat 321D equipped with the Topcon X-53i excavator system and two dozers, a New Holland DC80 and a Cat D6R high track dozer, equipped with Topcon 3D-MC2 systems. The contractor moved 20,000-25,000m3 of material and as the site is balanced, it became a matter of relocating the fill material as per the design grades. The grade needed to match into the existing grades at all of the property lines.

“The Topcon systems helped us achieve grade on this challenging site and saved us time, which has helped us meet the tight deadlines,” Burrows-Rabb said. “The ROI on the technology was immediately obvious to us. We don’t feel a need to quantify what we already know, which is why we purchased a second unit as quickly as we did.”

Help in selecting the GPS machine control systems and with training was provided by GeoShack Canada, based in Ottawa. According to Burrows-Rabb, the operator training on the GPS controls made a difference with the confidence for using the technology. “We’ve eliminated the necessity for multiple passes and there is no need to revisit any of our work.”

The X-53i 3D control for excavators boosted the Cat 321D’s versatility. According to Burrows-Rabb, the system’s 3D positioning capabilities helped the excavator with sewer installation for bedding grade, rough grade, and “just about every task – it is very useful.”

“We knew about Topcon machine control for some time – however, it is an expensive investment,” stated Burrows-Rabb. “It became evident as we used it that it is worth the capital investment. Our efficiency has improved. For example, with the grading of the parking lot stone the D6R dozer with GPS control can be operated without foreman supervision. This frees up key personnel to complete other required work.”

For Rabb Construction achieving the correct grade according to the provided design drawings and elevations was critical, since the firm was preparing the sub-grade for the asphalt paving and concrete contractors. All quantities of crushed stone, asphalt, and concrete materials to be supplied are based on the Rabb-produced sub-grade elevation. The elevation needed to be accurate and match the city-approved grading and servicing plans.

As Burrows-Rabb reflected, “We were met with difficult site conditions and a very aggressive schedule. Certainly, having the machine control technology has helped us tremendously.”

For more information on companies in this article

Related Content

  • Innovative machine control systems for Canadian slipforming work
    November 29, 2013
    Advanced machine control technologies are speeding site layout and construction operations Canadian house building firm Mattamy Homes has brought in a contractor that has used sophisticated equipment to build the roads around its new development in Oakville, Ontario. The site is just 30 minutes drive from Toronto. Phase 1-A of the project is under construction and nearly every one of the 550 homes that will be built there has been sold already. Additional phases will bring the total number of homes to 1,800
  • Topcon machine control units take the heat off an Alaskan contractor
    December 4, 2015
    Juniper, spruce, cranberry, cottonwood and rose. Most people think of pine trees and berries amid beautiful country fields. But for one contractor based just below the Arctic Circle in the US state of Alaska, the names represent a successful job completed using machine control. Valley General Construction recently finished a US$350,000 contract for the upgrading of country roads in the local borough of Matanuska-Susitna. The colourful names belong to roads in a heavily wooded residential subdivision located
  • GPS machine control boosts road surface quality
    February 14, 2012
    The use of GPS machine control on sub-base has improved final rideability on a major highway reconstruction project. Innovative construction techniques have helped to upgrade a 9.6km stretch of the 307km long I-96 highway in the US state of Michigan. The Michigan Department of Transportation (MDOT) project was initiated in the third quarter of 2009 and was completed in the fourth quarter of 2010. Interstate Highway Construction acted as general contractor on the project, which included widening the shoulder
  • Machine control used for road revamp for Arkansas highway
    June 23, 2015
    A historic route in the US state of Arkansas has benefited from the use of machine control during its upgrade The south-west - north-east US Route 67 in Arkansas has long been a significant transport route. This old road follows the natural break between the Ozark Mountains and the Ouachita Mountains. In the 1920s, funding became available for road paving, and the route was designated US Route 67.