B2W Software has developed a sophisticated new B2W Production Targets package. According to the firm, this allows heavy construction contractors to assess job progress more accurately at any given point in time. Using B2W Production Targets, the firm says that contractors can set specific, variable targets for expected productivity according to the conditions, plan and resources for each individual day. Without this capability, daily targets are typically set by averaging projected productivity from the
August 14, 2019 Read time: 2 mins
B2W Software has developed a sophisticated new B2W Production Targets package. According to the firm, this allows heavy construction contractors to assess job progress more accurately at any given point in time.


Using B2W Production Targets, the firm says that contractors can set specific, variable targets for expected productivity according to the conditions, plan and resources for each individual day. Without this capability, daily targets are typically set by averaging projected productivity from the estimate evenly over the duration of a job or job phase. The averaged targets, however, can present a distorted impression of job progress on a given day or series of days when compared to actual production data.

For example, a contractor planning a five-day highway paving job requiring 5,000tonnes of asphalt could set differing daily targets. These would account for limited productivity based on slower shoulder or on/off ramp work over the first two days, and much higher production at the end of the week for mainline paving. The variable targets would allow a more accurate assessment of job status versus plan each day.

Relying on an average target of 1,000tonnes/day instead could present an inaccurate impression that the job was behind schedule over the first two or three days.

According to the firm, contractors are pushing for better data to make more informed decisions in the field, and having timely data on job progress offers significant benefits. Using the B2W Production Targets and electronic field logs provides this key data and allows users to make timely adjustments to keep jobs on schedule and budget.

B2W Software users can now use current versions of the B2W Schedule solution for resource scheduling and dispatching and/or the B2W Track solution for field tracking and analysis to implement B2W Production Targets. Users can set variable daily targets in electronic field logs, and B2W Track then allows them to enter actual productivity in the field for comparison to the targets in real time.

Related Content

  • Work begins on Stockholm’s new bypass
    August 22, 2016
    The first tunnels are being excavated for the huge bypass tunnel in Sweden’s capital Stockholm – Adrian Greeman writes. After years of preparation and design, blasting and rock moving for Sweden's largest infrastructure project began south of the city this year. It sets in train a decade-long project that will create a new half-ring dual three-lane motorway for the city, 20km long. With most of it deep underground, it will also be one of Europe's largest ever road tunnels. The scheme is aimed at transformin
  • Using ITS to maximise safety and traffic flow for cycling
    January 22, 2013
    Copenhagen, Denmark, has long been known as one of the world’s leading cities for cycling. In some areas of the city, the modal share of bikes has reached a level of as much as 50 %. And on some of the most frequently used bike paths the average daily number of cyclists is close to 30,000. As these numbers continue to rise, new ways of planning and implementing cycling infrastructure are needed. Increasingly, Danish traffic planners are turning to technology as a tool for planning cycling infrastructure. I
  • Intelligent paving and compaction holds the key
    October 16, 2024
    Intelligent paving and compaction holds the key to more efficient road construction according to BOMAG – Mike Woof writes
  • Trimble is developing smart construction site solutions
    March 7, 2016
    Trimble is taking the concept of the building information model (BIM) one stage further with its development of its construction continuum concept. This is intended to show the process and benefits to building a construction-ready model embedded with intelligent data. Such a model can serve as the basis for how contractors plan and execute construction projects. With intelligent modeling, users can add and remove information in real time while simultaneously looking at multiple ways to perform construction