Accurate logistics planning with B2W

B2W Software has developed a sophisticated new B2W Production Targets package. According to the firm, this allows heavy construction contractors to assess job progress more accurately at any given point in time. Using B2W Production Targets, the firm says that contractors can set specific, variable targets for expected productivity according to the conditions, plan and resources for each individual day. Without this capability, daily targets are typically set by averaging projected productivity from the
August 14, 2019 Read time: 2 mins
B2W Software has developed a sophisticated new B2W Production Targets package. According to the firm, this allows heavy construction contractors to assess job progress more accurately at any given point in time.


Using B2W Production Targets, the firm says that contractors can set specific, variable targets for expected productivity according to the conditions, plan and resources for each individual day. Without this capability, daily targets are typically set by averaging projected productivity from the estimate evenly over the duration of a job or job phase. The averaged targets, however, can present a distorted impression of job progress on a given day or series of days when compared to actual production data.

For example, a contractor planning a five-day highway paving job requiring 5,000tonnes of asphalt could set differing daily targets. These would account for limited productivity based on slower shoulder or on/off ramp work over the first two days, and much higher production at the end of the week for mainline paving. The variable targets would allow a more accurate assessment of job status versus plan each day.

Relying on an average target of 1,000tonnes/day instead could present an inaccurate impression that the job was behind schedule over the first two or three days.

According to the firm, contractors are pushing for better data to make more informed decisions in the field, and having timely data on job progress offers significant benefits. Using the B2W Production Targets and electronic field logs provides this key data and allows users to make timely adjustments to keep jobs on schedule and budget.

B2W Software users can now use current versions of the B2W Schedule solution for resource scheduling and dispatching and/or the B2W Track solution for field tracking and analysis to implement B2W Production Targets. Users can set variable daily targets in electronic field logs, and B2W Track then allows them to enter actual productivity in the field for comparison to the targets in real time.

Related Content

  • Innovations in aggregate production
    February 20, 2012
    Innovations abound in the aggregate production sector - Mike Woof reports. With road construction accounting for a significant percentage of aggregate production, developments in this industry are of major importance for the highway sector. Technical advances in aggregate production methods have pushed technological boundaries, resulting in cost/tonne reductions for products and improving operating efficiency for major producers.
  • Upgrading a busy A road link in the UK
    July 4, 2018
    The upgrade to the UK’s busy A14 route will address a significant traffic bottleneck - Mike Woof writes The UK is suffering badly from traffic congestion, a problem that is particularly severe in and around its major cities. Lack of investment in road construction over many years has resulted in a major backlog of work, while the country has seen growing vehicle numbers. To make matters worse, there have been few additions to the major road network since the late 1980s and early 1990s. And the combinatio
  • Skanska’s sophisticated satellite system saves fuel
    April 23, 2013
    Satellite vehicle tracking technology from Isotrak is helping Skanska UK’s utilities business save on fuel and be kinder to the environment by reducing emissions. Using the real time system to track the company’s mobile workforce on the road enables efficient vehicle management and provides detailed reporting on individual driving styles for each driver. This is said to have enabled Skanska UK, a leading utility infrastructure and asset management provider, covering telecommunications, gas, power and water
  • Gritty decisions need Smart Modelling
    April 11, 2022
    Mark Fisher, principal strategic consultant with Amey Consulting, explains how its data-led Smart Winter modelling improved a UK local government’s winter gritting efficiency by 18%.