Accurate logistics planning with B2W

B2W Software has developed a sophisticated new B2W Production Targets package. According to the firm, this allows heavy construction contractors to assess job progress more accurately at any given point in time. Using B2W Production Targets, the firm says that contractors can set specific, variable targets for expected productivity according to the conditions, plan and resources for each individual day. Without this capability, daily targets are typically set by averaging projected productivity from the
August 14, 2019 Read time: 2 mins
B2W Software has developed a sophisticated new B2W Production Targets package. According to the firm, this allows heavy construction contractors to assess job progress more accurately at any given point in time.


Using B2W Production Targets, the firm says that contractors can set specific, variable targets for expected productivity according to the conditions, plan and resources for each individual day. Without this capability, daily targets are typically set by averaging projected productivity from the estimate evenly over the duration of a job or job phase. The averaged targets, however, can present a distorted impression of job progress on a given day or series of days when compared to actual production data.

For example, a contractor planning a five-day highway paving job requiring 5,000tonnes of asphalt could set differing daily targets. These would account for limited productivity based on slower shoulder or on/off ramp work over the first two days, and much higher production at the end of the week for mainline paving. The variable targets would allow a more accurate assessment of job status versus plan each day.

Relying on an average target of 1,000tonnes/day instead could present an inaccurate impression that the job was behind schedule over the first two or three days.

According to the firm, contractors are pushing for better data to make more informed decisions in the field, and having timely data on job progress offers significant benefits. Using the B2W Production Targets and electronic field logs provides this key data and allows users to make timely adjustments to keep jobs on schedule and budget.

B2W Software users can now use current versions of the B2W Schedule solution for resource scheduling and dispatching and/or the B2W Track solution for field tracking and analysis to implement B2W Production Targets. Users can set variable daily targets in electronic field logs, and B2W Track then allows them to enter actual productivity in the field for comparison to the targets in real time.

Related Content

  • Digital solutions for accurate road construction
    November 19, 2021
    Construction firms are now delivering roads that are more durable and feature better surface quality due to the use of digital measurement solutions. These technologies help to transfer target values into precise actual values on the ground
  • Machine control technology round table discussion with Leica Geosystems, Topcon and Trimble
    January 4, 2022
    In this, the first in a series of top-level roundtable discussions led by World Highways, editor Mike Woof and editorial director Geoff Hadwick talk machine control technology with three world-class experts from Leica Geosystems, part of Hexagon, Topcon and Trimble. Find out what these key opinion leaders are thinking on six vitally important topics. Let them help you stay ahead of the game.
  • David Barwell suggests six steps for closing the UK funding gap
    January 11, 2019
    Six steps for closing the UK funding gap Plenty of private money is seeking UK investment opportunities. The government and the infrastructure sector in general must make projects more attractive, writes David Barwell* It is widely acknowledged that the UK faces mounting economic, environmental and social problems if the nation's infrastructure fails to meet present and future demands. Government estimates propose that almost €561 billion is required to bridge the infrastructure funding gap. As part o
  • A vision of roads
    September 3, 2012
    By 2040 European roads could be built differently, and hopefully be safer, according to the EU research programme NR2C