Runway rebuild for Detroit airport

A US contractor has employed equipment from Guntert & Zimmerman to help carry out a runway rebuild at Detroit Metro Airport The busy airport handles around 30 million passengers/year and the project had to be carried out in a tight timeframe as a result, with the paving crew working 16 hours/day to meet the schedule. Ajax Construction has been using its G&Z S850 paver for the work, which was needed as the existing concrete surface on runway 4L/22R had suffered from an alkali silica reaction (ASR). The
January 25, 2017 Read time: 2 mins
Equipment from G&Z has been used to rebuild a runway suffering from alkali silica reaction
A US contractor has employed equipment from 225 Guntert & Zimmerman to help carry out a runway rebuild at Detroit Metro Airport

The busy airport handles around 30 million passengers/year and the project had to be carried out in a tight timeframe as a result, with the paving crew working 16 hours/day to meet the schedule.

Ajax Construction has been using its G&Z S850 paver for the work, which was needed as the existing concrete surface on runway 4L/22R had suffered from an alkali silica reaction (ASR). The 3km long by 46m wide runway had to be replaced, using a total of 170,438m3 of PCC concrete. The 457mm of crushed aggregate base for the concrete runway was retained however as the base for the new concrete surface. The paver was used along with texture cure equipment from 218 GOMACO and Guntert & Zimmerman for the project as well as 2122 Trimble stringless machine control technology, so as to ensure the surface would meet the tight specifications of the runway project.

The runway was closed for the work and the old concrete was milled out to a depth of 432mm, along with 75mm of the 228m bituminous base underneath, leaving the 457mm crushed aggregate base untouched. Paving was carried out in multiple passes to a width of 5.7m, with 510mm dowel bars also being used. The project also called for full depth reclamation of the asphalt shoulders and their aggregate base structures, and their replacement with new layers. New 127mm deep asphalt shoulders were constructed on top of 228mm aggregate base structures on either side of the runway, along with underdrain improvements to optimise water removal after heavy rain showers.

Other work included installing new, high efficiency LED runway lighting for the resurfaced runway as well as new markings and security fencing.

There is still a portion of the work for the airport to be carried out in 2017 and this will involve additional paving for some taxiways and parking areas.

For more information on companies in this article

Related Content

  • Advances in concrete paving materials
    July 9, 2012
    Innovations in materials technology, as well as machines, could provide a major boost to the concrete paving sector - Mike Woof reports Development of new material technologies for the concrete paving sector continues apace and the latest innovations could provide the biggest boost for this market in many years. High performance cementitious material (HPCM) is an innovative concept that has been developed and tested for road surfacing applications as part of a project in which the UK's Transport Research La
  • Concrete runway surface for Indonesian airport
    May 14, 2020
    The new Yogyakarta International Airport in Indonesia is seeing the benefit of a high-quality runway surface. The runway was built quickly and efficiently to a high standard, using the latest equipment. In all, 11 slipform pavers from Wirtgen played a key role in the airport’s construction.
  • Developments in the concrete pavers market
    February 20, 2012
    The market for concrete pavers continues to fuel research and development into new models writes Mike Woof. The range and breadth of concrete slipforming and paving equipment on the market continues to grow as firms develop new and improved models. Prior to the recent CONEXPO-CON/AGG 2011 construction equipment show in Las Vegas, some of the best known manufacturers had already announced their new and improved slipforming machines. GOMACO, Guntert & Zimmermann, Power Curbers and Wirtgen all had recent or ne
  • Ammann plant assists in Indian airport rebuilding
    October 2, 2020