Property issues holding back start of work on Gordie Howe Bridge

Delays in buying properties in Detroit, Michigan, could hold up construction of the proposed 3.2km Gordie Howe International Bridge that will link the US city to Windsor in Canada. A report by the Detroit Free press said that around 30 of the estimated 900 parcels of land in the city’s Delray district could pose potential problems if owners resist selling the sites to the bridge’s developers. The newspaper noted that Dwight Duncan, interim chair of the Windsor-Detroit Bridge Authority - the Canadian e
July 19, 2016 Read time: 4 mins
Delays in buying properties in Detroit, Michigan, could hold up construction of the proposed 3.2km Gordie Howe International Bridge that will link the US city to Windsor in Canada.

A report by the Detroit Free press said that around 30 of the estimated 900 parcels of land in the city’s Delray district could pose potential problems if owners resist selling the sites to the bridge’s developers.

The newspaper noted that Dwight Duncan, interim chair of the Windsor-Detroit Bridge Authority - the Canadian entity managing the project - said about 20 of 30 parcels belong to businessman Manuel (Matty) Moroun, owner of the 2.3km Ambassador Bridge that already spans the Detroit River.

The new bridge will have access roads to two major Interstate highways to bypass the centres of Detroit and the new Herb Gray Parkway out of Windsor in the Canadian province of Ontario. But Moroun, owns a large trucking yard which would be needed for the new bridge’s approaches in Detroit.

“The 30 that we are concerned about are not adverse at this time,” Duncan said. “They could become adverse. We are subject to United States law. Any landowner if there becomes an adverse relationship has certain rights. We’re quite confident that eventually we will have all the properties we need, but we have to respect the law.”

Mourun has been actively trying to stop construction of a new crossing which could siphon away commercial vehicle from the 2.3km suspension bridge of four undivided lanes. The Ambassador was opened in 1929 and bought in 1979 by US trucking businessman Moroun. It is managed through his Detroit International Bridge Company in the US and the Canadian Transit Company subsidiary in Canada.

The Detroit Free Press said that delays in getting all the parcels needed in hand has held up release of the bridge authority’s Request for Proposals – RFP, a detailed bid document that will go out to three international teams of contractors, engineers and architects.

The three teams are Legacy Link Partners, Bridging North America and CanAm Gateway.

2482 SNC Lavalin is heading up Legacy Link that includes French firm 4084 Vinci Concessions, 1021 American Bridge Company and Windsor-based Amico Infrastructure. Bridging North America includes 917 ACS Infrastructure Canada, 6343 Fluor Canada and 4761 Dragados Canada and DBI Services to handle maintenance and repairs of the Herb Gray Parkway. CanAm Gateway is led by Canadian construction company EllisDon and major global player 4138 Bechtel Canada.

The bridge authority said it had planned to issue the RFP at the end of 2015, but this has yet to be done, although Duncan remains upbeat. “We’re ready to go with the RFP. We intend to release it shortly,” he said.

“However because of the properties on both sides not being in our possession we’re going to wait a little bit longer before we release the RFP to make sure we are able to manage the risk associated if in fact we don’t get the properties in a timely enough fashion for when they’re needed for construction.”

The three finalists will need several months to respond to the RFP, meaning completion might slip back to 2021 at the earliest, according to the newspaper.

Meanwhile, Canadian contractors have been doing site preparation, such as building the access road. Duncan said the Canadian government, which is paying upfront for nearly all the costs of the more than US$2 billion project, has spent $600 million this year on it compared to about $100 million last year and only $8 million the year before.

The bridge is named after a professional ice hockey player who for years played with the Detroit Red Wings in the continent’s National Hockey League, the NHL.

For more information on companies in this article

Related Content

  • HxGN Live 2014: Hexagon CEO lays out firm’s machine control vision
    June 5, 2014
    Hexagon CEO and president Ola Rollén has outlined the company and its global brand network’s vision for the future of mining and construction machine control. Speaking during a Hexagon media luncheon Q&A during the four-day HxGN Live 2014 conference being staged at the MGM Grand Hotel in Las Vegas, Rollén emphasised the strength of Hexagon’s Mining Division which currently consists of Leica Geosystems surveying equipment; SAFEmine mine safety and collision avoidance systems; Devex and Leica Geosystems Minin
  • Kosovan highway ahead of schedule
    April 25, 2012
    In Kosovo, work is pushing ahead of schedule on the Route 7 highway to link capital Pristina with the Albanian border. Sections of the 120km highway have been opened, one year ahead of schedule. An official opening of several sections of the highway has been carried out by Kosovan leaders, including Prime Minister Hashim Thaçi, President Atifete Jahjaga, and members of Parliament, along with Albanian Prime Minister Sali Berisha and US representatives Eliot Engel (D- NY) and Gary Peters (D-MI) joined thousan
  • Innovative projects at IRF Awards luncheon
    February 22, 2013
    Since the launch of the IRF Global Road Achievement Awards (GRAA) program in 2000, our main objective has been to showcase innovation and leadership in the global road industry,” noted IRF president & CEO Patrick Sankey, as he opened the luncheon. “We are extremely proud our Awards Program has become an industry reference for innovators across the globe.” IRF Chairman Abdullah Al-Mogbel offered his congratulations to the award winners, noting, “…the award winners provide an inspiring example of the ingenuit
  • Dragados among six in the running for fourth Panama bridge deal
    August 23, 2016
    All six consortia that submitted documents in May to design and build a fourth bridge over the Panama Canal have pre-qualified, according to media reports. The companies officially vying for the estimated US$1 billion contract are: • Dragados • Consorcio CCB: Constructora Norberto Odebrecht, Odebrecht Engenharia e Construcao International • Consorcio Hyundai, Sacyr JV • Consorcio Astaldi – Daelim • Consorcio Panamá Cuarto Puente: China Communications Contruction Company, China Harbour Engi