Kosovan highway ahead of schedule

In Kosovo, work is pushing ahead of schedule on the Route 7 highway to link capital Pristina with the Albanian border. Sections of the 120km highway have been opened, one year ahead of schedule. An official opening of several sections of the highway has been carried out by Kosovan leaders, including Prime Minister Hashim Thaçi, President Atifete Jahjaga, and members of Parliament, along with Albanian Prime Minister Sali Berisha and US representatives Eliot Engel (D- NY) and Gary Peters (D-MI) joined thousan
April 25, 2012 Read time: 3 mins
RSSIn Kosovo, work is pushing ahead of schedule on the Route 7 highway to link capital Pristina with the Albanian border. Sections of the 120km highway have been opened, one year ahead of schedule. An official opening of several sections of the highway has been carried out by Kosovan leaders, including Prime Minister Hashim Thaçi, President Atifete Jahjaga, and members of Parliament, along with Albanian Prime Minister Sali Berisha and US representatives Eliot Engel (D- NY) and Gary Peters (D-MI) joined thousands of Kosovans to celebrate at an opening ceremony.

The project is being carried out by US/Turkish joint venture partners 4138 Bechtel and 5252 Enka, with construction having commenced in the second quarter of 2010. Funding for the project has come from the Kosovan Government itself and route optimisation work by Bechtel-Enka managed to avoid the need for boring twin tube tunnels to the south east of Pristina. Instead the main Route 7 highway joins with the M9 dual carriageway to the south west of the city, which was built recently by a local contractor. This modified route reduced construction costs for the Route 7 project considerably, a major factor in Bechtel-Enka winning the contract.

"These first 38km represent the new reality of a new country, Kosovo”, said prime minister Hashim Thaçi.

The newly-opened route runs 38km between Morinë, at the border with Albania, and an area north of Suhareka. Upon completion, the full motorway will extend to the north of Kosovo’s capital, Pristina and will serve as the centerpiece of Kosovo’s national transport system, helping to promote trade and economic development in Kosovo and throughout the region.

”We are committed to helping Kosovo to build its country and economy: 70% of the workforce on the project has been local Kosovans. Some 80 local contractors and hundreds of local suppliers have worked on the project”, said Mike Adams, president of Bechtel’s civil infrastructure unit. “We would like to thank the Kosovan government for an excellent working relationship, which has helped us to complete the first part of the motorway within budget and a year ahead of schedule.”

Construction started on the Kosovo motorway in April 2010. Bechtel and Enka’s optimum alignment solution avoided the requirement to build the twin tube tunnel, resulting in significant cost savings for the government. Together, Bechtel and Enka have successfully delivered several major infrastructure projects in the region including highways in Albania, Croatia, and Turkey. Enka chairman Sinan Tara added, “We’re delighted to be working on such a prestigious project. The motorway will be a key pillar in the development of the transportation infrastructure for Kosovo, providing access to international markets.” The motorway is scheduled for completion in 2013.

For more information on companies in this article

Related Content

  • Breakthrough for Slovenian Karavanke Tunnel
    April 2, 2024
    The existing tunnel Karavanke Tunnel tube between Austria and Slovenia opened in 1991.
  • Serbia’s pan-European Corridor X is in the slow lane
    October 23, 2017
    It’s been slow progress on Serbia’s Corridor X project. Gordon Feller reports. Back in the early 2000’s, the European Union undertook an ambitious programme to link the main cities of its south-eastern region. This involved connecting five key seaports – the Greek cities of Patras, Igoumenitsa, Piraeus and Thessaloniki as well as Romania’s Black Sea city of Constanta. Initially the plan involved two motorways across Greece. The first was a new 780km route including a branch to Ormenio on Greece’s north-eas
  • Serbia highway projects moving ahead
    September 30, 2016
    Progress is being seen in Serbia with regard to some of the country’s key highway projects. The Ljig-Preljina stretch of the Corridor 11 highway will open for traffic at the end of October 2016. The highway route will be tolled but these will not be implemented until the start of 2017. Plans are also moving ahead for the ring road project for the capital, Belgrade. Meanwhile talks are being held with the European Investment Bank (EIB) over the new highway link to run from Nis, through Merdare and over the b
  • Cowi appointed advisor for Bar-Boljare highway in Montenegro
    November 16, 2017
    Consulting engineer Cowi has been appointed adviser on bridge and tunnel work for the Smokovac-Uvac-Matesevo section of the 170km Bar-Boljare highway in Montenegro. The Smokovac-Uvac-Matesevo section is a priority project for the Bar-Boljare highway project that will eventually run north to south from Montenegro's main sea port of Bar to the Serbian border. Cowi was awarded the work from main project contractor China Road and Bridge Corporation.