Topcon machine control units take the heat off an Alaskan contractor

Juniper, spruce, cranberry, cottonwood and rose. Most people think of pine trees and berries amid beautiful country fields. But for one contractor based just below the Arctic Circle in the US state of Alaska, the names represent a successful job completed using machine control. Valley General Construction recently finished a US$350,000 contract for the upgrading of country roads in the local borough of Matanuska-Susitna. The colourful names belong to roads in a heavily wooded residential subdivision located
December 4, 2015 Read time: 4 mins
Machine control systems helped boost project quality in Alaska
Juniper, spruce, cranberry, cottonwood and rose. Most people think of pine trees and berries amid beautiful country fields. But for one contractor based just below the Arctic Circle in the US state of Alaska, the names represent a successful job completed using machine control

Valley General Construction recently finished a US$350,000 contract for the upgrading of country roads in the local borough of Matanuska-Susitna. The colourful names belong to roads in a heavily wooded residential subdivision located in the borough, not far from the town of Palmer, population about 6,500.

Valley is a medium-to-small size contractor – up to eight employees – based in Palmer. Local roadwork and commercial projects are the bulk of the business but the company also works at times in Anchorage, only about 70km away and – with a population of about 300,000 –is the state’s largest city.

In 2014, the Matanuska-Susitna Borough decided on a two-year plan to upgrade the subdivision’s dirt roads that are laid out in a grid pattern, roughly square and with a total length of 1.5km. The objective for year one is to raise the embedded dirt roads to grade and then let them “winter over” – settle down – so that in year two they can be paved.

“Since the roads are embedded below grade, there have been major drainage problems,” stated Brian Hooks, project manager and co-owner of Valley General Construction. “We needed to bring the road not only up to grade but also build in a culvert to address the water run off.”

The borough’s engineers produced CAD drawings showing the 3.6m-wide roads, culverts almost a metre wide and the cut-ins for 50 driveway approaches.

“I took the engineers’ drawings and used 342 Topcon MAGNET Office Site to create a site model and files that could control the excavator and dozer we used on the project,” said Hooks.

But Hooks first needed to upgrade an older and limited machine control system so he consulted GPS Alaska, based in Anchorage, and received additional training and help to select a robust system for the company’s 178 Caterpillar dozer. Valley General purchased the Topcon 3D-MC2 machine control designed to access all satellites and provide position updates up to 100 times per second.

The 3D-MC2 sensor combines a gyro, compass and inertial sensor to measure the X, Y and Z positions as well as the roll, pitch, yaw and acceleration of the dozer. The Topcon system connects to both GPS and GLONASS satellites.

Additionally, Valley purchased a Topcon X62 excavator grade control system for its 233 Hitachi ZX210-6 hydraulic excavator that has an operating weight of 21,900kg and a bucket force of 158kN. The project was also the first job where Valley had used machine control technology on an excavator.

The embedded roads were already several inches below grade. Excavation brought each road to a uniform 10 inches below grade before lifts of fill soil, crushed stone and a binder-layer of reclaimed asphalt pavement – RAP – were added.

Once completed, the roads will winter over until next spring. Alaskan winters are long so the borough wants to adjust the roads after the several freeze-thaw cycles that can occur during a winter season before a finished asphalt surface is paved.

The subdivision project required about 3,060m3 of fill dirt and nearly 6,120m3 of #5 crushed stone. Additionally, 76m of culvert pipe was laid down. “We completed in two weeks,” said Hooks. “Our accuracy is spot on, so we’ve eliminated wasted time with rework.”

Without machine control technology, the job would have taken twice as long and had more risks of delays.

Hooks said Valley’s machine operators can literally go out on to the job and know, by looking at their monitors, what needs to be done. “The project is stake-less, so we don’t need surveyors or have delays when a stake is run over. Plus, we also eliminated the need for a worker to walk along with the excavator for spotting and checks,” he said.

“We’ve been using the technology for so long, it’s hard to imagine running a project without it. If someone took it away, people would walk out the door…probably following me, it’s that important.”

For more information on companies in this article

Related Content

  • HxGN Live 2014: Hexagon CEO lays out firm’s machine control vision
    June 5, 2014
    Hexagon CEO and president Ola Rollén has outlined the company and its global brand network’s vision for the future of mining and construction machine control. Speaking during a Hexagon media luncheon Q&A during the four-day HxGN Live 2014 conference being staged at the MGM Grand Hotel in Las Vegas, Rollén emphasised the strength of Hexagon’s Mining Division which currently consists of Leica Geosystems surveying equipment; SAFEmine mine safety and collision avoidance systems; Devex and Leica Geosystems Minin
  • Concrete paving a smoother surface using machine control technology
    May 17, 2017
    Innovative technology has been used to deliver a smooth concrete road surface on a busy stretch of highway in Nebraska. Much-needed work on a busy section of Interstate 80 has been carried out in Nebraska to improve the road surface. This is one of the most important highways in the US, providing a link that stretches right across the country between the east and west coasts. This busy highway carries a high percentage of heavy truck traffic as it is a vital transport route. However this constant flow of la
  • Sophisticated machine control for slipforming
    March 10, 2021
    The use of 3D stringless controls in large concrete paving work is very well established. However, the lower cost of these systems means that the technology is now being used widely for smaller slipforming works, such as kerbing or drain construction
  • Roadtec machines deliver Alaska runway rebuild
    January 26, 2017
    A challenging airport runway project in Alaska has been carried out with the help of Roadtec construction equipment equipped with Topcon machine control systems. Anchorage-based Knik Construction carried out the work at the airport in Yakutat, located in the southeast corner of Alaska. Bounded by the Gulf of Alaska to the South, mountains to the North, and coastal glaciers to the East and West, Yakutat is remote even for Alaska. There are no roads leading in or out and all commerce and access is by air o