Rebuilding a critical transportation artery in Italy

Software from Bentley Systems has played an important role in the Morandi Bridge replacement project
September 7, 2020 Read time: 3 mins
Photo Credit: Bentley Systems

In August 2018, a 210m section of the Morandi Bridge in Genoa Italy suddenly collapsed. Although the cause was never officially determined, corrosion had affected the bridge’s structure. Italferr was selected to design an emergency replacement for the 1,182m viaduct over the Polcevera River which is part of a key roadway that links Italy and France and is a main access point to a nearby airport. Consequently, rebuilding it as quickly as possible was critical for the city’s long-term economic and cultural health—and construction would need to begin as the design progressed.

Morandi Bridge Photo Credit: Bentley Systems
Image Credit: Bentley Systems

Italferr faced the challenge of completing the design of the €202 million project in only three months—extraordinarily fast for a project of this size and complexity. It also had to create a simple design while incorporating new Italian safety standards for the cross-section of the deck and the curvature radii of the junctions and entrances. Lastly, the project team needed to design and build the bridge on the same footprint as the previous one, with reinforced concrete piers positioned 50-100m apart. Each of these piers has been designed with a continuous cross-section for their entire height.

It was determined that the main deck should feature a continuous 1,067m girder with 14 50m and three 100m steel-concrete spans. The Polcevera Viaduct (now known as the Viaduct San Giorgio) would also include one 41m steel-concrete span approaching the west shoulder, one 26m steel-concrete span approaching the east shoulder, and a 110m steel-concrete ramp with three spans connected structurally to the deck. Various important technological features needed to be incorporated throughout the structure, including dehumidifiers and a solar generation plant, to enhance the bridge’s aesthetics, ensure road traffic safety, improve energy efficiency, and maximise durability.

Morandi Bridge ​Photo Credit: Bentley Systems
Image Credit: Bentley Systems

To ensure the accuracy of the design while staying on schedule, Italferr used Bentley’s BIM methodology and created a digital twin of the viaduct to streamline workflows throughout the design phase. “While we were completing our design, the construction team was starting to demolish and build piles and foundations,” said Stefano Casula, structural engineer and BIM expert with Italferr. “We had to catch any mistakes and interferences as soon as possible.” To achieve this goal, Italferr incorporated detailed information for construction and operation into the model, as there was little time to significantly alter the model after the design phase. The organisation also established an open, connected data environment based on Bentley software to promote collaboration among the multidiscipline project team and ensure a single source of truth.

Image Credit: Bentley Systems
Image Credit: Bentley Systems

Leveraging BIM and creating a digital workflow with Bentley applications allowed Italferr to visualise the design with a much higher degree of quality and speed than traditional 2D designs. Because of Italferr’s work with 4Dvisualisation, the completed bridge will increase the flow of goods and services in and out of Genoa compared to the previous design. Though the collapse caused nearly two years of economic disruption, Italferr’s work has helped to restore the important transitway, and sets up the city for continued cultural and economic growth.

Read more about this project here.


Sponsored content produced in association with Bentley Systems

For more information on companies in this article

Related Content

  • Italy’s Morandi Bridge collapses killing at least 35
    August 15, 2018
    Investigators and rescuers in the northern Italian city of Genoa are scouring the wreckage of a cable stayed motorway bridge that collapsed, killing at least 35 people. A tower collapsed and then a 209m section – the longest - plummeted to the river and train tracks below at around 11:30 during heavy rain, media sources said. One truck driver managed to stop only metres from the edge of the missing section of bridge. "It was just after 11:30 when we saw lightning strike the bridge," an eyewitness was quote
  • The Lessons of the Genoa bridge collapse
    April 23, 2019
    The partial collapse of the Polcevera viaduct, better known as the Morandi Bridge, has prompted debate regarding the technical and administrative aspects of maintaining road infrastructures. We discussed it with the engineer Gabriele Camomilla, former Director of Research and Maintenance of the Società Autostrade, who coordinated the only major structural intervention performed on the bridge, carried out in the early 1990s
  • New generator power systems
    August 10, 2022
    New power generation systems are now coming to market that offer lower emissions and cleaner options for customers. Engine technology has improved enormously in recent years, with exhaust emissions from industrial diesels having been reduced significantly. Meanwhile, manufacturers have also introduced new systems that can further reduce emissions while retaining output and performance.
  • Piling productively with Soilmec
    November 27, 2020
    A project in Frankfurt, Germany has benefited from the use of a piling rig supplied by Soilmec. The SR-125 HIT unit has been employed in an application requiring it to drive segmental casing in challenging site conditions.