Mallorca airport runway upgrade with machine control

The latest machine control technology has played an important role in an airport runway upgrade for Mallorca. The Spanish island has long been a major tourist destination and its airport has been struggling to cope with demand, handling around 26 million passengers in 2016. Palma de Mallorca Airport is the third largest airport in Spain and during the peak summer holiday period, the massive influx of tourists makes it one of the busiest airports in Europe.
April 13, 2017 Read time: 3 mins
Two Wirtgen milling machines operating together were controlled by one system from Leica Geosystems
The latest machine control technology has played an important role in an airport runway upgrade for Malloca.


The Spanish island has long been a major tourist destination and its airport has been struggling to cope with demand, handling around 26 million passengers in 2016. Palma de Mallorca Airport is the third largest airport in Spain and during the peak summer holiday period, the massive influx of tourists makes it one of the busiest airports in Europe.

In November 2016, upgrade work for the airport’s southern runway commenced. The work has been carried out by a consortium called UTE Regeneración Pista Sur, which comprises the contractors MAB Obras Públicas and CONELSAN.

The consortium partners were given a specific task to carry out, correcting the slope of the runway and exchanging the horizontal and vertical runway signals. Because of the specialised nature of the milling job, this portion of the work was subcontracted to Iber Samop, which employed a PaveSmart 3D system from 265 Leica Geosystems on its mobile machines to deliver the necessary finish.

The milling job was carried out by a 2395 Wirtgen 200i milling machine, equipped with a PaveSmart 3D solution. In addition, the firm also had a second Wirtgen W2000 with a conventional levelling system. The 3D-controlled height of the first lane was used to provide the height reference for side plate height control of the next lane. The result was a no-slope-error propagation across lanes, while the side plate sensing delivered accurate joint-matching for the asphalt paving phase of the project. This ensured better quality asphalt joints and the set-up proved to be a cost-efficient use of two milling machines, operating with a single machine control solution.

Working in two shifts 24 hours/day, Iber Samop was able to use its equipment package to mill the 3km-long x 60m-wide runway in just seven days. The Leica PaveSmart 3D was used to measure the machine position and adjust the milling depth and cross-slope automatically. The benefit of the 3D milling solution is that it eliminates human error, while also provide a safer work environment and provides an accurate and uniform surface for a new asphalt pavement. In this way it helps to minimise costs of the new asphalt mix and eliminates the copying effect and long waves.


According to Iber Samop, this high rate of productivity could not be achieved without the use of up to date machine control equipment to guide the milling machines and deliver better quality results.

To meet the CS-ADR-DSN regulation covering the runways would have been difficult using conventional methods and systems. Iber Samop pointed out that with a profile milling job, the layer thickness can vary continuously. This can range from 10mm to 50mm just a few seconds later, according to the design. However, the firm said that the required evenness can be achieved by using the latest machine control technology to deliver an automated work process. The manual work process would require a surveyor in front of the machine at all times who would be busy measuring and marking the target milling thickness on the ground. But by using a machine control solution for milling, the human error in the conventional process can be eliminated and also allow for a safer working environment.

The work was carried out during a period of low air traffic volumes for the airport, so as to minimise delays for passengers. And with the runway now upgraded, Mallorca’s airport should be able to handle the 10% increase in passengers anticipated.

For more information on companies in this article

Related Content

  • Road repairs fuel demand for milling machines
    February 13, 2012
    A need for road repairs is fuelling demand for new milling machines, Mike Woof reports. With many roads in Europe and North America needing repairs, manufacturers continue to meet demand by offering improved compact milling machines, as well as full-sized planers. The versatile and manoeuvrable compact machines can play a useful role in on-site recycling jobs for urban road improvements while the larger mills can be vital for in-situ recycling work.
  • Asphalt paving is seeing innovative new technology
    April 4, 2013
    With new machines coming to market, the asphalt paving sector is seeing an array of sophisticated technology now available
  • Mobile plant provides asphalt answer at airport
    September 30, 2013
    The project to upgrade Kassel-Calden Airport in Germany is providing a much improved facility. Opened in 1970, the original airport had a short runway that was not suited to predicted traffic volumes and current standards so a complete reconstruction of the facility has been carried out. The €271 million investment in the facility is expected by the developers to provide a strong economic benefit to the area. The original airport was built on an area of over 200ha and a new and longer runway has been con
  • Reduced emissions, costs, with recycled asphalt
    February 21, 2012
    Recycling is a key issue for asphalt road construction, with many technologies now coming to market. Bith an ever increasing emphasis on sustainability forcing change in the construction sector in Europe and North America, the highway sector now has to seek new solutions.